FDOT contract T3A25 bid tabulation
SR 8 (I-10) FROM MILLER BLUFF RD TO OKALOOSA COUNTY LINE. Let by Florida DOT on October 28, 2026, Santa Rosa, District 3. 3 bids received; low bid $14,321,626 by Anderson Columbia Co., Inc..
- Owner
- Florida DOT
- Letting
- 28 OCT 2026
- Pay items
- 78
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Anderson Columbia Co., Inc. | $14,321,626 | Low |
| 2 | C.W. Roberts Contracting, Inc. | $15,415,357 | +8.0% |
| 3 | Panhandle Grading & Paving, Inc. | $17,903,151 | +25% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Anderson Columbia Co., Inc. | 2. C.W. Roberts Contracting, Inc. | 3. Panhandle Grading & Paving, Inc. |
|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $578,879 | $347,500 | $667,490 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $246,568 | $251,000 | $525,000 |
| 0015 | Traffic control officer (0102-14) | HR | 4,640 | $5.72 | $71.00 | $80.00 |
| 0020 | Work zone sign (0102-60) | ED | 10,920 | $0.32 | $0.40 | $0.17 |
| 0025 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 63,496 | $0.11 | $0.15 | $0.10 |
| 0030 | Arrow board / advance warning arrow panel (0102-76) | ED | 464 | $5.42 | $7.65 | $5.50 |
| 0035 | Portable changeable message sign, temporary (0102-99) | ED | 678 | $16.25 | $19.00 | $16.50 |
| 0040 | Portable regulatory, sign (0102-150-1) | ED | 928 | $7.58 | $7.65 | $5.50 |
| 0045 | Radar speed display unit (0102-150-2) | ED | 928 | $7.58 | $7.65 | $5.50 |
| 0050 | Artificial coverings /rolled erosion control products (0104-1) | SY | 441 | $22.57 | $9.00 | $6.00 |
| 0055 | Sediment barrier (0104-10-3) | LF | 20,531 | $0.50 | $2.80 | $2.50 |
| 0060 | Inlet protection system (0104-18) | EACH | 48 | $216.66 | $220.00 | $160.00 |
| 0065 | Litter removal (0107-1) | ACRE | 2,058.16 | $5.42 | $49.00 | $49.50 |
| 0070 | Mowing (0107-2) | ACRE | 1,877.96 | $5.42 | $49.00 | $49.50 |
| 0075 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $54,229 | $63,000 | $387,420 |
| 0080 | Removal of existing concrete (0110-4-10) | SY | 123 | $5.00 | $30.00 | $65.00 |
| 0085 | Regular excavation (0120-1) | CY | 33.40 | $70.97 | $46.00 | $75.00 |
| 0090 | Borrow excavation, truck measure (0120-2-2) | CY | 326.60 | $19.32 | $13.00 | $55.00 |
| 0095 | Regular excavation (3-R projects only) (0120-71) | LS | 1 | $2,612.83 | $16,000 | $51,870 |
| 0100 | Type B stabilization (0160-4) | SY | 791 | $25.76 | $25.00 | $12.00 |
| 0105 | Optional base, base group 01 (0285-701) | SY | 495 | $39.46 | $24.00 | $38.00 |
| 0110 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 87,602 | $0.50 | $1.30 | $2.35 |
| 0115 | Milling existing asphalt pavement, 2 1/4" avg depth (0327-70-11) | SY | 83,017 | $0.50 | $1.05 | $2.70 |
| 0120 | Milling existing asphalt pavement, 3 3/4" avg depth (0327-70-20) | SY | 82,751 | $0.50 | $1.70 | $3.75 |
| 0125 | Superpave asphaltic concrete, traffic E, PG76-22 (0334-1-55) | TN | 14,114.70 | $184.57 | $127.85 | $165.00 |
| 0130 | Superpave asphaltic concrete, traffic E, high polymer (0334-1-59) | TN | 13,653.80 | $169.90 | $181.75 | $197.00 |
| 0135 | Asphalt concrete friction course, inc bit, FC-5, PG 76-22 (0337-7-25) | TN | 7,003.90 | $178.52 | $210.80 | $238.00 |
| 0140 | Inlets, gutter, type S, partial (0425-1705) | EACH | 14 | $500.00 | $3,400.00 | $9,500.00 |
| 0145 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 54 | $90.61 | $60.00 | $165.00 |
| 0150 | Mitered end section, optional round, 18" CD (0430-982125) | EACH | 2 | $2,350.07 | $1,400.00 | $3,200.00 |
| 0155 | Edgedrain draincrete, (0446-1-1) | LF | 59,441 | $38.64 | $51.00 | $51.70 |
| 0160 | Edgedrain outlet pipe, 4" (0446-71-1) | LF | 5,129 | $55.72 | $51.00 | $52.53 |
| 0165 | Shoulder gutter- concrete (0520-6) | LF | 280 | $10.00 | $56.00 | $100.00 |
| 0170 | Performance turf, sod (0570-1-2) | SY | 14,258 | $2.92 | $4.40 | $4.50 |
| 0175 | Performance turf, sod and shoulder treatment index (0570-1-3) | SY | 29,884 | $2.92 | $4.40 | $7.25 |
| 0180 | Raised pavement marker, type B (0706-1-3) | EACH | 1,508 | $4.87 | $4.95 | $4.95 |
| 0185 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 11.22 | $1,299.98 | $1,300.00 | $1,320.00 |
| 0190 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 11.22 | $1,083.31 | $1,100.00 | $1,100.00 |
| 0195 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 11.23 | $1,299.98 | $1,300.00 | $1,320.00 |
| 0200 | High tension cable barrier system - length of need (0904-540-13) | LF | 28,824 | $43.62 | $46.00 | $44.31 |
| 0205 | High tension cable barrier system - end terminal (0904-540-14) | EACH | 18 | $5,416.57 | $5,500.00 | $5,275.00 |
| 0210 | High tension cable barrier system, end terminal foundation- miscellaneous drilled shaft (0904-540-15) | CY | 144 | $7,748.70 | $8,200.00 | $7,915.00 |
| 0215 | High tension cable barrier system, concrete mow strip (0904-540-16) | LF | 28,734 | $32.50 | $33.00 | $31.65 |
| 0220 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $150,000 | $150,000 | $150,000 |
| 0225 | Ground-in rumble strips, 16" (0546-72-1) | GM | 22.45 | $2,901.32 | $3,000.00 | $2,750.00 |
| 0230 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 2 | $1,624.97 | $1,600.00 | $1,650.00 |
| 0235 | Raised pavement marker, type B (0706-1-3) | EACH | 1,508 | $4.87 | $4.95 | $4.95 |
| 0240 | Painted pavement markings, surface (0710-90) | LS | 1 | $41,344 | $42,000 | $41,981 |
| 0245 | Thermoplastic, standard-open graded asphalt surfaces solid, 6" (0711-15101) | GM | 11.22 | $4,874.91 | $4,900.00 | $4,950.00 |
| 0250 | Thermoplastic, standard-open graded asphalt surfaces, skip, 6",10-30 skip or 3-9 lane (0711-15131) | GM | 11.22 | $3,791.60 | $3,800.00 | $3,850.00 |
| 0255 | Thermoplastic, standard-open graded asphalt surfaces, yellow, solid, 6" (0711-15201) | GM | 11.23 | $4,874.91 | $4,900.00 | $4,950.00 |
| 0260 | Existing ITS maintenance (0102-112) | DA | 325 | $108.33 | $110.00 | $110.00 |
| 0265 | Itsfm subsurface documentation- project length (0611-1-1) | MI | 5.61 | $5,416.57 | $5,500.00 | $5,500.00 |
| 0270 | Itsfm location documentation- ITS site (0611-2-2) | EACH | 2 | $2,767.87 | $2,800.00 | $2,810.50 |
| 0275 | Conduit, furnish & install, open trench (0630-2-11) | LF | 5,105 | $16.25 | $16.40 | $16.50 |
| 0280 | Conduit, furnish & install, aboveground (0630-2-14) | LF | 30 | $21.67 | $22.00 | $2,200.00 |
| 0285 | Fiber optic cable, F&I, underground,2-12 fibers (0633-1121) | LF | 735 | $5.42 | $5.50 | $5.50 |
| 0290 | Fiber optic connection, install, splice (0633-2-31) | EACH | 4 | $108.33 | $110.00 | $110.00 |
| 0295 | Fiber optic connection, install, termination (0633-2-32) | EACH | 12 | $108.33 | $110.00 | $110.00 |
| 0300 | Fiber optic connection hardware, F&I, splice enclosure (0633-3-11) | EACH | 1 | $2,166.63 | $2,200.00 | $2,200.00 |
| 0305 | Fiber optic connection hardware, F&I, splice tray (0633-3-12) | EACH | 1 | $108.33 | $110.00 | $110.00 |
| 0310 | Fiber optic connection hardware, F&I, patch panel- terminated (0633-3-16) | EACH | 1 | $2,708.28 | $2,700.00 | $2,750.00 |
| 0315 | Fiber optic cable locator (0633-6) | DA | 325 | $108.33 | $110.00 | $110.00 |
| 0320 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 12 | $1,624.97 | $1,600.00 | $1,650.00 |
| 0325 | Pull & splice box, F&I, 24" X 36" cover size (0635-2-12) | EACH | 1 | $2,004.13 | $2,000.00 | $2,035.00 |
| 0330 | Pull & splice box, F&I, 30" X 60" rectangular or 36" round size (0635-2-13) | EACH | 1 | $4,333.25 | $4,400.00 | $4,400.00 |
| 0335 | Electrical power service, adjust/modify (0639-1500) | AS | 1 | $3,791.60 | $2,700.00 | $3,850.00 |
| 0340 | Electrical service wire, & install (0639-2-1) | LF | 4,529 | $7.04 | $7.10 | $7.15 |
| 0345 | Electrical service disconnect, F&I, pole mount (0639-3-11) | EACH | 2 | $1,299.98 | $1,300.00 | $1,320.00 |
| 0350 | Electrical service disconnect, remove- pole or cabinet to remain (0639-3-60) | EACH | 1 | $108.33 | $110.00 | $110.00 |
| 0355 | Electrical power service- transformer, F&I, <5 kva, single phase, copper windings (0639-6111) | EACH | 1 | $2,708.28 | $2,700.00 | $2,750.00 |
| 0360 | Electrical power service- transformer, F&I, 5-10 kva, phase, copper windings (0639-6121) | EACH | 1 | $5,416.57 | $5,500.00 | $5,500.00 |
| 0365 | Steel CCTV pole, furnish & install with lowering device, 50' (0649-2150) | EACH | 1 | $64,999 | $66,000 | $66,000 |
| 0370 | ITS cabinet, furnish & install, pole mount with sunshield, 24" W X 46" H X 22" D (0676-2122) | EACH | 1 | $9,749.82 | $9,900.00 | $9,900.00 |
| 0375 | ITS CCTV camera, non- pressurized, IP, high definition (0682-1173) | EACH | 2 | $5,524.90 | $5,600.00 | $5,610.00 |
| 0380 | Managed field ethernet switch, furnish & install (0684-1-1) | EACH | 1 | $2,708.28 | $2,700.00 | $2,750.00 |
| 0385 | Uninterruptible power supply, furnish and install, line interactive (0685-1-11) | EACH | 1 | $5,958.23 | $6,000.00 | $6,050.00 |
| 0390 | Remote power management rpmu, furnish and install (0685-2-1) | EACH | 1 | $1,083.31 | $1,100.00 | $1,100.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of October 28, 2026. Compiled by Mirage Metrics.