INDOT contract B-42884-A bid tabulation
BRIDGE DECK OVERLAY. Let by Indiana DOT on September 10, 2025, Brown, Seymour. 7 bids received; low bid $485,210 by Dave Omara Contractor Inc.
- Owner
- Indiana DOT
- Letting
- 10 SEP 2025
- Pay items
- 61
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Dave Omara Contractor Inc | $485,210 | Low |
| 2 | Force Construction Co Inc | $495,000 | +2.0% |
| 3 | E & B Paving LLC | $512,500 | +6.0% |
| 4 | His Constructors Inc | $515,917 | +6.0% |
| 5 | Ragle, Inc. | $592,363 | +22% |
| 6 | William Charles Construction Company | $593,111 | +22% |
| 7 | Milestone Contractors LP | $630,480 | +30% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Dave Omara Contractor Inc | 2. Force Construction Co Inc | 3. E & B Paving LLC | 4. His Constructors Inc | 5. Ragle, Inc. | 6. William Charles Construction Company |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $4,500.00 | $6,040.00 | $10,000 | $5,000.00 | $10,500 | $25,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $26,000 | $60,000 | $24,685 | $41,598 | $29,250 | $29,000 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $8,700.00 | $10,310 | $500.00 | $10,000 | $11,750 | $25,000 |
| 0011 | Pavement removal (202-02240) | SYS | 252 | $40.00 | $29.00 | $60.00 | $87.00 | $40.00 | $40.00 |
| 0012 | Guardrail end treatment, remove (202-93741) | EACH | 4 | $225.00 | $234.00 | $225.00 | $240.00 | $500.00 | $225.00 |
| 0013 | Excavation, common (203-02000) | CYS | 120 | $225.00 | $36.00 | $120.00 | $89.00 | $75.00 | $120.00 |
| 0014 | Stormwater management budget (205-12108) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0015 | Stormwater management implementation (205-12616) | LS | 1 | $3,000.00 | $3,394.00 | $4,000.00 | $5,800.00 | $7,500.00 | $12,000 |
| 0016 | Subgrade treatment, type IC (207-09935) | SYS | 80 | $140.00 | $65.00 | $150.00 | $55.00 | $65.00 | $65.00 |
| 0017 | Geotextile for pavement, type 2B (214-12239) | SYS | 332 | $3.00 | $8.00 | $5.00 | $5.00 | $5.50 | $5.00 |
| 0018 | Subbase for PCCP (302-06464) | CYS | 64 | $160.00 | $102.00 | $120.00 | $87.00 | $175.00 | $125.00 |
| 0019 | Compacted aggregate, no. 53 (303-01180) | TON | 104 | $65.00 | $52.00 | $110.00 | $46.00 | $111.02 | $85.00 |
| 0020 | Milling, transition (306-08043) | SYS | 760 | $7.50 | $6.20 | $10.00 | $4.25 | $3.50 | $5.00 |
| 0021 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 70 | $150.00 | $234.00 | $225.00 | $240.00 | $225.00 | $225.00 |
| 0022 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 11 | $150.00 | $557.00 | $535.00 | $571.00 | $535.00 | $535.00 |
| 0023 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 27 | $150.00 | $266.00 | $255.00 | $272.00 | $255.00 | $255.00 |
| 0024 | Joint adhesive (401-11526) | LFT | 690 | $1.00 | $2.20 | $2.10 | $2.24 | $2.10 | $2.10 |
| 0025 | Asphalt for tack coat (406-05521) | SYS | 920 | $0.50 | $0.25 | $0.25 | $0.27 | $0.25 | $0.25 |
| 0026 | Guardrail, remove (601-02241) | LFT | 525 | $4.00 | $4.20 | $4.00 | $4.27 | $7.00 | $4.00 |
| 0027 | Guardrail transition, MGS without curb (601-12292) | EACH | 4 | $2,900.00 | $3,020.00 | $2,900.00 | $3,000.00 | $2,900.00 | $2,900.00 |
| 0028 | Guardrail end treatment, type OS (601-94689) | EACH | 4 | $3,000.00 | $3,124.00 | $3,000.00 | $3,200.00 | $3,000.00 | $3,000.00 |
| 0029 | Reinforced concrete bridge approach, 10 in. (609-06257) | SYS | 252 | $200.00 | $166.00 | $250.00 | $273.00 | $210.00 | $250.00 |
| 0030 | Riprap, revetment (616-06405) | TON | 47 | $125.00 | $71.00 | $200.00 | $118.00 | $110.00 | $135.00 |
| 0031 | Geotextile for riprap, type 2A (616-12248) | SYS | 96 | $3.50 | $11.00 | $10.00 | $13.00 | $13.50 | $11.00 |
| 0032 | Mobilization and demobilization for seeding (621-01004) | EACH | 1 | $1,500.00 | $521.00 | $1,200.00 | $1,281.00 | $500.00 | $500.00 |
| 0033 | Mulched seeding, type R (621-06559) | SYS | 396 | $9.00 | $10.00 | $5.00 | $8.00 | $10.00 | $10.00 |
| 0034 | Water (621-06567) | KGAL | 1 | $10.00 | $0.10 | $25.00 | $26.00 | $0.10 | $0.10 |
| 0035 | Sodding, nursery (621-06575) | SYS | 30 | $125.00 | $139.00 | $100.00 | $106.00 | $140.00 | $133.00 |
| 0036 | Computer system equipment (628-11976) | EACH | 2 | $900.00 | $891.00 | $500.00 | $600.00 | $1,000.00 | $1,250.00 |
| 0037 | Field office, type D (628-12683) | MOS | 6 | $2,500.00 | $3,957.00 | $3,000.00 | $2,500.00 | $3,100.00 | $3,500.00 |
| 0038 | Field drilled hole in concrete (702-51863) | EACH | 78 | $18.00 | $21.00 | $25.00 | $43.00 | $22.50 | $30.00 |
| 0039 | Reinforcing bars, epoxy coated (703-06029) | LBS | 16,540 | $2.00 | $1.60 | $2.00 | $1.52 | $2.00 | $1.95 |
| 0040 | Concrete bridge railing transition, type TFC , modified (706-11620) | EACH | 4 | $6,500.00 | $3,709.00 | $2,500.00 | $7,100.00 | $5,000.00 | $6,595.00 |
| 0041 | Surface seal , bridge no. 1 (709-51821) | LS | 1 | $2,653.00 | $2,763.00 | $3,000.00 | $3,000.00 | $2,653.00 | $4,155.00 |
| 0042 | Patching concrete structures (710-09158) | SFT | 50 | $168.00 | $43.00 | $200.00 | $363.00 | $150.00 | $168.00 |
| 0043 | Bridge deck overlay, rigid (722-000134) | SYS | 274 | $260.00 | $181.00 | $245.00 | $180.00 | $217.00 | $250.00 |
| 0044 | Hydrodemolition (722-01066) | SYS | 274 | $110.00 | $145.00 | $230.00 | $133.00 | $200.00 | $175.00 |
| 0045 | Bridge deck overlay budget (722-12380) | DOL | 1,074 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0046 | Bridge deck, remove concrete surface (722-12464) | SYS | 274 | $25.00 | $15.00 | $50.00 | $18.00 | $23.50 | $15.00 |
| 0047 | Longitudinal grooving (722-12732) | SYS | 274 | $9.00 | $11.00 | $40.00 | $9.00 | $13.50 | $12.00 |
| 0048 | Bridge deck patching, full depth (722-51401) | SFT | 70 | $115.00 | $61.00 | $25.00 | $361.00 | $125.00 | $200.00 |
| 0049 | Bridge deck patching, partial depth (722-51852) | SFT | 80 | $67.20 | $26.00 | $1.00 | $134.00 | $105.00 | $50.00 |
| 0050 | Overlay dam (722-51874) | SFT | 82 | $130.00 | $36.00 | $100.00 | $144.00 | $50.00 | $200.00 |
| 0051 | Road closure sign assembly (801-04308) | EACH | 7 | $233.00 | $312.00 | $300.00 | $321.00 | $300.00 | $300.00 |
| 0052 | Detour route marker assembly (801-06625) | EACH | 19 | $170.00 | $130.00 | $125.00 | $134.00 | $125.00 | $125.00 |
| 0053 | Construction sign, type A (801-06640) | EACH | 10 | $180.00 | $151.00 | $145.00 | $155.00 | $145.00 | $145.00 |
| 0054 | Maintaining traffic (801-06775) | LS | 1 | $13,500 | $65,646 | $5,000.00 | $2,500.00 | $104,500 | $36,013 |
| 0055 | Barricade, type III-A (801-07118) | LFT | 64 | $12.00 | $16.00 | $15.55 | $17.00 | $15.55 | $15.55 |
| 0056 | Barricade, type III-B (801-07119) | LFT | 48 | $13.00 | $16.00 | $15.55 | $17.00 | $15.55 | $15.55 |
| 0057 | Line, paint, solid, white, 6 in. (808-75007) | LFT | 683 | $2.60 | $0.80 | $0.75 | $1.00 | $0.75 | $0.75 |
| 0058 | Line, paint, solid, yellow, 6 in. (808-75047) | LFT | 683 | $2.60 | $0.80 | $0.75 | $1.00 | $0.75 | $0.75 |
| 0059 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 9 | $61.05 | $58.00 | $1.00 | $60.00 | $52.50 | $55.55 |
| 0060 | Snowplowable raised pavement marker (808-75998) | EACH | 9 | $125.00 | $78.00 | $75.00 | $80.00 | $75.00 | $75.00 |
| 0061 | Railing, remove (202-51133) | LFT | 63 | $90.00 | $63.00 | $75.00 | $50.00 | $42.50 | $115.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of September 10, 2025. Compiled by Mirage Metrics.