FDOT contract T3969 bid tabulation

SR 20 FROM SR 75 (US 231) TO CALHOUN CO LINE. Let by Florida DOT on December 3, 2025, Bay, District 3. 5 bids received; low bid $1,393,732 by Roberts and Roberts, Inc..

Owner
Florida DOT
Letting
03 DEC 2025
Pay items
71
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Roberts and Roberts, Inc.$1,393,732Low
2C.W. Roberts Contracting, Inc.$1,599,589+15%
3Pigott Asphalt and Sitework LLC$1,685,798+21%
4Anderson Columbia Co., Inc.$1,696,493+22%
5American Sand & X-Cavation, Inc. DBA American Sand & Asphalt Paving$2,012,181+44%
FDOT contract T3969: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Roberts and Roberts, Inc.2. C.W. Roberts Contracting, Inc.3. Pigott Asphalt and Sitework LLC4. Anderson Columbia Co., Inc.5. American Sand & X-Cavation, Inc. DBA American Sand & Asphalt Paving
0005Mobilization (0101-1)LS1$60,000$61,728$86,500$154,872$225,000
0010Maintenance of traffic (0102-1)DA1$30,000$48,731$69,500$123,774$175,000
0015Commercial material for temporary driveway maintenance (0102-3)CY29.70$116.00$370.96$100.00$35.00$100.00
0020Traffic control officer (0102-14)HR12$65.00$128.47$300.00$89.71$90.00
0025Work zone sign (0102-60)ED7,382$1.20$1.03$0.30$1.12$0.28
0030Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED50,124$0.10$0.05$0.01$0.05$0.17
0035Arrow board / advance warning arrow panel (0102-76)ED100$5.80$5.14$1.00$5.61$13.20
0040Portable changeable message sign, temporary (0102-99)ED1,016$14.40$12.85$1.00$11.22$30.80
0045Temporary signalization and maintenance, intersection (0102-104)ED170$13.80$12.33$1.00$11.22$22.00
0050Temporary traffic detection and maintenance, intersection (0102-107-1)ED170$13.80$12.33$1.00$11.22$22.00
0055Type III barricade (0102-115)ED12$0.30$0.26$1.00$0.28$5.50
0060Temporary raised rumble per day, includes all sets and relocations (0102-909)DA140$30.00$30.83$5.00$1.12$50.00
0065Sediment barrier (0104-10-3)LF120$5.60$15.36$12.50$1.96$10.00
0070Floating turbidity barrier (0104-11)LF46$20.00$22.78$30.00$11.22$20.00
0075Staked turbidity barrier- nylon reinforced PVC (0104-12)LF52$20.20$28.57$30.00$8.41$20.00
0080Litter removal (0107-1)ACRE109.48$86.30$77.08$10.00$84.12$85.00
0085Mowing (0107-2)ACRE93.15$86.30$77.08$10.00$84.12$85.00
0090Clearing & grubbing (0110-1-1)ACRE1$20,000$16,871$10,000$31,383$40,000
0095Borrow excavation, truck measure (0120-2-2)CY8.70$25.00$55.98$300.00$139.78$100.00
0100Regular excavation (3-R projects only) (0120-71)LS1$6,000.00$10,092$5,000.00$15,440$13,680
0105Type B stabilization (0160-4)SY867$9.00$12.89$5.00$13.83$18.00
0110Optional base, base group 06 (0285-706)SY704$25.00$20.06$7.50$21.97$48.00
0115Turnout base- optional materials (0286-1)SY401$35.00$27.22$30.00$21.51$105.00
0120Milling existing asphalt pavement, 2" avg depth (0327-70-5)SY33,176$2.50$2.28$2.00$1.18$2.75
0125Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY15,142$2.50$3.42$2.00$3.43$2.50
0130Milling existing asphalt pavement, 1 1/4" avg depth (0327-70-12)SY125$2.50$17.70$3.00$30.87$125.00
0135Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53)TN23.80$150.00$298.95$200.00$619.98$200.00
0140Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83)TN5,054.30$122.00$136.05$169.00$134.33$138.00
0145Miscellaneous asphalt (0339-1)TN9$200.00$518.44$400.00$1,601.76$350.00
0150Pipe culvert, optional material, round, 18"SD (0430-174118)LF80$115.00$87.94$165.00$118.09$123.21
0155Mitered end section, optional round, 18" SD (0430-984125)EACH4$1,525.00$2,188.72$2,500.00$2,610.27$1,400.00
0160Guardrail -roadway, general (0536-1-1)LF100$34.50$30.83$1.00$44.86$44.40
0165Guardrail removal (0536-73)LF100$5.80$5.14$1.00$11.22$20.00
0170Performance turf, sod (0570-1-2)SY6,696$4.40$2.83$4.00$3.93$5.50
0175Performance turf, sod and shoulder treatment index (0570-1-3)SY32$20.10$20.90$12.00$3.93$5.50
0180Raised pavement marker, type B (0706-1-3)EACH459$5.80$5.40$5.50$6.17$5.50
0185Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM0.29$2,915.30$2,735.91$2,500.00$2,242.88$2,750.00
0190Painted pavement markings, standard, yellow, skip, 6" (0710-11231)GM2.25$2,298.00$2,156.62$2,000.00$1,121.45$2,200.00
0195Single component injection (0906-173100)GA692$191.50$369.15$216.76$128.97$150.00
0200Initial contingency amount, DO not bid (0999-25)LS1$45,423$45,423$45,423$45,423$45,423
0205Raised rumble strip set- permanent (0546-71-1)EACH4$1,092.50$1,025.31$1,050.00$616.79$1,054.50
0210Ground-in rumble strips, 8" sinusoidal (0546-72-3)GM6.84$1,495.00$1,403.87$1,800.00$2,808.79$1,992.02
0215Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH11$575.00$513.87$600.00$560.72$649.00
0220Single column ground sign assembly, relocate (0700-1500)EACH1$102.20$91.26$250.00$99.58$71.50
0225Single column ground sign assembly, remove (0700-1600)EACH2$40.30$35.97$100.00$61.68$50.00
0230Retroreflective sign strip- furnish and install, 5' (0700-13-15)EACH2$86.30$77.08$150.00$84.10$83.00
0235Object marker, type 1 (0705-10-1)EACH24$258.80$231.24$300.00$252.32$357.50
0240Raised pavement marker, type B (0706-1-3)EACH459$5.80$5.40$5.50$6.17$5.50
0245Painted pavement markings, standard, yellow, island nose (0710-11290)SF26$3.50$3.24$5.00$5.61$3.30
0250Painted pavement markings, surface (0710-90)LS1$10,925$10,253$12,500$13,457$10,450
0255Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124)LF313$6.40$5.94$5.65$5.61$6.05
0260Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF269$7.50$7.02$7.00$7.85$7.15
0265Thermoplastic, standard, message or symbol (0711-11160)EACH2$287.50$269.82$250.00$168.22$275.00
0270Thermoplastic, standard, blue, solid,6" (0711-11421)LF41$4.60$3.40$5.00$5.61$3.46
0275Thermoplastic, preformed, 6" white, railroad dynamic envelope (0711-14191)LF22$7.20$6.75$7.50$5.61$6.87
0280Thermoplastic, preformed, 12" white on asphalt pavement, railroad dynamic envelope (0711-14193)LF158$11.50$10.79$12.00$11.22$11.00
0285Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM4.71$5,865.00$5,508.95$5,300.00$5,999.73$5,622.10
0290Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM0.29$5,692.50$5,417.10$5,000.00$5,999.73$4,950.00
0295Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231)GM2.25$2,240.60$2,102.70$2,000.00$3,196.12$2,164.50
0300Permanent tape, white, solid, 6" for concrete bridges (0713-103101)GM0.05$37,375$35,792$50,000$39,251$35,750
0305Permanent tape, yellow, 10-30 skip, 6" wide, for concrete surfaces (0713-103281)GM0.03$20,700$19,427$25,000$11,214$16,500
0310Mobilization (0101-1)LS1$2,300.00$3,083.25$5,000.00$21,868$25,000
0315Maintenance of traffic (0102-1)DA1$9,200.00$8,833.93$5,000.00$5,137.09$35,000
0320Conduit, furnish & install, open trench (0630-2-11)LF1,321$13.80$14.39$22.00$16.82$24.20
0325Conduit, furnish & install, directional bore (0630-2-12)LF520$43.70$39.05$50.00$50.47$49.50
0330Signal cable- repair/replace/other, furnish & install (0632-7-2)LF1,671$3.50$3.08$6.00$11.22$6.60
0335Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH12$920.00$822.20$1,800.00$1,345.73$1,870.00
0340Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- flexible required (0650-2109)EACH9$316.30$282.63$1,000.00$751.36$825.00
0345Loop assembly- F&I, type A (0660-2101)AS1$1,265.00$1,130.52$2,500.00$5,607.23$2,200.00
0350Enhanced highway sign solar powered, F&I ground mount, W/beacon, 12-20 SF of static sign panels (0700-142112)EACH4$8,505.40$7,601.23$15,000$16,822$15,950
0355Initial contingency amount, DO not bid (0999-25)LS1$4,577.37$4,577.37$4,577.37$4,577.37$4,577.37
FDOT contract T3969: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of December 3, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy