IDOT contract 62R99 bid tabulation
Section FAP. Let by Illinois DOT on January 17, 2025, Cook, District 01. 5 bids received; low bid $1,945,196 by Martam Construction Incorporated.
- Owner
- Illinois DOT
- Letting
- 17 JAN 2025
- Pay items
- 62
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Martam Construction Incorporated | $1,945,196 | Low |
| 2 | Rausch Infrastructure, LLC | $2,155,853 | +11% |
| 3 | Areatha Construction Co., Inc. | $2,167,078 | +11% |
| 4 | D. Construction, Inc. | $2,169,326 | +12% |
| 5 | Lorig Construction Company | $2,284,093 | +17% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Martam Construction Incorporated | 2. Rausch Infrastructure, LLC | 3. Areatha Construction Co., Inc. | 4. D. Construction, Inc. | 5. Lorig Construction Company |
|---|---|---|---|---|---|---|---|---|
| 1 | Acrylic coating (X0325748) | SY | 34.10 | $98.00 | $78.00 | $70.00 | $110.00 | $85.00 |
| 2 | Fiber wrap (X0325749) | SF | 307 | $85.00 | $84.00 | $75.00 | $77.00 | $80.00 |
| 3 | Structure adj (X0326862) | EACH | 5 | $800.00 | $1,000.00 | $1,393.75 | $0.01 | $2,200.00 |
| 4 | CC&G RMVL repl < = 10 (X4400501) | LF | 100 | $85.00 | $130.00 | $70.00 | $50.00 | $180.00 |
| 5 | CC&G RMVL repl > 10FT (X4400503) | LF | 100 | $72.00 | $125.00 | $70.00 | $50.00 | $150.00 |
| 6 | CL D patch T4 10 SPL (X4421768) | SY | 749 | $115.00 | $94.00 | $30.00 | $112.00 | $89.00 |
| 7 | BR deck grooving long (X5030250) | SY | 4,120 | $4.20 | $4.00 | $3.70 | $4.50 | $4.00 |
| 8 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 12 | $3,200.00 | $5,500.00 | $2,500.00 | $5,000.00 | $3,500.00 |
| 9 | Traf cont & prot SPL (X7010216) | LS | 1 | $112,000 | $38,000 | $25,500 | $55,000 | $300,000 |
| 10 | RRPM reflector removl (X7830050) | EACH | 40 | $20.00 | $14.00 | $12.50 | $10.00 | $13.00 |
| 11 | RRPM reflector replac (X7830052) | EACH | 40 | $20.00 | $16.00 | $15.00 | $16.50 | $25.00 |
| 12 | Det loop repl (X8860105) | LF | 140 | $30.00 | $31.00 | $111.20 | $31.15 | $38.00 |
| 13 | BR DK LTX C oly 2 3/4 (Z0006016) | SY | 4,542 | $114.00 | $98.00 | $131.10 | $107.00 | $105.00 |
| 14 | Clean drainage system (Z0010605) | LS | 1 | $6,000.00 | $32,000 | $7,145.80 | $15,000 | $100.00 |
| 15 | BR deck scar 3/4 (Z0012130) | SY | 4,542 | $44.00 | $38.00 | $73.30 | $45.00 | $62.00 |
| 16 | STR rep con DP = < 5 (Z0012754) | SF | 153 | $200.00 | $213.00 | $192.60 | $165.00 | $225.00 |
| 17 | STR rep con DP over 5 (Z0012755) | SF | 41 | $209.00 | $223.00 | $208.75 | $200.00 | $300.00 |
| 18 | Deck slab rep (FD-T1) (Z0016001) | SY | 7 | $3,200.00 | $3,900.00 | $1,613.45 | $2,500.00 | $4,500.00 |
| 19 | Deck slab rep (FD-T2) (Z0016002) | SY | 1 | $3,000.00 | $18,000 | $1,611.55 | $5,000.00 | $4,000.00 |
| 20 | Drainage scuppers adj (Z0018051) | EACH | 8 | $1,200.00 | $1,100.00 | $1,011.70 | $800.00 | $1,000.00 |
| 21 | Diamond grind BR sec (Z0029090) | SY | 4,206 | $6.60 | $6.00 | $7.55 | $7.00 | $6.25 |
| 22 | Temp info signing (Z0030850) | SF | 58 | $20.00 | $22.00 | $20.00 | $25.00 | $22.00 |
| 23 | Polymer concrete (Z0041895) | CF | 10 | $950.00 | $1,200.00 | $1,657.10 | $1,750.00 | $2,200.00 |
| 24 | RR prot liability ins (Z0048665) | LS | 1 | $8,000.00 | $27,000 | $50,000 | $7,500.00 | $12,000 |
| 25 | Temp shoring & crib (Z0073200) | EACH | 5 | $9,800.00 | $9,500.00 | $5,500.00 | $10,000 | $5,000.00 |
| 26 | Temp TR signal timing (Z0073510) | EACH | 2 | $900.00 | $675.00 | $600.00 | $910.80 | $1,000.00 |
| 27 | Bit matls tack CT (40600290) | LB | 198 | $0.10 | $0.01 | $10.00 | $0.01 | $0.10 |
| 28 | Mix CR JTS flangewys (40600400) | TON | 20 | $250.00 | $268.00 | $635.00 | $0.01 | $250.00 |
| 29 | PCC surf rem butt JT (40600985) | SY | 525 | $12.00 | $21.00 | $11.30 | $0.01 | $20.00 |
| 30 | P HMA SC IL-9.5 E N70 (40604172) | TON | 387 | $156.00 | $157.00 | $132.00 | $170.00 | $145.00 |
| 31 | CL D patch T2 10 (44201765) | SY | 64 | $120.00 | $109.00 | $77.00 | $175.00 | $105.00 |
| 32 | Conc rem (50102400) | CY | 60.10 | $1,800.00 | $2,200.00 | $2,159.00 | $2,500.00 | $2,600.00 |
| 33 | Protective shield (50157300) | SY | 1,767 | $32.00 | $102.00 | $5.00 | $85.00 | $45.00 |
| 34 | Conc sup-STR (50300255) | CY | 67.10 | $2,100.00 | $3,300.00 | $3,442.00 | $3,000.00 | $2,000.00 |
| 35 | Protective coat (50300300) | SY | 5,332 | $1.00 | $5.00 | $1.75 | $3.00 | $1.65 |
| 36 | Reinf bars, epoxy CTD (50800205) | LB | 9,460 | $3.00 | $2.00 | $3.25 | $3.00 | $2.75 |
| 37 | Bar splicers (50800515) | EACH | 84 | $63.00 | $139.00 | $37.40 | $45.00 | $90.00 |
| 38 | Pref joint seal 2 (52000025) | LF | 42 | $95.00 | $487.00 | $89.00 | $120.00 | $115.00 |
| 39 | Pref JT strip seal (52000110) | LF | 349 | $235.00 | $286.00 | $414.65 | $250.00 | $310.00 |
| 40 | Concrete sealer (58700300) | SF | 1,955 | $2.00 | $2.00 | $3.40 | $3.00 | $4.00 |
| 41 | Epoxy crack injection (59000200) | LF | 111 | $66.00 | $67.00 | $60.00 | $100.00 | $54.00 |
| 42 | Mobilization (67100100) | LS | 1 | $110,000 | $129,000 | $131,100 | $122,750 | $110,000 |
| 43 | Changeable message SN (70107025) | CAL DAY | 84 | $35.00 | $56.00 | $50.00 | $85.00 | $55.00 |
| 44 | Temp PVT MK LTR & sym T4 tape (70307100) | SF | 73 | $11.00 | $8.10 | $7.20 | $5.00 | $7.50 |
| 45 | Temp PVT MK L4 T4 tape (70307120) | LF | 12,636 | $1.30 | $1.30 | $1.20 | $3.00 | $1.20 |
| 46 | Temp PVT MK L6 T4 tape (70307130) | LF | 38 | $7.00 | $2.00 | $1.80 | $4.00 | $2.00 |
| 47 | Temp PVT MK L24 T4 tape (70307210) | LF | 13 | $22.00 | $8.10 | $7.20 | $6.00 | $8.00 |
| 48 | Temp conc barrier (70400100) | LF | 1,000 | $22.00 | $29.00 | $33.95 | $30.00 | $27.00 |
| 49 | Rel temp conc barrier (70400200) | LF | 1,000 | $8.00 | $4.00 | $6.25 | $15.00 | $6.00 |
| 50 | Imp attn temp FRD TL2 (70600235) | EACH | 2 | $4,800.00 | $4,900.00 | $4,368.00 | $6,500.00 | $6,500.00 |
| 51 | Imp attn rel FRN TL2 (70600322) | EACH | 2 | $2,200.00 | $2,200.00 | $1,988.00 | $2,000.00 | $5,000.00 |
| 52 | THPL PVT MK LTR & sym (78000100) | SF | 73 | $9.00 | $5.90 | $5.25 | $5.78 | $7.20 |
| 53 | THPL PVT MK line 4 (78000200) | LF | 6,272 | $1.30 | $0.80 | $0.80 | $0.86 | $1.20 |
| 54 | THPL PVT MK line 6 (78000400) | LF | 514 | $2.20 | $1.50 | $1.35 | $1.49 | $1.80 |
| 55 | THPL PVT MK line 12 (78000600) | LF | 165 | $4.40 | $2.90 | $2.65 | $2.92 | $7.20 |
| 56 | Pref PL PM TD STD L 7 (78004635) | LF | 388 | $16.00 | $12.90 | $11.50 | $12.65 | $10.00 |
| 57 | Mod ureth PM line 4 (78009004) | LF | 4,376 | $2.20 | $1.50 | $1.40 | $1.54 | $2.00 |
| 58 | Mod ureth PM line 12 (78009012) | LF | 112 | $7.00 | $4.70 | $4.20 | $4.62 | $6.10 |
| 59 | GRV RCSD PVT MRKG 8 (78011040) | LF | 388 | $8.00 | $7.80 | $7.00 | $7.70 | $9.20 |
| 60 | Raised refl pavt MKR (78100100) | EACH | 16 | $260.00 | $300.00 | $270.00 | $297.00 | $235.00 |
| 61 | Raised ref PVT MK rem (78300200) | EACH | 16 | $30.00 | $11.20 | $15.00 | $10.00 | $25.00 |
| 62 | PVT MKG rem WTR blast (78300202) | SF | 7,994 | $1.30 | $1.10 | $1.00 | $5.00 | $1.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 17, 2025. Compiled by Mirage Metrics.