INDOT contract B-43600-A bid tabulation
BRIDGE REPLACEMENT. Let by Indiana DOT on October 8, 2025, Clinton, Crawfordsville. 8 bids received; low bid $1,181,697 by Duncan Robertson Inc.
- Owner
- Indiana DOT
- Letting
- 08 OCT 2025
- Pay items
- 55
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Duncan Robertson Inc | $1,181,697 | Low |
| 2 | William Charles Construction Company | $1,240,395 | +5.0% |
| 3 | Milestone Contractors LP | $1,320,550 | +12% |
| 4 | Superior Construction Co Inc | $1,331,420 | +13% |
| 5 | Beaty Construction Inc | $1,430,376 | +21% |
| 6 | Pontem Contractors Inc | $1,454,000 | +23% |
| 7 | His Constructors Inc | $1,493,565 | +26% |
| 8 | E & B Paving LLC | $1,531,500 | +30% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Duncan Robertson Inc | 2. William Charles Construction Company | 3. Milestone Contractors LP | 4. Superior Construction Co Inc | 5. Beaty Construction Inc | 6. Pontem Contractors Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $10,000 | $25,000 | $11,000 | $75,000 | $8,900.22 | $15,015 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $57,500 | $60,000 | $65,500 | $66,500 | $68,000 | $72,700 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $45,000 | $35,000 | $52,500 | $13,700 | $50,000 | $58,160 |
| 0011 | Present structure, remove, structure no. 1 (202-51330) | LS | 1 | $140,000 | $72,121 | $90,900 | $102,976 | $83,400 | $155,877 |
| 0012 | Excavation, common (203-02000) | CYS | 65 | $75.00 | $100.00 | $325.00 | $240.00 | $95.00 | $90.89 |
| 0013 | Borrow (203-02070) | CYS | 1,155 | $20.00 | $0.01 | $39.00 | $0.01 | $45.00 | $45.99 |
| 0014 | Stormwater management budget (205-12108) | DOL | 24,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0015 | Stormwater management implementation (205-12616) | LS | 1 | $18,500 | $6,000.00 | $1,300.00 | $20,000 | $7,200.00 | $19,785 |
| 0016 | Excavation, wet (206-51220) | CYS | 225 | $25.00 | $40.00 | $127.00 | $80.00 | $74.00 | $77.16 |
| 0017 | Excavation, foundation, unclassified (206-51230) | CYS | 65 | $90.00 | $35.00 | $13.00 | $40.00 | $16.00 | $62.43 |
| 0018 | Cofferdam (206-51235) | LS | 1 | $22,500 | $36,135 | $26,000 | $60,000 | $180,000 | $105,000 |
| 0019 | Subgrade treatment, type IC (207-09935) | SYS | 1,150 | $35.00 | $32.00 | $34.00 | $33.00 | $30.50 | $39.56 |
| 0020 | Structure backfill, type 4 (211-09267) | CYS | 16 | $400.00 | $325.00 | $250.00 | $190.00 | $390.00 | $223.42 |
| 0021 | Geotextile for pavement, type 2B (214-12239) | SYS | 184 | $5.00 | $10.00 | $10.00 | $8.00 | $6.00 | $10.54 |
| 0022 | Compacted aggregate, no. 53 (301-12234) | CYS | 235 | $95.00 | $85.00 | $100.00 | $80.00 | $85.00 | $84.03 |
| 0023 | Subbase for PCCP (302-06464) | CYS | 46 | $145.00 | $110.00 | $160.00 | $110.00 | $165.00 | $188.98 |
| 0024 | Compacted aggregate, no. 53 (303-01180) | TON | 295 | $70.00 | $50.00 | $65.00 | $50.00 | $51.00 | $54.00 |
| 0025 | QC/QA-HMA, 2, 58S, surface, 9.5 MM (401-000001) | TON | 80 | $193.00 | $175.60 | $175.60 | $150.00 | $175.00 | $210.00 |
| 0026 | QC/QA-HMA, 2, 58S, intermediate, 19.0 MM (401-000037) | TON | 138 | $152.00 | $138.00 | $138.00 | $125.00 | $138.00 | $178.50 |
| 0027 | Joint adhesive (401-11526) | LFT | 940 | $0.77 | $0.70 | $0.70 | $2.00 | $0.70 | $0.05 |
| 0028 | Asphalt for tack coat (406-05521) | SYS | 950 | $0.33 | $0.30 | $0.30 | $0.50 | $0.30 | $0.11 |
| 0029 | Guardrail terminal system, W-beam, curved, type 1 (601-01700) | EACH | 1 | $2,915.00 | $2,650.00 | $2,650.00 | $2,650.00 | $2,600.00 | $2,782.50 |
| 0030 | Guardrail transition, type TGS-1 , modified (601-06374) | EACH | 4 | $1,210.00 | $1,100.00 | $1,100.00 | $1,100.00 | $1,500.00 | $1,155.00 |
| 0031 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 137.50 | $22.00 | $20.00 | $20.00 | $20.00 | $29.25 | $21.00 |
| 0033 | Guardrail end treatment, type OS (601-94689) | EACH | 3 | $3,080.00 | $2,800.00 | $2,800.00 | $2,800.00 | $2,275.00 | $2,940.00 |
| 0034 | Reinforced concrete bridge approach, 10 in. (609-06257) | SYS | 180 | $235.00 | $220.00 | $210.00 | $125.00 | $215.00 | $215.16 |
| 0035 | Monument, type B (615-06505) | EACH | 2 | $990.00 | $900.00 | $900.00 | $900.00 | $1,775.00 | $945.00 |
| 0036 | Riprap, class 1 (616-05688) | TON | 355 | $115.00 | $100.00 | $147.00 | $105.00 | $76.00 | $118.63 |
| 0037 | Geotextile for riprap, type 1A (616-12246) | SYS | 395 | $3.50 | $3.55 | $1.30 | $2.00 | $3.00 | $4.21 |
| 0038 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $550.00 | $500.00 | $425.00 | $500.00 | $800.00 | $210.00 |
| 0039 | Mulched seeding, type R (621-06559) | SYS | 2,600 | $1.37 | $1.25 | $3.00 | $1.25 | $1.35 | $2.05 |
| 0040 | Field office, type C (628-09403) | MOS | 9 | $2,250.00 | $2,300.00 | $4,100.00 | $3,600.00 | $2,755.00 | $3,341.90 |
| 0041 | Dynamic pile load test (701-06011) | EACH | 4 | $4,250.00 | $6,500.00 | $7,350.00 | $10,000 | $5,700.00 | $4,884.14 |
| 0042 | Test pile, dynamic, production (701-09557) | LFT | 250 | $70.00 | $140.00 | $83.00 | $85.00 | $120.00 | $90.51 |
| 0043 | Test pile, dynamic, restrike (701-09559) | EACH | 4 | $3,750.00 | $5,500.00 | $6,100.00 | $10,000 | $5,150.00 | $4,832.45 |
| 0044 | Pile, steel pipe, 0.5 in., diameter 14 in. (701-09826) | LFT | 1,240 | $70.00 | $125.00 | $130.00 | $80.00 | $120.00 | $90.89 |
| 0045 | Concrete, A, substructure (702-51005) | CYS | 107.60 | $975.00 | $995.00 | $1,150.00 | $1,300.00 | $1,075.00 | $1,211.79 |
| 0046 | Reinforcing bars (703-06028) | LBS | 15,650 | $1.60 | $1.65 | $1.50 | $1.15 | $1.50 | $1.36 |
| 0047 | Reinforcing bars, epoxy coated (703-06029) | LBS | 43,983 | $2.00 | $2.15 | $1.60 | $1.25 | $1.55 | $1.47 |
| 0048 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 26 | $65.00 | $44.00 | $50.00 | $41.25 | $55.00 | $44.22 |
| 0049 | Concrete, C, superstructure (704-51002) | CYS | 149.20 | $1,100.00 | $1,520.00 | $1,254.00 | $1,300.00 | $1,500.00 | $1,441.97 |
| 0050 | Railing, steel type TS-1 (706-06344) | LFT | 188 | $81.50 | $81.25 | $74.00 | $74.00 | $84.00 | $77.70 |
| 0051 | Longitudinal grooving (722-12732) | SYS | 429 | $12.00 | $8.62 | $6.50 | $6.99 | $12.25 | $20.43 |
| 0052 | Road closure sign assembly (801-04308) | EACH | 4 | $284.00 | $258.00 | $350.00 | $258.00 | $350.00 | $270.90 |
| 0053 | Construction sign, type A (801-06640) | EACH | 2 | $218.00 | $198.00 | $190.00 | $198.00 | $190.00 | $207.90 |
| 0054 | Maintaining traffic (801-06775) | LS | 1 | $15,000 | $10,000 | $6,559.40 | $75,000 | $14,750 | $13,499 |
| 0055 | Barricade, type III-A (801-07118) | LFT | 48 | $16.50 | $15.17 | $20.00 | $15.17 | $20.00 | $15.93 |
| 0056 | Barricade, type III-B (801-07119) | LFT | 48 | $16.50 | $15.17 | $20.00 | $15.17 | $20.00 | $15.93 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of October 8, 2025. Compiled by Mirage Metrics.