IDOT contract 62G55 bid tabulation
Section 2018-036-RS-SW. Let by Illinois DOT on March 7, 2025, Will, District 01. 6 bids received; low bid $1,427,655 by Gallagher Asphalt Corporation.
- Owner
- Illinois DOT
- Letting
- 07 MAR 2025
- Pay items
- 66
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Gallagher Asphalt Corporation | $1,427,655 | Low |
| 2 | K-Five Construction Corporation | $1,456,611 | +2.0% |
| 3 | P. T. Ferro Construction Co. | $1,490,945 | +4.0% |
| 4 | D. Construction, Inc. | $1,535,597 | +8.0% |
| 5 | Austin Tyler Construction, Inc. | $1,556,297 | +9.0% |
| 6 | Builders Paving, LLC | $1,681,551 | +18% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Gallagher Asphalt Corporation | 2. K-Five Construction Corporation | 3. P. T. Ferro Construction Co. | 4. D. Construction, Inc. | 5. Austin Tyler Construction, Inc. | 6. Builders Paving, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Selective clearing (X2010516) | UNIT | 4 | $400.00 | $400.00 | $400.00 | $440.00 | $400.00 | $750.00 |
| 2 | Grading & shap SHLDRS (X2020110) | UNIT | 72 | $74.00 | $85.00 | $75.00 | $60.00 | $150.00 | $50.00 |
| 3 | CC&G RMVL repl < = 10 (X4400501) | LF | 60 | $165.00 | $135.00 | $100.00 | $50.00 | $92.00 | $90.00 |
| 4 | CC&G RMVL repl > 10FT (X4400503) | LF | 80 | $130.00 | $125.00 | $100.00 | $45.00 | $62.00 | $75.00 |
| 5 | SS cleaned 12 (X5537800) | LF | 90 | $2.00 | $2.00 | $14.00 | $2.20 | $5.00 | $2.00 |
| 6 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 12 | $500.00 | $3,300.00 | $0.01 | $5,000.00 | $3,000.00 | $3,250.00 |
| 7 | Construction layout (Z0013798) | LS | 1 | $3,700.00 | $3,100.00 | $0.01 | $5,000.00 | $4,500.00 | $10,000 |
| 8 | Drainage STR cleaned (Z0018500) | EACH | 6 | $400.00 | $400.00 | $375.00 | $440.00 | $300.00 | $400.00 |
| 9 | Temp info signing (Z0030850) | SF | 150 | $12.00 | $30.00 | $30.00 | $25.00 | $19.58 | $18.00 |
| 10 | Earth excavation (20200100) | CY | 115 | $140.00 | $125.00 | $40.00 | $50.00 | $85.00 | $75.00 |
| 11 | Rem & disp uns matl (20201200) | CY | 206 | $136.00 | $65.00 | $35.00 | $40.00 | $55.00 | $75.00 |
| 12 | Furnished excavation (20400800) | CY | 392.40 | $55.00 | $0.01 | $15.00 | $30.00 | $60.00 | $60.00 |
| 13 | Topsoil F & P 4 (21101615) | SY | 4,634 | $7.00 | $7.50 | $0.01 | $8.25 | $6.00 | $7.50 |
| 14 | Grading & shap ditch (21400100) | LF | 360 | $14.70 | $22.50 | $10.00 | $15.00 | $25.00 | $17.00 |
| 15 | Seeding CL 2A (25000210) | ACRE | 0.08 | $2,420.00 | $11,500 | $20,000 | $12,650 | $5,000.00 | $11,500 |
| 16 | Erosion contr blanket (25100630) | SY | 1,440 | $6.00 | $1.25 | $16.00 | $1.38 | $1.50 | $1.25 |
| 17 | Sodding salt tolerant (25200110) | SY | 31 | $100.00 | $125.00 | $50.00 | $137.50 | $30.00 | $125.00 |
| 18 | Supple watering (25200200) | UNIT | 0.30 | $500.00 | $25.00 | $1,000.00 | $27.50 | $500.00 | $25.00 |
| 19 | Stone riprap CL A4 (28100107) | SY | 133.33 | $100.00 | $75.00 | $60.00 | $80.00 | $140.00 | $125.00 |
| 20 | Bit matls tack CT (40600290) | LB | 28,864 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 21 | Long joint sealant (40600370) | LF | 14,126 | $2.90 | $2.65 | $2.90 | $3.52 | $2.75 | $3.00 |
| 22 | Mix CR JTS flangewys (40600400) | TON | 65 | $50.00 | $50.00 | $0.01 | $0.01 | $340.00 | $250.00 |
| 23 | HMA surf rem butt JT (40600982) | SY | 197 | $16.00 | $0.01 | $0.01 | $0.01 | $0.01 | $20.00 |
| 24 | P HMA BC IL-4.75 N50 (40603200) | TON | 1,764 | $111.00 | $115.00 | $102.00 | $100.00 | $95.00 | $81.00 |
| 25 | P HMA SC SMA 9.5 F N80 (40605026) | TON | 4,191 | $123.00 | $117.00 | $120.00 | $111.50 | $110.00 | $108.00 |
| 26 | Protective coat (42001300) | SY | 20 | $10.00 | $55.00 | $10.00 | $1.00 | $10.00 | $10.00 |
| 27 | HMA surf rem 2 1/2 (44000159) | SY | 42,761 | $2.80 | $2.75 | $3.50 | $2.45 | $2.50 | $5.00 |
| 28 | CL D patch T1 14 (44201811) | SY | 107 | $180.00 | $54.00 | $175.00 | $150.00 | $165.00 | $205.00 |
| 29 | CL D patch T2 14 (44201815) | SY | 856 | $76.00 | $54.00 | $155.00 | $135.00 | $140.00 | $165.00 |
| 30 | CL D patch T3 14 (44201819) | SY | 642 | $72.00 | $54.00 | $135.00 | $130.00 | $135.00 | $150.00 |
| 31 | CL D patch T4 14 (44201821) | SY | 535 | $70.00 | $54.00 | $110.00 | $130.00 | $125.00 | $140.00 |
| 32 | Agg wedge SHLD type B (48102100) | TON | 146 | $75.00 | $75.00 | $45.00 | $40.00 | $65.00 | $50.00 |
| 33 | CB adjust (60250200) | EACH | 1 | $915.00 | $1,500.00 | $1,000.00 | $800.00 | $350.00 | $850.00 |
| 34 | Pipe culv cleaned 18 (60920018) | LF | 393 | $4.50 | $4.50 | $7.00 | $4.95 | $25.00 | $4.50 |
| 35 | Pipe culv cleaned 24 (60920024) | LF | 46 | $5.50 | $5.50 | $30.00 | $6.05 | $50.00 | $5.50 |
| 36 | Non SPL waste disposl (66900200) | CY | 321 | $0.01 | $65.00 | $85.00 | $75.00 | $73.00 | $100.00 |
| 37 | Soil disposal analy (66900530) | EACH | 2 | $1,500.00 | $1,500.00 | $1,500.00 | $1,650.00 | $1,750.00 | $1,750.00 |
| 38 | Reg sub P-const plan (66901001) | LS | 1 | $3,400.00 | $3,400.00 | $3,400.00 | $2,250.00 | $2,300.00 | $2,300.00 |
| 39 | Reg sub F con report (66901003) | LS | 1 | $500.00 | $500.00 | $500.00 | $2,250.00 | $2,100.00 | $2,300.00 |
| 40 | Reg sub mon (66901006) | CAL DAY | 5 | $700.00 | $700.00 | $700.00 | $900.00 | $990.00 | $990.00 |
| 41 | Mobilization (67100100) | LS | 1 | $82,000 | $85,000 | $84,000 | $92,000 | $90,000 | $89,000 |
| 42 | Traf cont-prot 701306 (70100460) | LS | 1 | $500.00 | $500.00 | $50.00 | $0.01 | $1.00 | $1,000.00 |
| 43 | TR cont & prot 701502 (70102622) | LS | 1 | $3,600.00 | $500.00 | $50.00 | $0.01 | $1.00 | $1,000.00 |
| 44 | TR cont & prot 701602 (70102632) | LS | 1 | $3,600.00 | $81,000 | $35,000 | $73,900 | $7,700.00 | $35,000 |
| 45 | TR cont & prot 701701 (70102635) | LS | 1 | $1.00 | $1,000.00 | $500.00 | $0.01 | $1.00 | $1,000.00 |
| 46 | Short term pavt mking (70300100) | LF | 15,670 | $1.90 | $1.00 | $0.01 | $0.01 | $2.00 | $0.50 |
| 47 | SHRT TRM pavt MK rem (70300150) | SF | 5,224 | $0.01 | $2.00 | $0.01 | $0.01 | $3.00 | $3.00 |
| 48 | Temp PVT MK LTR & sym paint (70300211) | SF | 447 | $0.01 | $1.89 | $0.01 | $0.01 | $2.35 | $2.35 |
| 49 | Temp PVT MK line 4 - paint (70300221) | LF | 24,840 | $0.01 | $0.32 | $0.01 | $0.01 | $0.40 | $0.40 |
| 50 | Temp PVT MK line 6 - paint (70300241) | LF | 2,319 | $0.01 | $0.48 | $0.01 | $0.01 | $0.60 | $0.60 |
| 51 | Temp PVT MK line 8 - paint (70300251) | LF | 762 | $0.01 | $0.63 | $0.01 | $0.01 | $0.80 | $0.80 |
| 52 | Temp PVT MK line 12 - paint (70300261) | LF | 1,886 | $0.01 | $0.95 | $0.01 | $0.01 | $1.20 | $1.20 |
| 53 | Temp PVT MK line 24 - paint (70300281) | LF | 174 | $0.01 | $1.89 | $0.01 | $0.01 | $2.35 | $2.35 |
| 54 | Temp PVT MK L4 T4 tape (70307120) | LF | 3,918 | $1.40 | $2.00 | $0.01 | $0.01 | $2.00 | $0.50 |
| 55 | THPL PVT MK LTR & sym (78000100) | SF | 447 | $5.25 | $5.25 | $5.25 | $5.78 | $4.50 | $5.25 |
| 56 | THPL PVT MK line 4 (78000200) | LF | 24,840 | $0.65 | $0.65 | $0.65 | $0.72 | $0.63 | $0.65 |
| 57 | THPL PVT MK line 6 (78000400) | LF | 2,319 | $0.75 | $0.75 | $0.75 | $0.83 | $1.15 | $0.75 |
| 58 | THPL PVT MK line 8 (78000500) | LF | 762 | $1.95 | $1.95 | $1.95 | $2.15 | $1.50 | $1.95 |
| 59 | THPL PVT MK line 12 (78000600) | LF | 1,886 | $2.65 | $2.65 | $2.65 | $2.92 | $2.25 | $2.65 |
| 60 | THPL PVT MK line 24 (78000650) | LF | 174 | $5.75 | $5.75 | $5.75 | $6.33 | $4.50 | $5.75 |
| 61 | Raised refl pavt MKR (78100100) | EACH | 467 | $34.00 | $33.54 | $45.00 | $36.89 | $42.10 | $33.50 |
| 62 | Raised ref PVT MK rem (78300200) | EACH | 467 | $0.01 | $10.55 | $0.01 | $6.00 | $14.00 | $15.00 |
| 63 | Main EX TR sig instal (85000200) | EACH | 1 | $1,850.00 | $1,711.24 | $1,712.00 | $1,882.36 | $1,711.24 | $1,750.00 |
| 64 | Elcbl C lead 14 1PR (87301305) | LF | 2,139 | $1.70 | $1.63 | $1.65 | $1.79 | $1.63 | $1.65 |
| 65 | Inductive loop detect (88500100) | EACH | 4 | $280.00 | $263.35 | $264.00 | $289.69 | $263.35 | $265.00 |
| 66 | Det loop T1 (88600100) | LF | 601 | $18.00 | $17.63 | $17.70 | $19.39 | $17.63 | $17.65 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of March 7, 2025. Compiled by Mirage Metrics.