IDOT contract 61K79 bid tabulation
Carol Stream, section 17-00064-00-BT. Let by Illinois DOT on April 25, 2025, Dupage, District 01. 7 bids received; low bid $871,518 by Everlast Blacktop Inc..
- Owner
- Illinois DOT
- Letting
- 25 APR 2025
- Pay items
- 71
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Everlast Blacktop Inc. | $871,518 | Low |
| 2 | A Lamp Concrete Contractors, Inc. | $969,980 | +11% |
| 3 | Martam Construction Incorporated | $981,214 | +13% |
| 4 | Schroeder Asphalt Services, Inc. | $989,669 | +14% |
| 5 | R. W. Dunteman Company | $1,022,346 | +17% |
| 6 | PirTano Construction Co., LLC | $1,064,333 | +22% |
| 7 | Alliance Contractors, Inc. | $1,180,521 | +35% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Everlast Blacktop Inc. | 2. A Lamp Concrete Contractors, Inc. | 3. Martam Construction Incorporated | 4. Schroeder Asphalt Services, Inc. | 5. R. W. Dunteman Company | 6. PirTano Construction Co., LLC |
|---|---|---|---|---|---|---|---|---|---|
| 1 | T-quercus bicol 2 (A2006516) | EACH | 4 | $1,150.00 | $545.00 | $566.80 | $600.00 | $545.00 | $545.00 |
| 2 | T-quercus rubra 2 (A2007116) | EACH | 3 | $1,150.00 | $545.00 | $566.80 | $600.00 | $545.00 | $545.00 |
| 3 | S-hamamelis virg 5' (C2003360) | EACH | 2 | $650.00 | $285.00 | $296.40 | $315.00 | $285.00 | $285.00 |
| 4 | E-juniper chin MB 6' (D2000372) | EACH | 9 | $1,150.00 | $420.00 | $436.80 | $460.00 | $420.00 | $420.00 |
| 5 | Tree root pruning (K1005863) | EACH | 15 | $180.00 | $250.00 | $260.00 | $275.00 | $250.00 | $150.00 |
| 6 | Bike path rem (X0327036) | SY | 3,600 | $6.50 | $8.00 | $9.91 | $6.50 | $33.99 | $16.00 |
| 7 | R R FL beacon A comp (X1400326) | EACH | 2 | $13,000 | $12,100 | $12,926 | $13,400 | $15,000 | $9,546.00 |
| 8 | Solar-power FB instln (X1400349) | EACH | 2 | $4,300.00 | $3,925.00 | $4,183.49 | $4,500.00 | $5,000.00 | $8,436.00 |
| 9 | Stump removal only (X2010400) | UNIT | 71 | $170.00 | $10.00 | $10.40 | $12.00 | $10.00 | $150.00 |
| 10 | Selective clearing (X2010516) | UNIT | 1 | $2,600.00 | $1,500.00 | $1,560.00 | $1,750.00 | $1,500.00 | $1,875.00 |
| 11 | Temp access- com ent (X4022000) | EACH | 7 | $300.00 | $250.00 | $641.17 | $80.00 | $321.56 | $1,820.00 |
| 12 | Sanitary manhole adj (X6026050) | EACH | 6 | $850.00 | $1,185.00 | $1,159.21 | $1,320.00 | $1,185.00 | $1,251.00 |
| 13 | Temp info signing (X7200061) | SF | 268 | $32.00 | $15.00 | $16.64 | $23.00 | $25.00 | $25.00 |
| 14 | Stab constr entrance (Z0013797) | SY | 156 | $32.00 | $2.00 | $30.30 | $16.00 | $35.57 | $21.00 |
| 15 | Construction layout (Z0013798) | LS | 1 | $100.00 | $12,900 | $13,416 | $15,000 | $17,500 | $12,900 |
| 16 | Dust control watering (Z0019600) | UNIT | 100 | $1.00 | $1.00 | $33.57 | $60.00 | $5.00 | $12.00 |
| 17 | Temporary fence (20101000) | LF | 400 | $3.00 | $1.00 | $5.20 | $6.00 | $5.00 | $5.00 |
| 18 | Earth excavation (20200100) | CY | 580 | $51.00 | $68.13 | $49.10 | $47.00 | $69.09 | $100.00 |
| 19 | Rem & disp uns matl (20201200) | CY | 170 | $51.00 | $30.00 | $48.78 | $52.00 | $71.53 | $77.00 |
| 20 | Topsoil exc & plac (21101505) | CY | 790 | $23.00 | $47.00 | $27.28 | $40.00 | $69.86 | $86.00 |
| 21 | Seeding CL 1A (25000110) | ACRE | 3 | $4,400.00 | $3,200.00 | $3,328.00 | $3,600.00 | $3,200.00 | $3,200.00 |
| 22 | Nitrogen fert nutr (25000400) | LB | 275 | $4.40 | $2.00 | $2.08 | $2.20 | $2.00 | $2.00 |
| 23 | Potassium fert nutr (25000600) | LB | 275 | $4.40 | $2.00 | $2.08 | $2.20 | $2.00 | $2.00 |
| 24 | Erosion contr blanket (25100630) | SY | 6,857 | $1.85 | $1.30 | $1.35 | $1.43 | $1.30 | $1.00 |
| 25 | Supple watering (25200200) | UNIT | 10 | $380.00 | $1.00 | $1.04 | $1.10 | $1.00 | $1.00 |
| 26 | Temp eros contr seed (28000250) | LB | 148 | $8.80 | $5.00 | $5.20 | $5.50 | $5.00 | $5.00 |
| 27 | Perimeter eros bar (28000400) | LF | 9,660 | $2.10 | $2.50 | $2.60 | $2.75 | $2.50 | $2.50 |
| 28 | Inlet filters (28000510) | EACH | 10 | $380.00 | $15.00 | $202.80 | $225.00 | $195.00 | $195.00 |
| 29 | Temp eros contr blank (28001100) | SY | 6,857 | $1.50 | $0.01 | $0.01 | $0.02 | $0.01 | $0.01 |
| 30 | Sub gran mat B 6 (31101400) | SY | 418 | $11.24 | $15.35 | $13.64 | $6.00 | $12.35 | $23.00 |
| 31 | Agg base cse B 6 (35101800) | SY | 6,403 | $11.24 | $16.00 | $12.25 | $11.20 | $13.36 | $18.00 |
| 32 | PCC bse cse 8 (35300300) | SY | 37 | $167.56 | $80.00 | $98.80 | $108.00 | $101.10 | $98.00 |
| 33 | PCC bse cse 12 (35300700) | SY | 6 | $900.00 | $143.00 | $130.00 | $150.00 | $205.11 | $133.00 |
| 34 | Bit matls PR CT (40600275) | LB | 12,674 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $1.00 |
| 35 | Bit matls tack CT (40600290) | LB | 1,281 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $1.00 |
| 36 | HMA SC IL-9.5 D N50 (40604060) | TON | 1,275 | $110.25 | $123.00 | $145.63 | $110.00 | $109.25 | $125.00 |
| 37 | Protective coat (42001300) | SY | 1,180 | $5.00 | $0.01 | $0.78 | $1.75 | $0.01 | $1.00 |
| 38 | PCC driveway pavt 8 (42300400) | SY | 418 | $14.00 | $125.00 | $86.32 | $105.00 | $71.82 | $83.00 |
| 39 | PC conc sidewalk 5 (42400200) | SF | 6,077 | $12.00 | $8.50 | $9.88 | $9.50 | $8.01 | $10.00 |
| 40 | Detectable warnings (42400800) | SF | 347 | $47.00 | $25.00 | $40.66 | $33.00 | $33.11 | $39.00 |
| 41 | Pavement rem (44000100) | SY | 43 | $18.00 | $25.50 | $42.16 | $22.00 | $32.66 | $67.00 |
| 42 | Drive pavement rem (44000200) | SY | 418 | $18.00 | $24.75 | $21.20 | $16.50 | $26.66 | $26.00 |
| 43 | Curb rem (44000300) | LF | 181 | $8.00 | $8.25 | $13.34 | $10.00 | $10.51 | $20.00 |
| 44 | Comb curb gutter rem (44000500) | LF | 275 | $8.00 | $8.75 | $13.77 | $10.00 | $9.96 | $34.00 |
| 45 | Sidewalk rem (44000600) | SF | 9,093 | $1.90 | $2.05 | $2.85 | $2.25 | $2.52 | $4.00 |
| 46 | Fire hydnts to BE rem (56400500) | EACH | 5 | $1,200.00 | $1,880.00 | $1,436.61 | $2,060.00 | $11,285 | $3,460.00 |
| 47 | Fire hydrants (56400600) | EACH | 5 | $11,800 | $11,285 | $11,103 | $12,350 | $1,880.00 | $12,080 |
| 48 | CB adjust (60250200) | EACH | 1 | $600.00 | $450.00 | $1,665.52 | $500.00 | $450.00 | $899.00 |
| 49 | CB adj new T1F CL (60250500) | EACH | 2 | $690.00 | $1,150.00 | $2,062.38 | $1,275.00 | $1,150.00 | $1,289.00 |
| 50 | Man adjust (60255500) | EACH | 1 | $600.00 | $685.00 | $1,665.52 | $740.00 | $685.00 | $899.00 |
| 51 | VV adjust (60265700) | EACH | 9 | $600.00 | $753.50 | $832.76 | $740.00 | $685.00 | $899.00 |
| 52 | Conc curb TB (60600605) | LF | 181 | $67.00 | $53.00 | $37.34 | $37.00 | $26.67 | $36.00 |
| 53 | Comb CC&G TB6.12 (60603800) | LF | 275 | $51.00 | $48.00 | $39.78 | $37.00 | $31.25 | $38.00 |
| 54 | Non SPL waste disposl (66900200) | CY | 450 | $89.00 | $75.00 | $85.70 | $105.00 | $109.49 | $99.00 |
| 55 | Soil disposal analy (66900530) | EACH | 1 | $2,000.00 | $1,550.00 | $1,612.00 | $1,700.00 | $1,550.00 | $1,550.00 |
| 56 | Reg sub P-const plan (66901001) | LS | 1 | $3,200.00 | $3,400.00 | $3,536.00 | $3,800.00 | $3,400.00 | $3,400.00 |
| 57 | Reg sub F con report (66901003) | LS | 1 | $2,700.00 | $500.00 | $520.00 | $550.00 | $500.00 | $500.00 |
| 58 | Reg sub mon (66901006) | CAL DAY | 8 | $1,200.00 | $700.00 | $728.00 | $825.00 | $700.00 | $700.00 |
| 59 | Engr field office A (67000400) | CAL MO | 6 | $3,200.00 | $1,000.00 | $4,678.94 | $3,000.00 | $3,000.00 | $2,500.00 |
| 60 | Mobilization (67100100) | LS | 1 | $49,371 | $58,150 | $58,873 | $11,000 | $54,321 | $29,000 |
| 61 | TR cont & prot 701501 (70102620) | LS | 1 | $8,000.00 | $87,450 | $60,169 | $4,500.00 | $41,167 | $11,725 |
| 62 | TR cont & prot 701701 (70102635) | LS | 1 | $100.00 | $5,740.00 | $1.04 | $1.00 | $129.76 | $100.00 |
| 63 | TR cont & prot 701801 (70102640) | LS | 1 | $9,600.00 | $5,740.00 | $4,160.00 | $9,500.00 | $108.44 | $100.00 |
| 64 | Sign panel T1 (72000100) | SF | 158 | $36.00 | $25.00 | $33.28 | $38.50 | $30.00 | $30.00 |
| 65 | Remov sign panel T1 (72400310) | SF | 14 | $42.00 | $28.00 | $15.60 | $44.00 | $20.00 | $20.00 |
| 66 | Teles STL sin support (72800100) | LF | 238 | $30.00 | $18.00 | $20.80 | $28.00 | $15.00 | $15.00 |
| 67 | Wood sin support (73000100) | LF | 36 | $44.00 | $15.00 | $26.00 | $44.00 | $30.00 | $30.00 |
| 68 | THPL PVT MK line 6 (78000400) | LF | 282 | $7.00 | $1.85 | $4.94 | $550.00 | $4.75 | $3.00 |
| 69 | THPL PVT MK line 12 (78000600) | LF | 550 | $11.00 | $3.60 | $9.88 | $10.75 | $9.50 | $9.50 |
| 70 | PVT MKG rem WTR blast (78300202) | SF | 300 | $6.00 | $15.00 | $14.04 | $20.00 | $10.00 | $10.00 |
| 71 | Conc FDN TY A (87800100) | LF | 8 | $390.00 | $354.00 | $378.72 | $400.00 | $344.04 | $589.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 25, 2025. Compiled by Mirage Metrics.