FDOT contract T3969 bid tabulation
SR 20 FROM SR 75 (US 231) TO CALHOUN CO LINE. Let by Florida DOT on December 3, 2025, Bay, District 3. 5 bids received; low bid $1,393,732 by Roberts and Roberts, Inc..
- Owner
- Florida DOT
- Letting
- 03 DEC 2025
- Pay items
- 71
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Roberts and Roberts, Inc. | $1,393,732 | Low |
| 2 | C.W. Roberts Contracting, Inc. | $1,599,589 | +15% |
| 3 | Pigott Asphalt and Sitework LLC | $1,685,798 | +21% |
| 4 | Anderson Columbia Co., Inc. | $1,696,493 | +22% |
| 5 | American Sand & X-Cavation, Inc. DBA American Sand & Asphalt Paving | $2,012,181 | +44% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Roberts and Roberts, Inc. | 2. C.W. Roberts Contracting, Inc. | 3. Pigott Asphalt and Sitework LLC | 4. Anderson Columbia Co., Inc. | 5. American Sand & X-Cavation, Inc. DBA American Sand & Asphalt Paving |
|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $60,000 | $61,728 | $86,500 | $154,872 | $225,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $30,000 | $48,731 | $69,500 | $123,774 | $175,000 |
| 0015 | Commercial material for temporary driveway maintenance (0102-3) | CY | 29.70 | $116.00 | $370.96 | $100.00 | $35.00 | $100.00 |
| 0020 | Traffic control officer (0102-14) | HR | 12 | $65.00 | $128.47 | $300.00 | $89.71 | $90.00 |
| 0025 | Work zone sign (0102-60) | ED | 7,382 | $1.20 | $1.03 | $0.30 | $1.12 | $0.28 |
| 0030 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 50,124 | $0.10 | $0.05 | $0.01 | $0.05 | $0.17 |
| 0035 | Arrow board / advance warning arrow panel (0102-76) | ED | 100 | $5.80 | $5.14 | $1.00 | $5.61 | $13.20 |
| 0040 | Portable changeable message sign, temporary (0102-99) | ED | 1,016 | $14.40 | $12.85 | $1.00 | $11.22 | $30.80 |
| 0045 | Temporary signalization and maintenance, intersection (0102-104) | ED | 170 | $13.80 | $12.33 | $1.00 | $11.22 | $22.00 |
| 0050 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 170 | $13.80 | $12.33 | $1.00 | $11.22 | $22.00 |
| 0055 | Type III barricade (0102-115) | ED | 12 | $0.30 | $0.26 | $1.00 | $0.28 | $5.50 |
| 0060 | Temporary raised rumble per day, includes all sets and relocations (0102-909) | DA | 140 | $30.00 | $30.83 | $5.00 | $1.12 | $50.00 |
| 0065 | Sediment barrier (0104-10-3) | LF | 120 | $5.60 | $15.36 | $12.50 | $1.96 | $10.00 |
| 0070 | Floating turbidity barrier (0104-11) | LF | 46 | $20.00 | $22.78 | $30.00 | $11.22 | $20.00 |
| 0075 | Staked turbidity barrier- nylon reinforced PVC (0104-12) | LF | 52 | $20.20 | $28.57 | $30.00 | $8.41 | $20.00 |
| 0080 | Litter removal (0107-1) | ACRE | 109.48 | $86.30 | $77.08 | $10.00 | $84.12 | $85.00 |
| 0085 | Mowing (0107-2) | ACRE | 93.15 | $86.30 | $77.08 | $10.00 | $84.12 | $85.00 |
| 0090 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $20,000 | $16,871 | $10,000 | $31,383 | $40,000 |
| 0095 | Borrow excavation, truck measure (0120-2-2) | CY | 8.70 | $25.00 | $55.98 | $300.00 | $139.78 | $100.00 |
| 0100 | Regular excavation (3-R projects only) (0120-71) | LS | 1 | $6,000.00 | $10,092 | $5,000.00 | $15,440 | $13,680 |
| 0105 | Type B stabilization (0160-4) | SY | 867 | $9.00 | $12.89 | $5.00 | $13.83 | $18.00 |
| 0110 | Optional base, base group 06 (0285-706) | SY | 704 | $25.00 | $20.06 | $7.50 | $21.97 | $48.00 |
| 0115 | Turnout base- optional materials (0286-1) | SY | 401 | $35.00 | $27.22 | $30.00 | $21.51 | $105.00 |
| 0120 | Milling existing asphalt pavement, 2" avg depth (0327-70-5) | SY | 33,176 | $2.50 | $2.28 | $2.00 | $1.18 | $2.75 |
| 0125 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 15,142 | $2.50 | $3.42 | $2.00 | $3.43 | $2.50 |
| 0130 | Milling existing asphalt pavement, 1 1/4" avg depth (0327-70-12) | SY | 125 | $2.50 | $17.70 | $3.00 | $30.87 | $125.00 |
| 0135 | Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53) | TN | 23.80 | $150.00 | $298.95 | $200.00 | $619.98 | $200.00 |
| 0140 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 5,054.30 | $122.00 | $136.05 | $169.00 | $134.33 | $138.00 |
| 0145 | Miscellaneous asphalt (0339-1) | TN | 9 | $200.00 | $518.44 | $400.00 | $1,601.76 | $350.00 |
| 0150 | Pipe culvert, optional material, round, 18"SD (0430-174118) | LF | 80 | $115.00 | $87.94 | $165.00 | $118.09 | $123.21 |
| 0155 | Mitered end section, optional round, 18" SD (0430-984125) | EACH | 4 | $1,525.00 | $2,188.72 | $2,500.00 | $2,610.27 | $1,400.00 |
| 0160 | Guardrail -roadway, general (0536-1-1) | LF | 100 | $34.50 | $30.83 | $1.00 | $44.86 | $44.40 |
| 0165 | Guardrail removal (0536-73) | LF | 100 | $5.80 | $5.14 | $1.00 | $11.22 | $20.00 |
| 0170 | Performance turf, sod (0570-1-2) | SY | 6,696 | $4.40 | $2.83 | $4.00 | $3.93 | $5.50 |
| 0175 | Performance turf, sod and shoulder treatment index (0570-1-3) | SY | 32 | $20.10 | $20.90 | $12.00 | $3.93 | $5.50 |
| 0180 | Raised pavement marker, type B (0706-1-3) | EACH | 459 | $5.80 | $5.40 | $5.50 | $6.17 | $5.50 |
| 0185 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 0.29 | $2,915.30 | $2,735.91 | $2,500.00 | $2,242.88 | $2,750.00 |
| 0190 | Painted pavement markings, standard, yellow, skip, 6" (0710-11231) | GM | 2.25 | $2,298.00 | $2,156.62 | $2,000.00 | $1,121.45 | $2,200.00 |
| 0195 | Single component injection (0906-173100) | GA | 692 | $191.50 | $369.15 | $216.76 | $128.97 | $150.00 |
| 0200 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $45,423 | $45,423 | $45,423 | $45,423 | $45,423 |
| 0205 | Raised rumble strip set- permanent (0546-71-1) | EACH | 4 | $1,092.50 | $1,025.31 | $1,050.00 | $616.79 | $1,054.50 |
| 0210 | Ground-in rumble strips, 8" sinusoidal (0546-72-3) | GM | 6.84 | $1,495.00 | $1,403.87 | $1,800.00 | $2,808.79 | $1,992.02 |
| 0215 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 11 | $575.00 | $513.87 | $600.00 | $560.72 | $649.00 |
| 0220 | Single column ground sign assembly, relocate (0700-1500) | EACH | 1 | $102.20 | $91.26 | $250.00 | $99.58 | $71.50 |
| 0225 | Single column ground sign assembly, remove (0700-1600) | EACH | 2 | $40.30 | $35.97 | $100.00 | $61.68 | $50.00 |
| 0230 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 2 | $86.30 | $77.08 | $150.00 | $84.10 | $83.00 |
| 0235 | Object marker, type 1 (0705-10-1) | EACH | 24 | $258.80 | $231.24 | $300.00 | $252.32 | $357.50 |
| 0240 | Raised pavement marker, type B (0706-1-3) | EACH | 459 | $5.80 | $5.40 | $5.50 | $6.17 | $5.50 |
| 0245 | Painted pavement markings, standard, yellow, island nose (0710-11290) | SF | 26 | $3.50 | $3.24 | $5.00 | $5.61 | $3.30 |
| 0250 | Painted pavement markings, surface (0710-90) | LS | 1 | $10,925 | $10,253 | $12,500 | $13,457 | $10,450 |
| 0255 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 313 | $6.40 | $5.94 | $5.65 | $5.61 | $6.05 |
| 0260 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 269 | $7.50 | $7.02 | $7.00 | $7.85 | $7.15 |
| 0265 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 2 | $287.50 | $269.82 | $250.00 | $168.22 | $275.00 |
| 0270 | Thermoplastic, standard, blue, solid,6" (0711-11421) | LF | 41 | $4.60 | $3.40 | $5.00 | $5.61 | $3.46 |
| 0275 | Thermoplastic, preformed, 6" white, railroad dynamic envelope (0711-14191) | LF | 22 | $7.20 | $6.75 | $7.50 | $5.61 | $6.87 |
| 0280 | Thermoplastic, preformed, 12" white on asphalt pavement, railroad dynamic envelope (0711-14193) | LF | 158 | $11.50 | $10.79 | $12.00 | $11.22 | $11.00 |
| 0285 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 4.71 | $5,865.00 | $5,508.95 | $5,300.00 | $5,999.73 | $5,622.10 |
| 0290 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 0.29 | $5,692.50 | $5,417.10 | $5,000.00 | $5,999.73 | $4,950.00 |
| 0295 | Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231) | GM | 2.25 | $2,240.60 | $2,102.70 | $2,000.00 | $3,196.12 | $2,164.50 |
| 0300 | Permanent tape, white, solid, 6" for concrete bridges (0713-103101) | GM | 0.05 | $37,375 | $35,792 | $50,000 | $39,251 | $35,750 |
| 0305 | Permanent tape, yellow, 10-30 skip, 6" wide, for concrete surfaces (0713-103281) | GM | 0.03 | $20,700 | $19,427 | $25,000 | $11,214 | $16,500 |
| 0310 | Mobilization (0101-1) | LS | 1 | $2,300.00 | $3,083.25 | $5,000.00 | $21,868 | $25,000 |
| 0315 | Maintenance of traffic (0102-1) | DA | 1 | $9,200.00 | $8,833.93 | $5,000.00 | $5,137.09 | $35,000 |
| 0320 | Conduit, furnish & install, open trench (0630-2-11) | LF | 1,321 | $13.80 | $14.39 | $22.00 | $16.82 | $24.20 |
| 0325 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 520 | $43.70 | $39.05 | $50.00 | $50.47 | $49.50 |
| 0330 | Signal cable- repair/replace/other, furnish & install (0632-7-2) | LF | 1,671 | $3.50 | $3.08 | $6.00 | $11.22 | $6.60 |
| 0335 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 12 | $920.00 | $822.20 | $1,800.00 | $1,345.73 | $1,870.00 |
| 0340 | Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- flexible required (0650-2109) | EACH | 9 | $316.30 | $282.63 | $1,000.00 | $751.36 | $825.00 |
| 0345 | Loop assembly- F&I, type A (0660-2101) | AS | 1 | $1,265.00 | $1,130.52 | $2,500.00 | $5,607.23 | $2,200.00 |
| 0350 | Enhanced highway sign solar powered, F&I ground mount, W/beacon, 12-20 SF of static sign panels (0700-142112) | EACH | 4 | $8,505.40 | $7,601.23 | $15,000 | $16,822 | $15,950 |
| 0355 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $4,577.37 | $4,577.37 | $4,577.37 | $4,577.37 | $4,577.37 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of December 3, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.