FDOT contract T5873 bid tabulation
SR 200 (SW COLLEGE RD) AT SW 60TH AVE. Let by Florida DOT on October 29, 2025, Marion, District 5. 2 bids received; low bid $1,014,097 by Chinchor Electric Inc..
- Owner
- Florida DOT
- Letting
- 29 OCT 2025
- Pay items
- 81
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Chinchor Electric Inc. | $1,014,097 | Low |
| 2 | Traffic Control Devices, Inc. | $1,072,250 | +6.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Chinchor Electric Inc. | 2. Traffic Control Devices, Inc. |
|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $125,042 | $106,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $47,080 | $36,600 |
| 0015 | Pedestrian or bicycle special detour (0102-4-1) | SY | 1 | $30,525 | $18,625 |
| 0020 | Traffic control officer (0102-14) | HR | 68 | $138.75 | $125.00 |
| 0025 | Work zone sign (0102-60) | ED | 2,755 | $0.30 | $0.35 |
| 0030 | Business sign (0102-61) | EACH | 4 | $53.45 | $56.00 |
| 0035 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 14,559 | $0.11 | $0.15 |
| 0040 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 4,704 | $0.18 | $0.20 |
| 0045 | Arrow board / advance warning arrow panel (0102-76) | ED | 84 | $7.13 | $7.50 |
| 0050 | Portable changeable message sign, temporary (0102-99) | ED | 473 | $11.88 | $12.50 |
| 0055 | Temporary signalization and maintenance, intersection (0102-104) | ED | 100 | $34.41 | $42.00 |
| 0060 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 100 | $5.55 | $1.00 |
| 0065 | Removable tape, white, 10'-30', 6'-10', or 2'-4' skip, 6" wide (0102-913-22) | GM | 0.04 | $11,100 | $12,423 |
| 0070 | Sediment barrier (0104-10-3) | LF | 904 | $9.71 | $9.50 |
| 0075 | Inlet protection system (0104-18) | EACH | 13 | $233.10 | $240.00 |
| 0080 | Litter removal (0107-1) | ACRE | 2.76 | $94.35 | $95.00 |
| 0085 | Mowing (0107-2) | ACRE | 2.02 | $105.45 | $125.00 |
| 0090 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $5,550.00 | $25,000 |
| 0095 | Removal of existing concrete (0110-4-10) | SY | 103 | $39.68 | $100.00 |
| 0100 | Borrow excavation, truck measure (0120-2-2) | CY | 17.30 | $84.64 | $100.00 |
| 0105 | Concrete curb & gutter, type E (0520-1-7) | LF | 34 | $58.83 | $74.50 |
| 0110 | Concrete curb & gutter, type F, with class IV concrete, project 451253-1-52-01 (0520-1110) | LF | 90 | $97.96 | $175.50 |
| 0115 | Concrete curb, type D (0520-2-4) | LF | 71 | $63.83 | $35.00 |
| 0120 | Traffic separator concrete- type I, 4' wide (0520-5-11) | LF | 5 | $194.25 | $750.50 |
| 0125 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 23 | $117.11 | $150.00 |
| 0130 | Concrete sidewalk and driveways, 6" thick, with class concrete, project 451253-1-52-01 (0522-2102) | SY | 69 | $146.24 | $176.00 |
| 0135 | Detectable warnings (0527-2) | SF | 60 | $53.28 | $124.50 |
| 0140 | Performance turf, sod (0570-1-2) | SY | 107 | $29.15 | $23.00 |
| 0145 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $45,000 | $45,000 |
| 0150 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 4 | $499.50 | $747.00 |
| 0155 | Single column ground sign assembly, remove (0700-1600) | EACH | 5 | $166.50 | $415.00 |
| 0160 | Object marker, type 1 (0705-10-1) | EACH | 1 | $222.00 | $351.75 |
| 0165 | Raised pavement marker, type B (0706-1-3) | EACH | 8 | $27.75 | $31.00 |
| 0170 | Painted pavement markings, standard, yellow, island nose (0710-11290) | SF | 6 | $27.75 | $31.00 |
| 0175 | Thermoplastic, refurbishment, white, solid, 8" (0711-12122) | LF | 87 | $2.22 | $2.50 |
| 0180 | Thermoplastic, refurbishment, white, solid, 12" for cross walk or roundabout (0711-12123) | LF | 313 | $7.77 | $8.70 |
| 0185 | Thermoplastic, refurbishment, white, solid, 18" for diagonal or chevron (0711-12124) | LF | 25 | $11.66 | $13.00 |
| 0190 | Thermoplastic, refurbishment, white, solid, 24" for stop line or crosswalk (0711-12125) | LF | 126 | $15.54 | $17.50 |
| 0195 | Thermoplastic, standard-open graded asphalt surfaces solid, 6" (0711-15101) | GM | 0.02 | $27,750 | $31,055 |
| 0200 | Conduit, furnish & install, open trench (0630-2-11) | LF | 229 | $20.07 | $12.74 |
| 0205 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 16 | $596.64 | $2,130.00 |
| 0210 | Electrical service wire, & install (0639-2-1) | LF | 22 | $5.49 | $7.75 |
| 0215 | Electrical service disconnect, F&I, pole mount (0639-3-11) | EACH | 1 | $3,228.66 | $2,435.00 |
| 0220 | Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12) | LF | 5,067 | $2.02 | $2.70 |
| 0225 | Luminaire & bracket arm- aluminum, furnish & install new luminaire and arm on new/existing pole (0715-5-31) | EACH | 1 | $3,106.45 | $1,955.00 |
| 0230 | Load center, F&I, secondary voltage (0715-7-11) | EACH | 1 | $14,613 | $26,500 |
| 0235 | Light pole complete, F&I, standard pole standard foundation, 40' mounting height, 10' arm length (0715-61321) | EACH | 3 | $7,967.08 | $9,238.00 |
| 0240 | Light pole complete, F&I, standard pole special foundation, 40' mounting height, 10' arm length (0715-62321) | EACH | 2 | $9,203.18 | $13,350 |
| 0245 | Light pole complete, F&I, utility conflict pole standard foundation, 35' mounting height, 16' arm length (0715-65266) | EACH | 3 | $9,559.49 | $10,145 |
| 0250 | Light pole complete, F&I, utility conflict pole special foundation, 40' mounting height, 16' arm length (0715-66366) | EACH | 1 | $10,320 | $15,460 |
| 0255 | Pole cable distribution system, furnish and install, conventional (0715-500-1) | EACH | 10 | $790.26 | $808.00 |
| 0260 | Itsfm subsurface documentation- project length (0611-1-1) | MI | 0.10 | $3,885.00 | $4,070.00 |
| 0265 | Itsfm location documentation- intersection (0611-2-1) | EACH | 1 | $2,775.00 | $1,627.00 |
| 0270 | Conduit, furnish & install, open trench (0630-2-11) | LF | 1,259 | $20.19 | $14.45 |
| 0275 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 740 | $37.00 | $36.90 |
| 0280 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 1 | $11,722 | $18,375 |
| 0285 | Fiber optic cable, F&I, underground,2-12 fibers (0633-1121) | LF | 369 | $4.16 | $3.50 |
| 0290 | Fiber optic connection, install, termination (0633-2-32) | EACH | 24 | $138.75 | $80.00 |
| 0295 | Span wire assembly, F&I, two point, diagonal (0634-4152) | PI | 1 | $13,271 | $3,430.00 |
| 0300 | Span wire assembly, remove- poles remain (0634-4600) | PI | 1 | $2,775.00 | $2,380.00 |
| 0305 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 24 | $596.64 | $1,200.00 |
| 0310 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 1 | $5,725.94 | $6,640.00 |
| 0315 | Electrical power service, remove overhead (0639-1610) | AS | 1 | $888.00 | $1,275.00 |
| 0320 | Electrical service wire, & install (0639-2-1) | LF | 141 | $5.49 | $7.75 |
| 0325 | Prestressed concrete pole, complete pole removal- pole 30' and greater (0641-2-80) | EACH | 1 | $18,371 | $28,095 |
| 0330 | Aluminum signals pole, (0646-1-11) | EACH | 2 | $2,895.51 | $2,555.00 |
| 0335 | Aluminum signals pole, furnish install pedestrian detector post (0646-1-12) | EACH | 5 | $2,869.38 | $2,295.00 |
| 0340 | Aluminum signals pole, remove (0646-1-60) | EACH | 2 | $888.00 | $295.00 |
| 0345 | Steel strain pole, F&I, type PS- X (0649-1-17) | EACH | 2 | $62,293 | $95,555 |
| 0350 | Vehicular traffic signal, furnish & install W/alum top, 3 section, 1 way (0650-1-24) | AS | 16 | $1,835.67 | $1,595.00 |
| 0355 | Vehicular traffic signal, furnish & install W alumin, 5 section cluster, 1 way (0650-1-29) | AS | 1 | $2,836.05 | $2,325.00 |
| 0360 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 2 | $795.02 | $795.00 |
| 0365 | Traffic data detection system- video, furnish and install, cabinet equipment (0660-9-11) | EACH | 2 | $41,702 | $20,720 |
| 0370 | Traffic data detection system- video, furnish and install, ground equipment (0660-9-12) | EACH | 4 | $15,065 | $11,425 |
| 0375 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 8 | $473.15 | $267.00 |
| 0380 | Pedestrian detector, remove- pole/pedestal to remain (0665-1-60) | EACH | 6 | $111.00 | $182.00 |
| 0385 | Traffic signal controller cabinet, adjust/modify (0676-1500) | EACH | 1 | $8,182.33 | $3,940.00 |
| 0390 | ITS CCTV camera, relocate (0682-1400) | EACH | 1 | $1,665.00 | $6,250.00 |
| 0395 | Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22) | EACH | 4 | $9,346.20 | $6,725.00 |
| 0400 | Enhanced highway sign AC powered, F&I ground mount, W/beacon, UP to 12 SF of static sign panels (0700-141111) | EACH | 2 | $10,728 | $10,775 |
| 0405 | Enhanced highway sign AC powered, F&I overhead blank out sign <12 SF (0700-141360) | EACH | 2 | $7,391.05 | $6,460.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of October 29, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.