FDOT contract T2A74 bid tabulation

SR 26 (W UNIVERSITY AVE) FROM SW 38TH ST TO GALE LEMERAND DR. Let by Florida DOT on August 26, 2026, Alachua, District 2. 3 bids received; low bid $3,511,852 by Preferred Materials Inc..

Owner
Florida DOT
Letting
26 AUG 2026
Pay items
114
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Preferred Materials Inc.$3,511,852Low
2Whitehurst, V. E. & Sons, Inc.$3,978,256+13%
3Watson Construction Company, LLC$4,432,222+26%
FDOT contract T2A74: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Preferred Materials Inc.2. Whitehurst, V. E. & Sons, Inc.3. Watson Construction Company, LLC
0005Mobilization (0101-1)LS1$261,814$517,600$300,000
0010Maintenance of traffic (0102-1)DA1$209,254$421,279$200,000
0015Pedestrian or bicycle special detour (0102-4-1)SY1$5,932.71$55,725$51,000
0020Pedestrian escort/flagger (0102-5)HR2,880$45.65$40.00$35.00
0025Traffic control officer (0102-14)HR368$100.00$125.00$110.00
0030Work zone sign (0102-60)ED18,690$0.19$0.24$0.25
0035Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED94,892$0.09$0.16$0.15
0040Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD11,972$0.05$0.06$0.08
0045Arrow board / advance warning arrow panel (0102-76)ED1,080$5.00$5.40$7.00
0050Temporary raised/retroreflective pavement marker, type B (0102-78-2)EACH1,159$5.00$5.65$6.50
0055Portable changeable message sign, temporary (0102-99)ED578$9.00$15.05$12.00
0060Temporary signalization and maintenance, intersection (0102-104)ED1,350$38.62$16.15$17.25
0065Temporary traffic detection and maintenance, intersection (0102-107-1)ED1,350$57.93$26.90$28.75
0070Type III barricade (0102-115)ED800$0.23$0.50$0.40
0075Removable tape, white, solid 6" (0102-913-21)GM0.03$17,813$26,875$40,000
0080Removable tape, white, 10'-30', 6'-10', or 2'-4' skip, 6" wide (0102-913-22)GM0.02$4,866.67$21,500$40,000
0085Removable tape, white, 12" crosswalk (0102-913-24)LF67$3.00$21.50$50.00
0090Inlet protection system (0104-18)EACH76$267.19$125.00$250.00
0095Litter removal (0107-1)ACRE91.74$150.00$268.75$125.00
0100Mowing (0107-2)ACRE72.62$150.00$268.75$125.00
0105Monitor existing structures- vibration monitoring (0108-2)LS1$15,000$2,625.00$15,000
0110Clearing & grubbing (0110-1-1)ACRE1$25,385$5,000.00$35,000
0115Clearing & grubbing (0110-1-1)ACRE1$3,000.00$12,850$35,000
0120Removal of existing concrete (0110-4-10)SY961$35.50$38.20$65.00
0125Milling existing asphalt pavement, 2" avg depth (0327-70-5)SY59,986$2.99$3.20$2.50
0130Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83)TN6,596.60$196.43$164.65$160.00
0135Manhole, adjust (0425-5)EACH11$1,260.00$1,355.00$2,400.00
0140Manhole, adjust, utilities (0425-5-1)EACH26$1,260.00$1,355.00$2,250.00
0145Valve boxes, adjust (0425-6)EACH16$1,260.00$1,355.00$1,500.00
0150Pedestrian/ bicycle railing, aluminum only,42" type 1 (0515-2311)LF44$90.00$96.75$175.00
0155Concrete curb & gutter, type F (0520-1-10)LF919$38.50$41.40$78.00
0160Concrete sidewalk and driveways, 4" thick (0522-1)SY509$47.50$51.10$120.00
0165Concrete sidewalk and driveways, 6" thick (0522-2)SY342$72.50$78.00$145.00
0170Detectable warnings (0527-2)SF703$35.50$38.20$45.00
0175Performance turf, sod (0570-1-2)SY346$7.25$5.50$22.00
0180Painted pavement markings, standard, white, solid, 6" (0710-11101)GM3.17$1,600.00$1,990.00$2,640.00
0185Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102)GM0.07$1,800.00$2,150.00$8,000.00
0190Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123)LF5,480$2.40$2.15$2.70
0195Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124)LF55$2.45$2.70$4.00
0200Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125)LF653$2.60$3.25$5.25
0205Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131)GM1.47$900.00$967.50$2,640.00
0210Painted pavement marking, standard,white, 3'-9' skip drop line and approach to toll 12" wide, (0710-11133)GM0.02$1,400.00$1,345.00$10,000
0215Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141)GM1.37$900.00$1,345.00$2,640.00
0220Painted pavement markings, standard, white, message or symbol (0710-11160)EACH6$85.00$86.00$300.00
0225Painted pavement markings, standard, white, arrows (0710-11170)EACH54$45.00$48.50$75.00
0230Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM3.32$1,600.00$1,990.00$2,640.00
0235Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224)LF228$2.45$2.70$4.00
0240Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241)GM0.16$900.00$1,345.00$2,640.00
0245Initial contingency amount, DO not bid (0999-25)LS1$40,025$40,025$40,025
0250Initial contingency amount, DO not bid (0999-25)LS1$9,975.50$9,975.50$9,975.50
0255Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH46$460.00$495.00$1,091.00
0260Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112)EACH3$2,000.00$2,150.00$700.00
0265Single column ground sign assembly, relocate (0700-1500)EACH11$175.00$190.00$175.00
0270Single column ground sign assembly, remove (0700-1600)EACH4$50.00$53.75$50.00
0275Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101)EACH2$170.00$185.00$550.00
0280Sign panel, remove, UP to 12 SF (0700-3601)EACH1$35.00$38.00$50.00
0285Retroreflective sign strip- furnish and install, 5' (0700-13-15)EACH14$45.00$48.50$125.00
0290Object marker, type 1 (0705-10-1)EACH9$250.00$270.00$150.00
0295Raised pavement marker, type B (0706-1-3)EACH1,159$5.00$5.65$6.50
0300Painted pavement markings, surface (0710-90)LS1$35,394$43,000$51,074
0305Thermoplastic, standard, solid, 8" for interchange and urban island (0711-11102)GM0.07$5,500.00$10,045$8,200.00
0310Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF5,728$3.50$4.75$5.00
0315Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124)LF55$4.20$6.25$8.00
0320Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF776$6.00$7.90$9.60
0325Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM1.37$1,750.00$2,822.00$7,920.00
0330Thermoplastic, standard, message or symbol (0711-11160)EACH6$150.00$170.00$550.00
0335Thermoplastic, standard, arrow (0711-11170)EACH54$65.00$113.00$400.00
0340Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF228$4.20$6.25$8.00
0345Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.16$1,700.00$2,825.00$7,920.00
0350Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF2,359$14.00$17.00$10.00
0355Thermoplastic, preformed, white, 2-4 dotted guideline on concrete surfaces (0711-14141)GM0.05$15,000$6,210.00$90,000
0360Thermoplastic, preformed, white, message (0711-14160)EACH56$150.00$226.00$550.00
0365Thermoplastic, preformed, white, arrow (0711-14170)EACH56$125.00$113.00$450.00
0370Thermoplastic, preformed, black, 2-4 dotted guideline on concrete surfaces (0711-14341)GM0.05$15,000$6,210.00$80,000
0375Thermoplastic, preformed, white with black contrast, arrow on concrete surface (0711-14570)EACH1$350.00$565.00$950.00
0380Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM3.17$4,600.00$5,760.00$7,920.00
0385Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM1.47$1,500.00$1,806.00$7,920.00
0390Thermoplastic, standard-other surfaces white, skip, 12"- approach to toll plaza or 3-9 lane drop (0711-16133)GM0.02$9,000.00$3,470.00$25,000
0395Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM3.32$4,200.00$5,760.00$7,920.00
0400Thermoplastic, remove existing thermoplastic pavement markings- surface to remain (0711-17-1)SF63$12.00$5.95$9,000.00
0405Permanent tape, white, solid W/contrast, 6" primary line width, for concrete surfaces (0713-103121)GM0.03$36,000$67,725$100,000
0410Permanent tape, white, 3-9 dotted, 12" wide, for concrete surfaces (0713-103173)GM0.02$30,000$28,220$90,000
0415Permanent tape, white, 10-30 6" wide, for concrete surfaces (0713-103181)GM0.03$16,000$16,935$90,000
0420Permanent tape, yellow, solid, for concrete bridges (0713-103201)GM0.07$36,000$50,795$90,000
0425Permanent tape, black, 3-9 dotted, 12" wide, for concrete surfaces (0713-103373)GM0.02$32,000$28,220$115,000
0430Permanent tape, black, 10-30 6" wide, for concrete surfaces (0713-103381)GM0.03$16,000$16,935$100,000
0435Preformed/permanent tape, remove (0713-107)SF323$2.25$5.95$15.00
0440Conduit, furnish & install, open trench (0630-2-11)LF171$18.19$24.15$18.50
0445Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH6$730.33$1,825.00$1,545.00
0450Itsfm subsurface documentation- project length (0611-1-1)MI2.03$4,088.30$3,785.00$4,050.00
0455Itsfm location documentation- intersection (0611-2-1)EACH5$2,880.00$2,660.00$2,846.25
0460Conduit, furnish & install, open trench (0630-2-11)LF180$22.54$24.15$26.00
0465Conduit, furnish & install, directional bore (0630-2-12)LF309$50.89$51.10$55.00
0470Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI3$3,581.33$13,765$14,725
0475Signal cable- repair/replace/other, furnish & install (0632-7-2)LF90$5.83$18.95$21.00
0480Fiber optic cable locator (0633-6)DA270$72.42$171.50$184.00
0485Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH17$730.24$1,825.00$1,951.00
0490Electrical power service, F&I, underground, meter by contractor (0639-1122)AS3$5,824.00$3,690.00$4,000.00
0495Electrical service wire, & install (0639-2-1)LF234$10.38$14.85$16.00
0500Aluminum signals pole, (0646-1-11)EACH4$4,159.50$1,662.00$1,800.00
0505Aluminum signals pole, furnish install pedestrian detector post (0646-1-12)EACH3$2,646.00$1,405.00$1,600.00
0510Steel mast arm assembly, and install, single arm 50' (0649-21-6)EACH1$80,791$92,855$99,400
0515Steel mast arm assembly, and install, single arm 60' (0649-21-10)EACH2$78,464$97,201$103,983
0520Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS6$840.17$1,322.00$1,415.00
0525Midblock crosswalk: hybrid beacon assembly, & install complete assembly (0654-3-10)AS12$2,423.67$2,010.00$2,151.00
0530Loop assembly, F&I, type F (0660-2106)AS26$1,930.15$1,720.00$1,840.00
0535Pedestrian detector, furnish & install, standard (0665-1-11)EACH7$592.71$380.00$407.00
0540Pedestrian detector, remove- pole/pedestal to remain (0665-1-60)EACH1$262.00$26.90$29.00
0545Traffic controller assembly, F&I, NEMA W/standard lock (0670-5160)AS3$43,626$57,905$61,945
0550Traffic controller, modify (0671-2-40)EACH5$1,955.40$3,650.00$3,906.00
0555Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201)EACH6$1,005.50$1,202.00$1,286.00
0560Sign panel, remove, UP to 12 SF (0700-3601)EACH2$262.00$75.25$100.00
0565Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22)EACH6$4,821.83$5,418.00$5,796.00
0570Enhanced highway sign AC powered, F&I overhead blank out sign <12 SF (0700-141360)EACH1$8,492.00$8,215.00$8,788.00
FDOT contract T2A74: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of August 26, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy