FDOT contract T3942 bid tabulation
SR 8 (I-10) FROM W OF SR 81 TO CHOCTAWHATCHEE RIVER BRIDGE. Let by Florida DOT on March 26, 2025, Holmes, District 3. 3 bids received; low bid $10,713,495 by C.W. Roberts Contracting, Inc..
- Owner
- Florida DOT
- Letting
- 26 MAR 2025
- Pay items
- 90
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | C.W. Roberts Contracting, Inc. | $10,713,495 | Low |
| 2 | American Sand & X-Cavation, Inc. DBA American Sand & Asphalt | $12,160,048 | +14% |
| 3 | Anderson Columbia Co., Inc. | $12,465,017 | +16% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. C.W. Roberts Contracting, Inc. | 2. American Sand & X-Cavation, Inc. DBA American Sand & Asphalt | 3. Anderson Columbia Co., Inc. |
|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $530,000 | $300,000 | $895,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $255,000 | $250,000 | $449,320 |
| 0015 | Traffic control officer (0102-14) | HR | 2,000 | $82.00 | $45.00 | $103.23 |
| 0020 | Work zone sign (0102-60) | ED | 17,914 | $0.25 | $0.50 | $0.29 |
| 0025 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 98,698 | $0.16 | $0.24 | $0.17 |
| 0030 | Arrow board / advance warning arrow panel (0102-76) | ED | 280 | $5.45 | $9.60 | $5.74 |
| 0035 | Portable changeable message sign, temporary (0102-99) | ED | 2,181 | $19.00 | $20.00 | $19.50 |
| 0040 | Portable regulatory, sign (0102-150-1) | ED | 560 | $5.45 | $6.00 | $5.74 |
| 0045 | Radar speed display unit (0102-150-2) | ED | 560 | $5.45 | $6.00 | $5.74 |
| 0050 | Sediment barrier (0104-10-3) | LF | 5,275 | $4.45 | $4.50 | $3.15 |
| 0055 | Inlet protection system (0104-18) | EACH | 16 | $450.00 | $200.00 | $367.55 |
| 0060 | Litter removal (0107-1) | ACRE | 4,558.83 | $49.15 | $60.00 | $57.36 |
| 0065 | Mowing (0107-2) | ACRE | 4,558.83 | $38.25 | $60.00 | $45.89 |
| 0070 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $23,000 | $30,000 | $78,738 |
| 0075 | Removal of existing concrete (0110-4-10) | SY | 570 | $13.00 | $22.00 | $64.22 |
| 0080 | Tree root and branch pruning (0110-22) | EACH | 4 | $450.00 | $2,500.00 | $2,365.69 |
| 0085 | Regular excavation (0120-1) | CY | 979.80 | $15.45 | $19.00 | $76.89 |
| 0090 | Borrow excavation, truck measure (0120-2-2) | CY | 1,206.20 | $30.10 | $23.00 | $40.50 |
| 0095 | Subsoil excavation (0120-4) | CY | 290 | $21.00 | $40.00 | $25.21 |
| 0100 | Type B stabilization (0160-4) | SY | 4,062 | $9.75 | $7.00 | $7.95 |
| 0105 | Optional base, base group 04 (0285-704) | SY | 4,240 | $22.00 | $26.00 | $24.45 |
| 0110 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 159,647 | $2.00 | $2.55 | $4.99 |
| 0115 | Milling existing asphalt pavement, 2 1/4" avg depth (0327-70-11) | SY | 253,015 | $1.50 | $1.75 | $3.10 |
| 0120 | Milling existing asphalt pavement, 3 3/4" avg depth (0327-70-20) | SY | 419 | $1.50 | $5.75 | $28.92 |
| 0125 | Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53) | TN | 7,723 | $133.00 | $155.00 | $145.74 |
| 0130 | Superpave asphaltic concrete, traffic E, PG76-22 (0334-1-55) | TN | 22,621.40 | $141.40 | $155.00 | $132.67 |
| 0135 | Asphalt concrete friction course, inc bit, FC-5, PG 76-22 (0337-7-25) | TN | 9,908.30 | $178.50 | $195.00 | $170.76 |
| 0140 | Asphalt concrete friction course,traffic B, FC-12.5, PG (0337-7-81) | TN | 624 | $170.00 | $165.00 | $156.08 |
| 0145 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 3,167.70 | $160.35 | $165.00 | $148.06 |
| 0150 | Miscellaneous asphalt (0339-1) | TN | 77.90 | $390.00 | $250.00 | $459.68 |
| 0155 | Inlets, gutter, type S, <10' (0425-1701) | EACH | 6 | $5,900.00 | $25,000 | $12,205 |
| 0160 | Pipe culvert optional material, round, 15", gutter drain (0430-173115) | LF | 24 | $480.00 | $85.00 | $316.82 |
| 0165 | Polymer nosing for bridge expansion joint (0458-2) | CF | 12 | $1,540.00 | $2,500.00 | $1,720.50 |
| 0170 | Shoulder gutter- concrete (0520-6) | LF | 1,220 | $58.00 | $40.00 | $96.35 |
| 0175 | Concrete traffic railing- retrofit-post & beam railing (0521-5-11) | EACH | 8 | $17,500 | $900.00 | $28,633 |
| 0180 | Guardrail -roadway, general (0536-1-1) | LF | 2,221 | $26.20 | $54.00 | $27.53 |
| 0185 | Guardrail transition to rigid barrier, F&I- index 536- 002, approach TL-3 (0536-8122) | EACH | 8 | $3,820.00 | $6,600.00 | $4,014.51 |
| 0190 | Guardrail removal (0536-73) | LF | 2,216 | $2.20 | $6.00 | $2.29 |
| 0195 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 8 | $3,300.00 | $6,000.00 | $3,441.01 |
| 0200 | Performance turf, sod (0570-1-2) | SY | 50,521 | $3.30 | $5.00 | $3.84 |
| 0205 | Raised pavement marker, type B (0706-1-3) | EACH | 6,970 | $5.45 | $6.00 | $5.74 |
| 0210 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 40.44 | $1,300.00 | $1,740.00 | $1,376.41 |
| 0215 | Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102) | GM | 1.53 | $1,400.00 | $1,920.00 | $1,514.05 |
| 0220 | Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124) | LF | 1,619 | $0.80 | $1.43 | $0.86 |
| 0225 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 16 | $2.75 | $2.56 | $2.87 |
| 0230 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 49.50 | $980.00 | $1,189.68 | $1,032.31 |
| 0235 | Painted pavement markings, standard, white, message or symbol (0710-11160) | EACH | 2 | $27.00 | $47.81 | $28.68 |
| 0240 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 17 | $27.00 | $45.25 | $28.68 |
| 0245 | Painted pavement markings, standard, white, yield line (0710-11180) | LF | 31 | $3.30 | $6.20 | $3.44 |
| 0250 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 38.20 | $1,200.00 | $1,740.00 | $1,261.70 |
| 0255 | Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224) | LF | 18 | $1.10 | $2.45 | $1.15 |
| 0260 | Work zone collision detection and avoidance system for operations (0924-102) | LS | 1 | $80,000 | $175,000 | $90,011 |
| 0265 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $149,630 | $149,630 | $149,630 |
| 0270 | Ground-in rumble strips, 16" (0546-72-1) | GM | 31.58 | $2,200.00 | $2,981.19 | $1,873.03 |
| 0275 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 6 | $55.00 | $250.00 | $143.38 |
| 0280 | Raised pavement marker, type B (0706-1-3) | EACH | 3,265 | $5.45 | $6.00 | $5.74 |
| 0285 | Painted pavement markings, surface (0710-90) | LS | 1 | $85,000 | $102,000 | $89,667 |
| 0290 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 1,641 | $5.45 | $5.09 | $5.74 |
| 0295 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 16 | $8.75 | $6.41 | $9.18 |
| 0300 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 2 | $140.00 | $251.77 | $143.38 |
| 0305 | Thermoplastic, standard, arrow (0711-11170) | EACH | 17 | $140.00 | $96.00 | $143.38 |
| 0310 | Thermoplastic, standard, yield line (0711-11180) | LF | 31 | $11.00 | $24.00 | $8.03 |
| 0315 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 18 | $8.75 | $5.59 | $9.18 |
| 0320 | Thermoplastic, standard, blue, solid,6" (0711-11421) | LF | 93 | $3.30 | $12.00 | $3.44 |
| 0325 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 2 | $600.00 | $1,440.00 | $516.15 |
| 0330 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 20.22 | $5,950.00 | $6,000.00 | $6,079.13 |
| 0335 | Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102) | GM | 0.76 | $6,100.00 | $8,160.00 | $6,308.53 |
| 0340 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 16.50 | $2,600.00 | $3,000.00 | $2,695.46 |
| 0345 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 19.10 | $5,900.00 | $6,000.00 | $6,079.13 |
| 0350 | Integrated multi-polymer pavement markings, white, solid 6" (0918-712100) | GM | 1.18 | $11,000 | $54,000 | $10,323 |
| 0355 | Integrated multi-polymer pavement markings, yellow, solid 6" (0918-712110) | GM | 1.18 | $11,000 | $54,000 | $10,323 |
| 0360 | Integrated multi-polymer pavement markings, white, 10-30 skip 6" (0918-712120) | GM | 0.99 | $6,000.00 | $24,000 | $5,161.53 |
| 0365 | Integrated multi-polymer pavement markings, white, 3-9 dotted 6" (0918-712121) | GM | 0.06 | $5,600.00 | $14,400 | $5,161.53 |
| 0370 | Integrated multi-polymer pavement markings, black, 10-30 skip 6" (0918-712130) | GM | 0.97 | $6,000.00 | $24,000 | $5,161.53 |
| 0375 | Integrated multi-polymer pavement markings, black, 3-9 dotted 6" (0918-712131) | GM | 0.06 | $5,600.00 | $14,400 | $5,161.53 |
| 0380 | Conduit, furnish & install, open trench (0630-2-11) | LF | 513 | $16.00 | $30.00 | $17.21 |
| 0385 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 370 | $44.00 | $48.00 | $45.89 |
| 0390 | Conduit, furnish & install, aboveground (0630-2-14) | LF | 120 | $22.00 | $48.00 | $22.94 |
| 0395 | Fiber optic cable locator (0633-6) | DA | 375 | $110.00 | $564.00 | $114.70 |
| 0400 | Multi-conductor cable, furnish & install, cat 6 (0633-8-11) | LF | 1,853 | $4.35 | $7.20 | $4.59 |
| 0405 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 4 | $1,700.00 | $2,400.00 | $1,783.60 |
| 0410 | Junction box, furnish & install, mounted (0635-3-12) | EACH | 4 | $1,600.00 | $1,140.00 | $1,720.50 |
| 0415 | Electrical service wire, & install (0639-2-1) | LF | 1,043 | $5.45 | $9.60 | $5.74 |
| 0420 | Vehicle detection system- wireless magnetometer, cabinet equipment (0660-5-61) | EACH | 2 | $660.00 | $1,200.00 | $688.21 |
| 0425 | Vehicle detection system- wireless magnetometer, above ground equipment (0660-5-62) | EACH | 2 | $270.00 | $1,200.00 | $286.75 |
| 0430 | Vehicle detection system- wireless magnetometer, in-road unit (0660-5-63) | EACH | 28 | $330.00 | $420.00 | $344.10 |
| 0435 | Vehicle detection system- parking detection system, furnish & install, sensor- camera (0660-12-11) | EACH | 4 | $24,000 | $42,000 | $25,234 |
| 0440 | Managed field ethernet switch, furnish & install (0684-1-1) | EACH | 1 | $4,900.00 | $6,600.00 | $5,161.53 |
| 0445 | Managed field ethernet switch, remove- cabinet to remain (0684-1-6) | EACH | 1 | $110.00 | $240.00 | $114.70 |
| 0450 | Network device, ethernet repeater (0684-90100) | EACH | 4 | $2,700.00 | $1,320.00 | $2,867.51 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of March 26, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way