FDOT contract T5861 bid tabulation
SR A1A (OCEAN SHORE BLVD) FROM N OF ROBERTA RD TO FLAGLER... Let by Florida DOT on October 29, 2025, Volusia, District 5. 4 bids received; low bid $12,993,380 by Masci General Contractors, Inc.
- Owner
- Florida DOT
- Letting
- 29 OCT 2025
- Pay items
- 98
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Masci General Contractors, Inc | $12,993,380 | Low |
| 2 | Halifax Paving, Inc. | $13,556,130 | +4.0% |
| 3 | C.W. Roberts Contracting, Inc. | $15,934,515 | +23% |
| 4 | Watson Civil Construction, Inc. | $17,514,578 | +35% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Masci General Contractors, Inc | 2. Halifax Paving, Inc. | 3. C.W. Roberts Contracting, Inc. | 4. Watson Civil Construction, Inc. |
|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $834,490 | $915,443 | $1,200,000 | $1,750,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $154,254 | $253,500 | $856,000 | $1,090,000 |
| 0015 | Special detour- temporary pavement (0102-2200) | SY | 1 | $47,500 | $50,000 | $65,000 | $114,000 |
| 0020 | Special detour- temporary earthwork/base (0102-2300) | CY | 1 | $158,565 | $80,000 | $190,000 | $186,000 |
| 0025 | Commercial material for temporary driveway maintenance (0102-3) | CY | 425.70 | $105.00 | $50.00 | $150.00 | $230.00 |
| 0030 | Pedestrian or bicycle special detour (0102-4-1) | SY | 1 | $88,800 | $240,000 | $620,000 | $604,000 |
| 0035 | Traffic control officer (0102-14) | HR | 240 | $90.00 | $125.00 | $100.00 | $120.00 |
| 0040 | Work zone sign (0102-60) | ED | 381,683 | $0.20 | $0.18 | $0.21 | $0.27 |
| 0045 | Business sign (0102-61) | EACH | 6 | $40.00 | $50.00 | $38.00 | $35.00 |
| 0050 | Temporary barrier, F&I, low profile, concrete (0102-71-13) | LF | 16,932 | $42.50 | $45.00 | $44.00 | $40.00 |
| 0055 | Temporary barrier, relocate, low profile concrete (0102-71-23) | LF | 3,768 | $13.50 | $16.00 | $14.00 | $12.00 |
| 0060 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 532,088 | $0.08 | $0.08 | $0.09 | $0.11 |
| 0065 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 7,301,162 | $0.04 | $0.03 | $0.04 | $0.04 |
| 0070 | Temporary raised/retroreflective pavement marker, type D (0102-78-1) | EACH | 704 | $5.00 | $5.00 | $5.50 | $5.00 |
| 0075 | Portable changeable message sign, temporary (0102-99) | ED | 6,942 | $9.35 | $8.50 | $9.50 | $13.00 |
| 0080 | Type III barricade (0102-115) | ED | 46,535 | $0.27 | $0.20 | $0.22 | $0.30 |
| 0085 | Temporary raised rumble per day, includes all sets and relocations (0102-909) | DA | 14 | $35.00 | $25.00 | $26.00 | $24.00 |
| 0090 | Removable tape, white, 24" stop bar (0102-913-23) | LF | 872 | $10.00 | $6.00 | $4.00 | $6.40 |
| 0095 | Removable tape, white, 12" crosswalk (0102-913-24) | LF | 6,896 | $5.00 | $4.00 | $4.00 | $4.25 |
| 0100 | Sediment barrier (0104-10-3) | LF | 17,340 | $1.00 | $1.50 | $1.50 | $2.10 |
| 0105 | Soil tracking prevention device (0104-15) | EACH | 2 | $3,500.00 | $3,500.00 | $4,000.00 | $5,700.00 |
| 0110 | Inlet protection system (0104-18) | EACH | 27 | $165.00 | $150.00 | $250.00 | $135.00 |
| 0115 | Litter removal (0107-1) | ACRE | 956.12 | $46.00 | $45.00 | $50.00 | $60.00 |
| 0120 | Mowing (0107-2) | ACRE | 425.22 | $86.00 | $85.00 | $95.00 | $90.00 |
| 0125 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $200,000 | $75,000 | $520,000 | $610,000 |
| 0130 | Removal of existing concrete (0110-4-10) | SY | 10,412 | $23.50 | $50.00 | $17.00 | $20.00 |
| 0135 | Mailbox, F&I single (0110-7-1) | EACH | 7 | $300.00 | $300.00 | $450.00 | $375.00 |
| 0140 | Regular excavation (0120-1) | CY | 3,522.40 | $17.90 | $60.00 | $55.00 | $27.00 |
| 0145 | Embankment (0120-6) | CY | 6,374.30 | $19.50 | $50.00 | $9.00 | $33.00 |
| 0150 | Type B stabilization (0160-4) | SY | 3,432 | $11.25 | $28.00 | $20.00 | $41.00 |
| 0155 | Optional base, base group 08 (0285-708) | SY | 2,118 | $39.29 | $52.00 | $57.00 | $73.00 |
| 0160 | Milling existing asphalt pavement, 3 1/2" avg depth (0327-70-2) | SY | 5,344 | $3.15 | $3.50 | $7.00 | $5.20 |
| 0165 | Milling existing asphalt pavement, 3" avg depth (0327-70-4) | SY | 89,882 | $2.90 | $3.00 | $6.30 | $3.70 |
| 0170 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 18,340 | $1.92 | $4.00 | $10.40 | $4.20 |
| 0175 | Superpave asphaltic conc, traffic C (0334-1-13) | TN | 19,417 | $129.15 | $150.00 | $130.00 | $177.00 |
| 0180 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 9,542.50 | $149.24 | $162.50 | $170.00 | $187.00 |
| 0185 | Pervious concrete pavement, 6" (0354-1102) | SY | 1,274 | $103.15 | $202.00 | $236.00 | $142.00 |
| 0190 | Concrete class NS, gravity index 400-011 (0400-0-11) | CY | 86 | $959.15 | $1,000.00 | $1,280.00 | $1,650.00 |
| 0195 | Inlets, curb, type P-5, <10' (0425-1351) | EACH | 6 | $9,965.00 | $10,500 | $11,970 | $8,900.00 |
| 0200 | Inlets, DT bot, type C,<10' (0425-1521) | EACH | 13 | $8,125.00 | $5,200.00 | $7,740.00 | $5,200.00 |
| 0205 | Inlets, ditch bottom, type C, partial (0425-1525) | EACH | 4 | $5,945.00 | $3,700.00 | $2,950.00 | $6,400.00 |
| 0210 | Inlets, ditch bottom, type F, partial (0425-1565) | EACH | 6 | $5,945.00 | $6,400.00 | $5,300.00 | $6,900.00 |
| 0215 | Manholes, J-7, partial (0425-2-73) | EACH | 12 | $7,327.00 | $5,800.00 | $5,000.00 | $4,400.00 |
| 0220 | Pipe culvert,optional material,round, 15"S/CD (0430-175115) | LF | 74 | $219.45 | $200.00 | $298.00 | $480.00 |
| 0225 | French drain, 18" (0443-70-3) | LF | 688 | $257.89 | $160.00 | $250.00 | $259.00 |
| 0230 | Pipe handrail - guiderail, aluminum (0515-1-2) | LF | 445 | $61.50 | $66.00 | $58.00 | $54.00 |
| 0235 | Concrete curb & gutter, type E (0520-1-7) | LF | 623 | $39.50 | $32.60 | $49.00 | $56.00 |
| 0240 | Concrete curb & gutter, type F (0520-1-10) | LF | 21,988 | $35.25 | $31.00 | $44.00 | $43.00 |
| 0245 | Concrete curb, type D (0520-2-4) | LF | 46 | $57.29 | $28.00 | $27.00 | $41.00 |
| 0250 | Concrete curb, ribbon curb (0520-2100) | LF | 2,909 | $37.59 | $24.90 | $24.00 | $17.50 |
| 0255 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 282 | $77.29 | $54.90 | $81.00 | $60.00 |
| 0260 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 22,779 | $85.76 | $61.25 | $71.00 | $72.00 |
| 0265 | Concrete ditch pavement, non reinforced, 4" (0524-1-2) | SY | 356 | $114.25 | $78.00 | $350.00 | $67.00 |
| 0270 | Detectable warnings (0527-2) | SF | 2,653 | $29.50 | $45.00 | $22.00 | $40.00 |
| 0275 | Performance turf, sod (0570-1-2) | SY | 44,372 | $3.99 | $5.00 | $5.50 | $6.30 |
| 0280 | Performance turf, sod and shoulder treatment index (0570-1-3) | SY | 5,121 | $5.95 | $8.50 | $12.00 | $6.90 |
| 0285 | Irrigation system- modify existing system (0590-70-5) | LS | 1 | $15,000 | $10,000 | $9,500.00 | $37,000 |
| 0290 | Raised pavement marker, type B (0706-1-3) | EACH | 5,340 | $4.75 | $5.00 | $5.50 | $5.30 |
| 0295 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 17.16 | $1,850.00 | $1,300.00 | $1,250.00 | $1,400.00 |
| 0300 | Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123) | LF | 188 | $2.10 | $2.25 | $2.00 | $2.40 |
| 0305 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 77 | $3.00 | $2.75 | $4.00 | $2.90 |
| 0310 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 0.33 | $950.00 | $850.00 | $1,000.00 | $875.00 |
| 0315 | Painted pavement markings, standard, white, message or symbol (0710-11160) | EACH | 18 | $70.00 | $95.00 | $92.00 | $100.00 |
| 0320 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 30 | $48.00 | $85.00 | $55.00 | $90.00 |
| 0325 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 19.76 | $1,850.00 | $1,300.00 | $1,250.00 | $1,400.00 |
| 0330 | Disputes review board, meeting- DO not bid (0999-20-1) | DA | 12 | $4,800.00 | $4,800.00 | $4,800.00 | $4,800.00 |
| 0335 | Disputes review board, hearing- DO not bid (0999-20-2) | EACH | 2 | $5,750.00 | $5,750.00 | $5,750.00 | $5,750.00 |
| 0340 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $150,000 | $150,000 | $150,000 | $150,000 |
| 0345 | Ground-in rumble strips, 8" sinusoidal (0546-72-3) | GM | 7.88 | $2,350.00 | $3,080.00 | $4,400.00 | $3,200.00 |
| 0350 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 339 | $529.00 | $390.00 | $520.00 | $405.00 |
| 0355 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 36 | $2,745.00 | $1,900.00 | $2,800.00 | $2,000.00 |
| 0360 | Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113) | EACH | 30 | $3,095.00 | $2,100.00 | $3,200.00 | $2,200.00 |
| 0365 | Single column ground sign assembly, relocate (0700-1500) | EACH | 60 | $225.00 | $100.00 | $200.00 | $104.00 |
| 0370 | Single column ground sign assembly, remove (0700-1600) | EACH | 286 | $42.00 | $50.00 | $40.00 | $52.00 |
| 0375 | Sign panel, remove, UP to 12 SF (0700-3601) | EACH | 35 | $30.00 | $75.00 | $25.00 | $78.00 |
| 0380 | Enhanced highway sign solar powered, F&I ground mount, W/eds and beacon, UP to 12 SF of static sign panels (0700-142171) | EACH | 2 | $16,991 | $16,000 | $16,500 | $19,800 |
| 0385 | Enhanced highway sign solar powered, remove - mount (0700-142902) | EACH | 2 | $650.00 | $1,850.00 | $300.00 | $900.00 |
| 0390 | Object marker, type 1 (0705-10-1) | EACH | 123 | $249.00 | $250.00 | $275.00 | $260.00 |
| 0395 | Raised pavement marker, type B (0706-1-3) | EACH | 1,965 | $4.75 | $5.00 | $5.50 | $5.30 |
| 0400 | Painted pavement markings, durable paint, yellow, island nose (0710-12290) | SF | 10 | $6.25 | $10.00 | $3.50 | $10.60 |
| 0405 | Painted pavement markings, surface (0710-90) | LS | 1 | $63,700 | $68,080 | $51,000 | $65,000 |
| 0410 | Thermoplastic, standard, solid, 6" for parking spaces (0711-11121) | LF | 631 | $7.25 | $5.75 | $2.00 | $6.10 |
| 0415 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 4,791 | $3.95 | $6.25 | $5.00 | $6.60 |
| 0420 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 951 | $6.85 | $6.75 | $5.50 | $7.15 |
| 0425 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 0.21 | $3,900.00 | $2,200.00 | $2,550.00 | $2,250.00 |
| 0430 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 1 | $250.00 | $200.00 | $250.00 | $215.00 |
| 0435 | Thermoplastic, standard, arrow (0711-11170) | EACH | 25 | $85.00 | $5.00 | $95.00 | $5.30 |
| 0440 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 1,069 | $6.00 | $6.50 | $5.50 | $6.90 |
| 0445 | Thermoplastic, standard, blue, solid,6" (0711-11421) | LF | 54 | $11.95 | $5.75 | $16.00 | $6.10 |
| 0450 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 1,325 | $16.54 | $15.00 | $18.00 | $16.00 |
| 0455 | Thermoplastic, preformed, color, in pavement warning (0711-14760) | EACH | 36 | $1,595.00 | $600.00 | $2,100.00 | $635.00 |
| 0460 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 14.11 | $5,800.00 | $4,800.00 | $6,000.00 | $5,100.00 |
| 0465 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 9.26 | $5,800.00 | $4,800.00 | $6,000.00 | $5,100.00 |
| 0470 | Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231) | GM | 2.76 | $2,385.00 | $2,200.00 | $3,100.00 | $2,320.00 |
| 0475 | Thermoplastic, remove existing thermoplastic pavement markings- surface to remain (0711-17-1) | SF | 53 | $4.65 | $5.00 | $7.00 | $5.30 |
| 0480 | Midblock crosswalk: rectangular rapid flashing beacon, furnish & install- complete sign assembly- back back (0654-2-22) | AS | 2 | $13,204 | $12,000 | $12,500 | $13,700 |
| 0485 | Midblock crosswalk: rec rapid flashing beacon, solar, sign assembly- back-back accessible detector (0654-2-28) | AS | 6 | $14,992 | $13,756 | $14,500 | $16,000 |
| 0490 | Midblock crosswalk: rectangular rapid flashing beacon, remove complete sign assembly (0654-2-60) | AS | 2 | $650.00 | $2,126.00 | $320.00 | $950.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of October 29, 2025. Compiled by Mirage Metrics.