FDOT contract T6625 bid tabulation
SR 968 (W FLAGLER ST) FROM E OF SW 48 CT TO W OF SW 48 AVE. Let by Florida DOT on July 29, 2026, Miami-Dade, District 6. 7 bids received; low bid $594,156 by Florida Signal & Lighting Contractors, Inc..
- Owner
- Florida DOT
- Letting
- 29 JUL 2026
- Pay items
- 62
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Florida Signal & Lighting Contractors, Inc. | $594,156 | Low |
| 2 | Florida Engineering & Development Corp | $596,907 | 0.0% |
| 3 | Arc Electric Inc | $624,242 | +5.0% |
| 4 | Traffico LLC | $643,888 | +8.0% |
| 5 | Horsepower Electric, Inc. | $649,445 | +9.0% |
| 6 | Signal Technology and Installation Corp. | $656,163 | +10% |
| 7 | Sice Inc | $675,646 | +14% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Florida Signal & Lighting Contractors, Inc. | 2. Florida Engineering & Development Corp | 3. Arc Electric Inc | 4. Traffico LLC | 5. Horsepower Electric, Inc. | 6. Signal Technology and Installation Corp. |
|---|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $55,000 | $71,223 | $65,000 | $64,917 | $60,000 | $48,184 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $55,000 | $66,554 | $45,000 | $45,000 | $20,000 | $32,950 |
| 0015 | Traffic control officer (0102-14) | HR | 16 | $85.00 | $87.95 | $100.00 | $120.00 | $100.00 | $106.13 |
| 0020 | Work zone sign (0102-60) | ED | 3,640 | $0.35 | $0.25 | $0.30 | $0.20 | $0.30 | $0.34 |
| 0025 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 3,780 | $0.25 | $0.20 | $0.25 | $0.20 | $0.30 | $0.25 |
| 0030 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 1,350 | $0.20 | $0.15 | $0.20 | $0.80 | $0.20 | $0.17 |
| 0035 | Arrow board / advance warning arrow panel (0102-76) | ED | 280 | $8.00 | $6.75 | $10.00 | $6.00 | $20.00 | $8.29 |
| 0040 | Portable changeable message sign, temporary (0102-99) | ED | 308 | $15.00 | $13.70 | $18.00 | $14.00 | $25.00 | $16.85 |
| 0045 | Type III barricade (0102-115) | ED | 280 | $0.35 | $0.90 | $1.00 | $5.00 | $0.50 | $1.08 |
| 0050 | Litter removal (0107-1) | ACRE | 1.58 | $6,000.00 | $289.75 | $1,200.00 | $100.00 | $90.00 | $27.61 |
| 0055 | Mowing (0107-2) | ACRE | 0.61 | $5,000.00 | $750.50 | $1,000.00 | $200.00 | $1,000.00 | $34.55 |
| 0060 | Monitor existing structures- inspection and settlement monitoring (0108-1) | LS | 1 | $3,500.00 | $7,560.15 | $8,000.00 | $8,500.00 | $10,000 | $5,930.28 |
| 0065 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $5,000.00 | $521.05 | $9,000.00 | $6,500.00 | $10,000 | $7,412.85 |
| 0070 | Removal of existing concrete (0110-4-10) | SY | 175 | $50.00 | $38.45 | $110.00 | $55.00 | $45.50 | $47.18 |
| 0075 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 1,664 | $12.00 | $3.75 | $4.00 | $11.00 | $8.00 | $11.80 |
| 0080 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 137.30 | $270.00 | $224.10 | $365.00 | $302.50 | $475.00 | $352.59 |
| 0085 | Manhole, adjust (0425-5) | EACH | 1 | $1,200.00 | $1,285.45 | $1,600.00 | $1,045.00 | $2,535.00 | $2,965.14 |
| 0090 | Concrete curb & gutter, type F (0520-1-10) | LF | 148 | $65.00 | $30.05 | $125.00 | $44.00 | $75.40 | $78.18 |
| 0095 | Concrete curb, type D (0520-2-4) | LF | 8 | $700.00 | $40.75 | $130.00 | $38.50 | $49.40 | $51.22 |
| 0100 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 100 | $80.00 | $67.20 | $135.00 | $99.00 | $114.40 | $132.09 |
| 0105 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 57 | $140.00 | $75.35 | $160.00 | $121.00 | $130.00 | $148.26 |
| 0110 | Detectable warnings (0527-2) | SF | 54 | $55.00 | $42.35 | $55.00 | $44.00 | $45.50 | $47.18 |
| 0115 | Electrical power service- contribution in aid of construction (ciac), FPL (DO not bid) (0639-8130) | LS | 1 | $1,032.81 | $1,032.81 | $1,032.81 | $1,032.81 | $1,032.81 | $1,032.81 |
| 0120 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $29,837 | $29,837 | $29,837 | $29,837 | $29,837 | $29,837 |
| 0125 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 7 | $800.00 | $761.50 | $1,000.00 | $650.00 | $936.00 | $1,347.80 |
| 0130 | Single column ground sign assembly, remove (0700-1600) | EACH | 2 | $100.00 | $10.95 | $150.00 | $250.00 | $97.50 | $134.78 |
| 0135 | Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201) | EACH | 4 | $1,100.00 | $1,089.20 | $900.00 | $750.00 | $1,200.00 | $2,695.59 |
| 0140 | Raised pavement marker, type B (0706-1-3) | EACH | 64 | $7.00 | $5.50 | $10.00 | $6.00 | $6.50 | $6.74 |
| 0145 | Painted pavement markings, surface (0710-90) | LS | 1 | $1,200.00 | $1,072.60 | $9,000.00 | $1,174.72 | $2,405.00 | $11,098 |
| 0150 | Thermoplastic, standard, solid, 8" for interchange and urban island (0711-11102) | GM | 0.01 | $6,500.00 | $6,936.25 | $10,000 | $7,603.20 | $6,630.00 | $18,898 |
| 0155 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 128 | $2.50 | $2.65 | $7.00 | $2.88 | $2.60 | $5.27 |
| 0160 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 7 | $20.00 | $3.95 | $9.00 | $4.32 | $3.90 | $7.92 |
| 0165 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 52 | $20.00 | $5.25 | $13.00 | $5.76 | $5.20 | $10.54 |
| 0170 | Thermoplastic, standard, arrow (0711-11170) | EACH | 1 | $150.00 | $87.55 | $165.00 | $96.00 | $130.00 | $90.31 |
| 0175 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 90 | $25.00 | $20.80 | $35.00 | $22.80 | $23.40 | $26.96 |
| 0180 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 0.15 | $6,500.00 | $6,935.95 | $12,000 | $7,603.20 | $6,519.00 | $14,172 |
| 0185 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 0.07 | $3,000.00 | $2,517.80 | $7,500.00 | $2,760.00 | $1,755.00 | $3,543.53 |
| 0190 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 0.09 | $10,000 | $6,942.20 | $12,000 | $7,603.20 | $6,519.00 | $12,570 |
| 0195 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 982 | $25.00 | $22.55 | $30.00 | $36.00 | $30.00 | $40.44 |
| 0200 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 9 | $1,500.00 | $1,618.55 | $1,500.00 | $1,900.00 | $1,900.00 | $2,248.94 |
| 0205 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 1 | $6,900.00 | $13,894 | $5,000.00 | $5,400.00 | $10,000 | $6,896.28 |
| 0210 | Electrical service disconnect, remove- pole or cabinet to remain (0639-3-60) | EACH | 1 | $850.00 | $683.05 | $500.00 | $2,000.00 | $100.00 | $1,153.20 |
| 0215 | Load center, F&I, secondary voltage (0715-7-11) | EACH | 1 | $23,500 | $16,641 | $12,500 | $22,000 | $25,000 | $22,301 |
| 0220 | Load center, remove, voltage (0715-7-41) | EACH | 1 | $850.00 | $910.70 | $500.00 | $5,000.00 | $500.00 | $3,459.54 |
| 0225 | Light pole complete, F&I, standard pole standard foundation, 30' mounting height, 10' arm length (0715-61121) | EACH | 1 | $11,000 | $6,904.50 | $10,000 | $9,000.00 | $13,000 | $12,784 |
| 0230 | Light pole complete, F&I, standard pole standard foundation, 40' mounting height, 10' arm length (0715-61321) | EACH | 1 | $12,000 | $7,312.85 | $12,000 | $10,000 | $14,000 | $13,072 |
| 0235 | Pole cable distribution system, furnish and install, conventional (0715-500-1) | EACH | 2 | $850.00 | $886.85 | $800.00 | $1,100.00 | $900.00 | $1,321.79 |
| 0240 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 423 | $35.00 | $48.20 | $40.00 | $36.00 | $30.00 | $47.18 |
| 0245 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 1 | $12,000 | $16,211 | $12,000 | $12,500 | $3,000.00 | $10,213 |
| 0250 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 15 | $1,500.00 | $1,349.55 | $1,300.00 | $1,900.00 | $1,900.00 | $1,761.00 |
| 0255 | Pull & splice box, F&I, 24" X 36" cover size (0635-2-12) | EACH | 1 | $2,500.00 | $2,798.15 | $3,000.00 | $2,800.00 | $2,500.00 | $2,671.51 |
| 0260 | Pull & splice box, install (0635-2-30) | EACH | 1 | $1,200.00 | $1,048.25 | $1,500.00 | $1,000.00 | $900.00 | $1,734.13 |
| 0265 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 1 | $6,000.00 | $10,972 | $6,200.00 | $5,400.00 | $10,000 | $6,896.28 |
| 0270 | Electrical service wire, & install (0639-2-1) | LF | 246 | $10.00 | $8.10 | $12.00 | $12.00 | $15.00 | $6.25 |
| 0275 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 1 | $2,500.00 | $4,372.50 | $3,000.00 | $3,200.00 | $4,500.00 | $6,661.21 |
| 0280 | Aluminum signals pole, (0646-1-11) | EACH | 2 | $2,100.00 | $2,641.90 | $1,600.00 | $3,000.00 | $3,000.00 | $4,987.29 |
| 0285 | Steel mast arm assembly, and install, single arm 70' (0649-21-15) | EACH | 1 | $80,000 | $103,486 | $85,000 | $108,000 | $112,000 | $94,492 |
| 0290 | Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14) | AS | 4 | $1,500.00 | $1,462.20 | $2,000.00 | $2,200.00 | $2,000.00 | $1,817.73 |
| 0295 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 2 | $1,200.00 | $792.30 | $1,600.00 | $2,400.00 | $1,100.00 | $982.11 |
| 0300 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 2 | $260.00 | $370.65 | $600.00 | $750.00 | $500.00 | $455.43 |
| 0305 | Traffic controller assembly, F&I, caltrans W/standard lock (0670-5180) | AS | 1 | $48,000 | $48,862 | $45,000 | $53,000 | $50,000 | $48,384 |
| 0310 | Cellular modem, furnish and install (0684-8-1) | EACH | 1 | $2,500.00 | $2,252.95 | $3,917.00 | $3,200.00 | $3,500.00 | $2,592.23 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of July 29, 2026. Compiled by Mirage Metrics.