IDOT contract 61K79 bid tabulation

Carol Stream, section 17-00064-00-BT. Let by Illinois DOT on April 25, 2025, Dupage, District 01. 7 bids received; low bid $871,518 by Everlast Blacktop Inc..

Owner
Illinois DOT
Letting
25 APR 2025
Pay items
71
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Everlast Blacktop Inc.$871,518Low
2A Lamp Concrete Contractors, Inc.$969,980+11%
3Martam Construction Incorporated$981,214+13%
4Schroeder Asphalt Services, Inc.$989,669+14%
5R. W. Dunteman Company$1,022,346+17%
6PirTano Construction Co., LLC$1,064,333+22%
7Alliance Contractors, Inc.$1,180,521+35%
IDOT contract 61K79: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Everlast Blacktop Inc.2. A Lamp Concrete Contractors, Inc.3. Martam Construction Incorporated4. Schroeder Asphalt Services, Inc.5. R. W. Dunteman Company6. PirTano Construction Co., LLC
1T-quercus bicol 2 (A2006516)EACH4$1,150.00$545.00$566.80$600.00$545.00$545.00
2T-quercus rubra 2 (A2007116)EACH3$1,150.00$545.00$566.80$600.00$545.00$545.00
3S-hamamelis virg 5' (C2003360)EACH2$650.00$285.00$296.40$315.00$285.00$285.00
4E-juniper chin MB 6' (D2000372)EACH9$1,150.00$420.00$436.80$460.00$420.00$420.00
5Tree root pruning (K1005863)EACH15$180.00$250.00$260.00$275.00$250.00$150.00
6Bike path rem (X0327036)SY3,600$6.50$8.00$9.91$6.50$33.99$16.00
7R R FL beacon A comp (X1400326)EACH2$13,000$12,100$12,926$13,400$15,000$9,546.00
8Solar-power FB instln (X1400349)EACH2$4,300.00$3,925.00$4,183.49$4,500.00$5,000.00$8,436.00
9Stump removal only (X2010400)UNIT71$170.00$10.00$10.40$12.00$10.00$150.00
10Selective clearing (X2010516)UNIT1$2,600.00$1,500.00$1,560.00$1,750.00$1,500.00$1,875.00
11Temp access- com ent (X4022000)EACH7$300.00$250.00$641.17$80.00$321.56$1,820.00
12Sanitary manhole adj (X6026050)EACH6$850.00$1,185.00$1,159.21$1,320.00$1,185.00$1,251.00
13Temp info signing (X7200061)SF268$32.00$15.00$16.64$23.00$25.00$25.00
14Stab constr entrance (Z0013797)SY156$32.00$2.00$30.30$16.00$35.57$21.00
15Construction layout (Z0013798)LS1$100.00$12,900$13,416$15,000$17,500$12,900
16Dust control watering (Z0019600)UNIT100$1.00$1.00$33.57$60.00$5.00$12.00
17Temporary fence (20101000)LF400$3.00$1.00$5.20$6.00$5.00$5.00
18Earth excavation (20200100)CY580$51.00$68.13$49.10$47.00$69.09$100.00
19Rem & disp uns matl (20201200)CY170$51.00$30.00$48.78$52.00$71.53$77.00
20Topsoil exc & plac (21101505)CY790$23.00$47.00$27.28$40.00$69.86$86.00
21Seeding CL 1A (25000110)ACRE3$4,400.00$3,200.00$3,328.00$3,600.00$3,200.00$3,200.00
22Nitrogen fert nutr (25000400)LB275$4.40$2.00$2.08$2.20$2.00$2.00
23Potassium fert nutr (25000600)LB275$4.40$2.00$2.08$2.20$2.00$2.00
24Erosion contr blanket (25100630)SY6,857$1.85$1.30$1.35$1.43$1.30$1.00
25Supple watering (25200200)UNIT10$380.00$1.00$1.04$1.10$1.00$1.00
26Temp eros contr seed (28000250)LB148$8.80$5.00$5.20$5.50$5.00$5.00
27Perimeter eros bar (28000400)LF9,660$2.10$2.50$2.60$2.75$2.50$2.50
28Inlet filters (28000510)EACH10$380.00$15.00$202.80$225.00$195.00$195.00
29Temp eros contr blank (28001100)SY6,857$1.50$0.01$0.01$0.02$0.01$0.01
30Sub gran mat B 6 (31101400)SY418$11.24$15.35$13.64$6.00$12.35$23.00
31Agg base cse B 6 (35101800)SY6,403$11.24$16.00$12.25$11.20$13.36$18.00
32PCC bse cse 8 (35300300)SY37$167.56$80.00$98.80$108.00$101.10$98.00
33PCC bse cse 12 (35300700)SY6$900.00$143.00$130.00$150.00$205.11$133.00
34Bit matls PR CT (40600275)LB12,674$0.01$0.01$0.01$0.01$0.01$1.00
35Bit matls tack CT (40600290)LB1,281$0.01$0.01$0.01$0.01$0.01$1.00
36HMA SC IL-9.5 D N50 (40604060)TON1,275$110.25$123.00$145.63$110.00$109.25$125.00
37Protective coat (42001300)SY1,180$5.00$0.01$0.78$1.75$0.01$1.00
38PCC driveway pavt 8 (42300400)SY418$14.00$125.00$86.32$105.00$71.82$83.00
39PC conc sidewalk 5 (42400200)SF6,077$12.00$8.50$9.88$9.50$8.01$10.00
40Detectable warnings (42400800)SF347$47.00$25.00$40.66$33.00$33.11$39.00
41Pavement rem (44000100)SY43$18.00$25.50$42.16$22.00$32.66$67.00
42Drive pavement rem (44000200)SY418$18.00$24.75$21.20$16.50$26.66$26.00
43Curb rem (44000300)LF181$8.00$8.25$13.34$10.00$10.51$20.00
44Comb curb gutter rem (44000500)LF275$8.00$8.75$13.77$10.00$9.96$34.00
45Sidewalk rem (44000600)SF9,093$1.90$2.05$2.85$2.25$2.52$4.00
46Fire hydnts to BE rem (56400500)EACH5$1,200.00$1,880.00$1,436.61$2,060.00$11,285$3,460.00
47Fire hydrants (56400600)EACH5$11,800$11,285$11,103$12,350$1,880.00$12,080
48CB adjust (60250200)EACH1$600.00$450.00$1,665.52$500.00$450.00$899.00
49CB adj new T1F CL (60250500)EACH2$690.00$1,150.00$2,062.38$1,275.00$1,150.00$1,289.00
50Man adjust (60255500)EACH1$600.00$685.00$1,665.52$740.00$685.00$899.00
51VV adjust (60265700)EACH9$600.00$753.50$832.76$740.00$685.00$899.00
52Conc curb TB (60600605)LF181$67.00$53.00$37.34$37.00$26.67$36.00
53Comb CC&G TB6.12 (60603800)LF275$51.00$48.00$39.78$37.00$31.25$38.00
54Non SPL waste disposl (66900200)CY450$89.00$75.00$85.70$105.00$109.49$99.00
55Soil disposal analy (66900530)EACH1$2,000.00$1,550.00$1,612.00$1,700.00$1,550.00$1,550.00
56Reg sub P-const plan (66901001)LS1$3,200.00$3,400.00$3,536.00$3,800.00$3,400.00$3,400.00
57Reg sub F con report (66901003)LS1$2,700.00$500.00$520.00$550.00$500.00$500.00
58Reg sub mon (66901006)CAL DAY8$1,200.00$700.00$728.00$825.00$700.00$700.00
59Engr field office A (67000400)CAL MO6$3,200.00$1,000.00$4,678.94$3,000.00$3,000.00$2,500.00
60Mobilization (67100100)LS1$49,371$58,150$58,873$11,000$54,321$29,000
61TR cont & prot 701501 (70102620)LS1$8,000.00$87,450$60,169$4,500.00$41,167$11,725
62TR cont & prot 701701 (70102635)LS1$100.00$5,740.00$1.04$1.00$129.76$100.00
63TR cont & prot 701801 (70102640)LS1$9,600.00$5,740.00$4,160.00$9,500.00$108.44$100.00
64Sign panel T1 (72000100)SF158$36.00$25.00$33.28$38.50$30.00$30.00
65Remov sign panel T1 (72400310)SF14$42.00$28.00$15.60$44.00$20.00$20.00
66Teles STL sin support (72800100)LF238$30.00$18.00$20.80$28.00$15.00$15.00
67Wood sin support (73000100)LF36$44.00$15.00$26.00$44.00$30.00$30.00
68THPL PVT MK line 6 (78000400)LF282$7.00$1.85$4.94$550.00$4.75$3.00
69THPL PVT MK line 12 (78000600)LF550$11.00$3.60$9.88$10.75$9.50$9.50
70PVT MKG rem WTR blast (78300202)SF300$6.00$15.00$14.04$20.00$10.00$10.00
71Conc FDN TY A (87800100)LF8$390.00$354.00$378.72$400.00$344.04$589.00
IDOT contract 61K79: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of April 25, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy