FDOT contract T3981 bid tabulation
CR 268 (HIGH BRIDGE RD) OVER LITTLE RIVER, BRIDGE NO 504159. Let by Florida DOT on June 10, 2026, Gadsden, District 3. 3 bids received; low bid $6,575,327 by Anderson Columbia Co., Inc..
- Owner
- Florida DOT
- Letting
- 10 JUN 2026
- Pay items
- 60
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Anderson Columbia Co., Inc. | $6,575,327 | Low |
| 2 | Murphree Bridge Corporation | $7,830,063 | +19% |
| 3 | RJ Gorman Contracting LLC | $8,953,734 | +36% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Anderson Columbia Co., Inc. | 2. Murphree Bridge Corporation | 3. RJ Gorman Contracting LLC |
|---|---|---|---|---|---|---|
| 0005 | Removal of existing structures/bridges (0110-3) | SF | 1 | $575,000 | $350,000 | $716,874 |
| 0010 | Concrete class II, approach slabs (0400-2-10) | CY | 86.50 | $840.00 | $1,100.00 | $929.74 |
| 0015 | Concrete class II, cast-in-place topping with shrinkage admixture (0400-2-47) | CY | 627.80 | $1,003.00 | $1,700.00 | $1,400.97 |
| 0020 | Concrete class IV, bridge substructure (0400-4-5) | CY | 176.90 | $1,500.00 | $2,750.00 | $2,731.23 |
| 0025 | Bridge deck grooving (0400-7-1) | SY | 2,176 | $6.50 | $5.00 | $7.41 |
| 0030 | Bridge deck planing (0400-9-1) | SY | 2,176 | $6.50 | $5.00 | $12.77 |
| 0035 | Plain neoprene bearing pads (0400-148) | CF | 28 | $1,250.00 | $1,350.00 | $1,362.37 |
| 0040 | Reinforcing steel - bridge superstructure (0415-1-4) | LB | 133,825 | $1.85 | $1.85 | $1.98 |
| 0045 | Reinforcing steel- bridge substructure (0415-1-5) | LB | 19,771 | $1.85 | $1.85 | $1.98 |
| 0050 | Reinforcing steel- approach slabs (0415-1-9) | LB | 16,355 | $1.85 | $1.85 | $1.98 |
| 0055 | Prestressed beam: florida slab beam, beam depth 18" carbon steel, width 52-54" (0450-8-32) | LF | 4,236 | $400.00 | $450.00 | $463.51 |
| 0060 | Preformed pile holes, 36" to 43" drill/punch size (0455-15-16) | LF | 1,425 | $63.00 | $205.00 | $73.99 |
| 0065 | Preformed pile holes casing, to 43" drill/punch size (0455-15-26) | LF | 1,425 | $63.00 | $80.00 | $293.97 |
| 0070 | Preformed pile holes grouting, 36" to 43" drill/punch size (0455-15-36) | LF | 1,425 | $80.00 | $130.00 | $98.68 |
| 0075 | Pile inspection, driven pile (0455-20-1) | EACH | 50 | $1,050.00 | $780.00 | $1,443.84 |
| 0080 | Prestressed concrete piling, SQ (0455-34-5) | LF | 2,037 | $225.00 | $325.00 | $364.20 |
| 0085 | Load test (dynamic), data collection and analysis (0455-137) | EACH | 50 | $1,650.00 | $2,600.00 | $3,244.84 |
| 0090 | Load test (dynamic), test (0455-137-2) | EACH | 3 | $2,700.00 | $500.00 | $2,646.44 |
| 0095 | Test piles-prestressed concrete,24" SQ (0455-143-5) | LF | 380 | $350.00 | $325.00 | $538.70 |
| 0100 | Bridge deck expansion joint, construction, F&I poured joint with backer rod (0458-1-11) | LF | 367 | $65.00 | $75.00 | $84.03 |
| 0105 | Concrete traffic railing- 36" single-slope (0521-5-13) | LF | 1,200 | $140.00 | $110.00 | $181.84 |
| 0110 | Riprap, sand-cement bags (0530-1100) | CY | 29.70 | $1,200.00 | $1,200.00 | $910.04 |
| 0115 | Riprap- rubble, bank and shore (0530-3-3) | TN | 1,510.70 | $140.00 | $120.00 | $173.89 |
| 0120 | Bedding stone (0530-74) | TN | 562.40 | $185.00 | $134.00 | $162.38 |
| 0125 | Conduit, furnish & install, embedded concrete barriers and traffic railings (0630-2-16) | LF | 3,600 | $11.00 | $14.00 | $8.62 |
| 0130 | Junction box, furnish & install, embedded (0635-3-13) | EACH | 18 | $500.00 | $1,200.00 | $610.05 |
| 0135 | Mobilization (0101-1) | LS | 1 | $601,000 | $735,426 | $879,082 |
| 0140 | Maintenance of traffic (0102-1) | DA | 1 | $10,000 | $51,000 | $13,056 |
| 0145 | Work zone sign (0102-60) | ED | 20,250 | $0.27 | $0.25 | $0.38 |
| 0150 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 10,500 | $0.11 | $0.10 | $0.15 |
| 0155 | Portable changeable message sign, temporary (0102-99) | ED | 2,625 | $11.00 | $10.00 | $15.20 |
| 0160 | Type III barricade (0102-115) | ED | 3,000 | $0.27 | $0.25 | $0.38 |
| 0165 | Sediment barrier (0104-10-3) | LF | 1,160 | $7.00 | $5.00 | $2.71 |
| 0170 | Floating turbidity barrier (0104-11) | LF | 1,290 | $15.00 | $20.00 | $15.95 |
| 0175 | Staked turbidity barrier- nylon reinforced PVC (0104-12) | LF | 495 | $18.00 | $15.00 | $12.60 |
| 0180 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $60,000 | $30,000 | $96,015 |
| 0185 | Regular excavation (0120-1) | CY | 2,214 | $12.00 | $17.00 | $20.78 |
| 0190 | Subsoil excavation (0120-4) | CY | 538.30 | $25.00 | $40.00 | $21.21 |
| 0195 | Channel excavation (0120-5) | CY | 1,158.90 | $22.00 | $24.00 | $20.75 |
| 0200 | Embankment (0120-6) | CY | 5,898.90 | $22.00 | $20.00 | $26.09 |
| 0205 | Type B stabilization (0160-4) | SY | 3,123 | $6.50 | $7.00 | $7.02 |
| 0210 | Optional base, base group 02 (0285-702) | SY | 853 | $22.00 | $20.00 | $38.69 |
| 0215 | Optional base, base group 06 (0285-706) | SY | 1,807 | $35.00 | $22.00 | $36.23 |
| 0220 | Superpave asphaltic concrete, traffic B, PG76-22 (0334-1-52) | TN | 193.10 | $225.00 | $237.50 | $379.96 |
| 0225 | Asphalt concrete friction course,traffic B, FC-12.5, PG (0337-7-81) | TN | 238.80 | $200.00 | $273.00 | $417.96 |
| 0230 | Miscellaneous asphalt (0339-1) | TN | 16.30 | $400.00 | $300.00 | $455.96 |
| 0235 | Inlets, adjacent barrier, <=10' (0425-1921) | EACH | 4 | $8,100.00 | $7,579.72 | $12,391 |
| 0240 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 82 | $270.00 | $140.67 | $155.35 |
| 0245 | Mitered end section, optional round, 18" CD (0430-982125) | EACH | 1 | $3,500.00 | $2,094.98 | $4,613.44 |
| 0250 | Shoulder concrete barrier, 38" or 44" height (0521-72-40) | LF | 64 | $825.00 | $985.00 | $564.27 |
| 0255 | Guardrail -roadway, general (0536-1-1) | LF | 358 | $22.00 | $20.00 | $59.53 |
| 0260 | Guardrail transition to rigid barrier, F&I- index 536- 001, approach TL-3 (0536-8112) | EACH | 4 | $3,800.00 | $3,500.00 | $10,418 |
| 0265 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 4 | $3,800.00 | $3,500.00 | $10,418 |
| 0270 | Performance turf, sod (0570-1-2) | SY | 6,218 | $4.00 | $4.75 | $6.84 |
| 0275 | Single column ground sign assembly, relocate (0700-1500) | EACH | 2 | $1,000.00 | $25.00 | $227.98 |
| 0280 | Profiled thermoplastic,standard- asphalt surfaces, white, (0701-18101) | GM | 0.29 | $13,750 | $12,500 | $18,998 |
| 0285 | Profiled thermoplastic,standard- asphalt surfaces, yellow, solid,6" (0701-18201) | GM | 0.29 | $13,750 | $12,500 | $18,998 |
| 0290 | Raised pavement marker, type B (0706-1-3) | EACH | 66 | $10.50 | $5.00 | $7.60 |
| 0295 | Permanent tape, white, solid, 6" for concrete bridges (0713-103101) | GM | 0.20 | $42,000 | $30,000 | $45,595 |
| 0300 | Permanent tape, yellow, solid, for concrete bridges (0713-103201) | GM | 0.20 | $42,000 | $30,000 | $45,595 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of June 10, 2026. Compiled by Mirage Metrics.