INDOT contract B-40891-A bid tabulation
BRIDGE REPLACEMENT. Let by Indiana DOT on April 8, 2026, Jackson, Seymour. 7 bids received; low bid $1,431,389 by Force Construction Co Inc.
- Owner
- Indiana DOT
- Letting
- 08 APR 2026
- Pay items
- 70
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Force Construction Co Inc | $1,431,389 | Low |
| 2 | Dave O'Mara Contractor Inc | $1,438,800 | +1.0% |
| 3 | Milestone Contractors LP | $1,480,799 | +3.0% |
| 4 | Sunesis Construction Company | $1,603,388 | +12% |
| 5 | American Contracting & Services Inc | $1,762,046 | +23% |
| 6 | E & B Paving LLC | $1,876,000 | +31% |
| 7 | Ragle, Inc. | $2,130,235 | +49% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Force Construction Co Inc | 2. Dave O'Mara Contractor Inc | 3. Milestone Contractors LP | 4. Sunesis Construction Company | 5. American Contracting & Services Inc | 6. E & B Paving LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $10,300 | $9,347.50 | $29,000 | $18,139 | $20,000 | $40,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $70,000 | $52,107 | $74,500 | $177,865 | $88,102 | $93,800 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $17,680 | $14,000 | $14,500 | $3,036.68 | $17,620 | $18,760 |
| 0011 | Present structure, remove, structure no. 1 (202-51330) | LS | 1 | $13,300 | $30,000 | $50,200 | $14,260 | $15,000 | $48,809 |
| 0012 | Excavation, common (203-02000) | CYS | 1,598 | $30.00 | $30.00 | $22.00 | $43.01 | $75.00 | $64.00 |
| 0013 | Borrow (203-02070) | CYS | 1,610 | $34.00 | $21.00 | $29.00 | $1.37 | $30.00 | $20.00 |
| 0014 | Pump around (205-11626) | EACH | 3 | $6,130.00 | $22,000 | $9,500.00 | $12,456 | $7,000.00 | $26,000 |
| 0015 | Stormwater management budget (205-12108) | DOL | 26,603 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0016 | Stormwater management implementation (205-12616) | LS | 1 | $7,759.00 | $37,000 | $11,500 | $5,260.36 | $25,000 | $18,000 |
| 0017 | SWQCP preparation (205-12618) | LS | 1 | $2,574.00 | $3,500.00 | $2,100.00 | $8,021.54 | $5,000.00 | $3,260.00 |
| 0018 | Cofferdam (206-51235) | LS | 1 | $30,000 | $60,000 | $58,000 | $42,330 | $85,000 | $90,000 |
| 0019 | Subgrade treatment, type II (207-08264) | SYS | 253 | $28.00 | $16.00 | $19.00 | $25.03 | $30.00 | $40.00 |
| 0020 | Subgrade treatment, type IC (207-09935) | SYS | 337 | $48.00 | $35.00 | $32.00 | $34.40 | $55.00 | $48.00 |
| 0021 | Structure backfill, type 4 (211-09267) | CYS | 13 | $371.00 | $300.00 | $350.00 | $121.37 | $500.00 | $425.00 |
| 0022 | Geotextile for pavement, type 2B (214-12239) | SYS | 565 | $4.20 | $3.50 | $6.50 | $6.40 | $8.00 | $10.00 |
| 0023 | Subbase for PCCP (302-06464) | CYS | 58 | $121.00 | $80.00 | $150.00 | $148.36 | $145.00 | $152.00 |
| 0024 | Compacted aggregate, no. 53 (303-01180) | TON | 208 | $57.00 | $35.00 | $38.00 | $62.30 | $75.00 | $80.00 |
| 0025 | Compacted aggregate, no. 73 (303-07449) | TON | 53 | $50.00 | $40.00 | $60.00 | $68.12 | $80.00 | $80.00 |
| 0026 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 251 | $23.00 | $18.00 | $21.00 | $19.21 | $30.00 | $27.00 |
| 0027 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 42 | $234.00 | $180.00 | $259.00 | $229.26 | $180.00 | $250.00 |
| 0028 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 38 | $244.00 | $180.00 | $256.00 | $239.13 | $180.00 | $200.00 |
| 0029 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 99 | $198.00 | $180.00 | $176.00 | $193.38 | $180.00 | $125.00 |
| 0030 | Guardrail transition, type TGB (601-01522) | EACH | 1 | $2,934.00 | $2,850.00 | $2,850.00 | $2,872.03 | $2,850.00 | $2,850.00 |
| 0031 | Guardrail connector system, W-beam, curved, type 2 (601-01626) | EACH | 2 | $2,265.00 | $2,200.00 | $2,200.00 | $2,217.01 | $2,200.00 | $2,200.00 |
| 0032 | Guardrail end treatment, type I (601-06037) | EACH | 2 | $1,699.00 | $1,650.00 | $1,650.00 | $1,662.76 | $1,650.00 | $1,650.00 |
| 0033 | Guardrail transition, MGS without curb (601-12292) | EACH | 3 | $3,295.00 | $3,200.00 | $3,200.00 | $3,224.74 | $3,200.00 | $3,200.00 |
| 0034 | Guardrail end treatment, type OS (601-94689) | EACH | 2 | $2,368.00 | $2,300.00 | $2,300.00 | $2,317.78 | $2,300.00 | $2,300.00 |
| 0035 | Barrier delineator (602-06729) | EACH | 10 | $46.00 | $25.00 | $500.00 | $12.09 | $50.00 | $42.00 |
| 0036 | Reinforced concrete bridge approach, 10 in. (609-06257) | SYS | 228 | $161.00 | $175.00 | $254.00 | $289.10 | $260.00 | $235.00 |
| 0037 | Riprap, revetment (616-06405) | TON | 501 | $77.00 | $65.00 | $54.00 | $45.57 | $75.00 | $125.00 |
| 0038 | Geotextile for riprap, type 1A (616-12246) | SYS | 782 | $3.40 | $2.00 | $2.30 | $2.48 | $5.00 | $2.00 |
| 0039 | Erosion control blanket (621-02770) | SYS | 2,435 | $1.50 | $3.00 | $3.00 | $3.02 | $1.50 | $1.50 |
| 0040 | Mulched seeding, type R (621-06559) | SYS | 2,475 | $1.30 | $3.50 | $3.50 | $5.00 | $1.25 | $1.25 |
| 0041 | Seed mixture, floodplain (621-12612) | LBS | 11 | $232.00 | $275.00 | $275.00 | $442.95 | $225.00 | $225.00 |
| 0042 | Computer system equipment (628-11976) | EACH | 2 | $824.00 | $900.00 | $600.00 | $1,112.33 | $1,000.00 | $500.00 |
| 0043 | Field office, type D (628-12683) | MOS | 12 | $4,118.00 | $2,700.00 | $3,600.00 | $2,699.18 | $5,500.00 | $2,850.00 |
| 0044 | Dynamic pile load test (701-06011) | EACH | 4 | $9,205.00 | $7,290.00 | $7,050.00 | $4,271.59 | $6,500.00 | $6,500.00 |
| 0045 | Test pile, dynamic, production (701-09557) | LFT | 290 | $117.00 | $75.00 | $55.00 | $100.58 | $130.00 | $175.00 |
| 0046 | Test pile, dynamic, restrike (701-09559) | EACH | 4 | $2,966.00 | $800.00 | $4,800.00 | $3,767.72 | $6,000.00 | $3,200.00 |
| 0047 | Pile, steel pipe, 0.250 in., diameter 14 in. (701-09662) | LFT | 1,792 | $79.00 | $110.00 | $102.00 | $105.92 | $110.00 | $120.00 |
| 0048 | Concrete, A, substructure (702-51005) | CYS | 132 | $997.00 | $730.00 | $920.00 | $910.78 | $1,050.00 | $1,050.00 |
| 0049 | Concrete, B, footings (702-51015) | CYS | 13 | $1,197.00 | $1,100.00 | $2,580.00 | $911.52 | $1,000.00 | $1,550.00 |
| 0050 | Reinforcing bars (703-06028) | LBS | 15,276 | $1.70 | $1.40 | $1.50 | $1.47 | $1.50 | $2.00 |
| 0051 | Reinforcing bars, epoxy coated (703-06029) | LBS | 60,444 | $1.40 | $1.50 | $1.60 | $1.58 | $1.65 | $1.75 |
| 0052 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 32 | $45.00 | $31.00 | $41.00 | $56.24 | $50.00 | $42.00 |
| 0053 | Concrete, C, superstructure (704-51002) | CYS | 167.20 | $1,232.00 | $1,300.00 | $1,400.00 | $2,132.64 | $2,100.00 | $1,850.00 |
| 0054 | Railing, concrete type FC (706-11600) | CYS | 17.60 | $1,131.00 | $1,099.00 | $1,099.00 | $1,638.57 | $1,100.00 | $1,099.00 |
| 0055 | Concrete bridge railing transition, type TFC (706-11620) | EACH | 4 | $1,452.00 | $1,410.00 | $1,410.00 | $2,407.61 | $1,500.00 | $1,410.00 |
| 0056 | Surface seal (709-51821) | LS | 1 | $1.00 | $5,000.00 | $0.01 | $2,750.49 | $5,000.00 | $1.00 |
| 0057 | Pipe extension, circular, diameter 15 in. , to extend to realigned channel (715-05595) | LFT | 25 | $98.00 | $70.00 | $130.00 | $94.17 | $125.00 | $200.00 |
| 0058 | Longitudinal grooving (722-12732) | SYS | 503 | $7.10 | $7.00 | $7.50 | $7.05 | $10.00 | $10.00 |
| 0059 | Road closure sign assembly (801-04308) | EACH | 2 | $288.00 | $220.00 | $280.00 | $372.43 | $220.00 | $369.57 |
| 0060 | Detour route marker assembly (801-06625) | EACH | 19 | $118.00 | $85.00 | $115.00 | $106.98 | $85.00 | $106.16 |
| 0061 | Construction sign, type A (801-06640) | EACH | 12 | $180.00 | $150.00 | $175.00 | $209.25 | $150.00 | $207.64 |
| 0062 | Maintaining traffic (801-06775) | LS | 1 | $121,000 | $73,000 | $9,003.34 | $2,995.65 | $10,000 | $35,000 |
| 0063 | Barricade, type III-A (801-07118) | LFT | 48 | $16.00 | $14.00 | $16.00 | $17.30 | $14.00 | $17.17 |
| 0064 | Barricade, type III-B (801-07119) | LFT | 24 | $16.00 | $15.00 | $16.00 | $17.30 | $15.00 | $17.17 |
| 0065 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 13 | $63.00 | $61.00 | $61.00 | $61.47 | $61.00 | $61.00 |
| 0066 | Monument, type B (615-06505) | EACH | 1 | $2,291.00 | $2,225.00 | $2,225.00 | $2,242.20 | $2,225.00 | $2,225.00 |
| 0067 | Mobilization and demobilization for seeding (621-01004) | EACH | 4 | $206.00 | $250.00 | $250.00 | $1,007.73 | $200.00 | $200.00 |
| 0068 | Topsoil processing and distribution (629-000149) | SYS | 2,475 | $5.20 | $7.50 | $9.25 | $2.02 | $3.00 | $14.50 |
| 0069 | Topsoil amendment budget (629-000150) | DOL | 4,950 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0070 | Pipe, remove (202-96133) | LFT | 32 | $40.00 | $25.00 | $70.00 | $12.83 | $25.00 | $32.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of April 8, 2026. Compiled by Mirage Metrics.