INDOT contract B-43958-A bid tabulation
SMALL STRUCTURE REPLACEMENT. Let by Indiana DOT on October 8, 2025, Marion, Greenfield. 9 bids received; low bid $359,570 by Midwest Paving LLC.
- Owner
- Indiana DOT
- Letting
- 08 OCT 2025
- Pay items
- 57
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Midwest Paving LLC | $359,570 | Low |
| 2 | Olco Inc | $366,177 | +2.0% |
| 3 | E & B Paving LLC | $367,513 | +2.0% |
| 4 | Morphey Construction Inc. | $387,000 | +8.0% |
| 5 | Calumet Civil Contractors Inc | $421,000 | +17% |
| 6 | Rieth-Riley Construction Co., Inc. | $431,621 | +20% |
| 7 | Superior Construction Co Inc | $494,515 | +38% |
| 8 | Milestone Contractors LP | $528,800 | +47% |
| 9 | Yarberry Companies Inc | $539,071 | +50% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Midwest Paving LLC | 2. Olco Inc | 3. E & B Paving LLC | 4. Morphey Construction Inc. | 5. Calumet Civil Contractors Inc | 6. Rieth-Riley Construction Co., Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $5,000.00 | $6,000.00 | $3,000.00 | $3,000.00 | $7,500.00 | $3,000.00 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $25,500 | $14,609 | $18,000 | $16,850 | $19,198 | $49,785 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $8,600.00 | $9,796.13 | $13,000 | $3,370.00 | $6,500.00 | $4,316.20 |
| 0011 | Paved side ditch, remove (202-02272) | LFT | 86 | $25.00 | $36.73 | $15.00 | $20.00 | $21.00 | $54.94 |
| 0012 | Catch basin, remove (202-02928) | EACH | 1 | $600.00 | $1,086.51 | $715.00 | $500.00 | $1,600.00 | $1,236.50 |
| 0013 | Present structure, remove, structure no. 1 (202-51330) | LS | 1 | $15,000 | $17,476 | $16,428 | $10,000 | $5,500.00 | $5,934.74 |
| 0014 | Fence, chain link, remove (202-91840) | LFT | 100 | $38.00 | $7.24 | $10.00 | $4.00 | $5.69 | $38.00 |
| 0015 | Pipe, remove (202-96133) | LFT | 46 | $90.00 | $43.19 | $15.00 | $20.00 | $72.78 | $50.74 |
| 0016 | Excavation, common (203-02000) | CYS | 120 | $115.00 | $52.54 | $110.00 | $55.00 | $123.27 | $153.25 |
| 0017 | Pump around (205-11626) | EACH | 1 | $7,500.00 | $6,892.07 | $7,500.00 | $10,000 | $7,500.00 | $18,076 |
| 0018 | Stormwater management budget (205-12108) | DOL | 9,500 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0019 | Stormwater management implementation (205-12616) | LS | 1 | $20,000 | $4,425.05 | $4,500.00 | $1,200.00 | $16,000 | $13,236 |
| 0020 | Subgrade treatment, type II (207-08264) | SYS | 33 | $21.00 | $47.41 | $40.00 | $30.00 | $75.00 | $38.15 |
| 0021 | Subgrade treatment, type IC (207-09935) | SYS | 125 | $30.00 | $54.10 | $50.00 | $55.00 | $75.00 | $48.06 |
| 0022 | Structure backfill, type 2 (211-09265) | CYS | 71 | $61.00 | $104.88 | $155.00 | $65.00 | $80.00 | $112.74 |
| 0023 | Structure backfill, type 5 (211-09268) | CYS | 92 | $155.00 | $260.92 | $155.00 | $155.00 | $250.00 | $291.10 |
| 0024 | Geogrid, type IB (214-11796) | SYS | 33 | $9.50 | $5.48 | $10.00 | $15.00 | $24.00 | $15.68 |
| 0025 | Geotextile for pavement, type 2B (214-12239) | SYS | 125 | $9.50 | $6.46 | $10.00 | $5.00 | $9.00 | $10.60 |
| 0026 | Dense graded subbase (302-07455) | CYS | 6 | $125.00 | $151.73 | $75.00 | $165.00 | $830.00 | $151.01 |
| 0027 | Compacted aggregate, no. 53 (303-01180) | TON | 35 | $80.00 | $69.75 | $55.00 | $50.00 | $157.98 | $63.58 |
| 0028 | Milling, transition (306-08043) | SYS | 267 | $15.00 | $14.03 | $17.00 | $20.00 | $25.00 | $19.95 |
| 0029 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 31 | $320.00 | $234.96 | $264.00 | $300.00 | $230.00 | $291.92 |
| 0030 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 16 | $320.00 | $256.79 | $256.00 | $320.00 | $355.00 | $589.58 |
| 0031 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 38 | $320.00 | $180.89 | $183.00 | $280.00 | $185.73 | $288.75 |
| 0032 | Joint adhesive (401-11526) | LFT | 180 | $1.00 | $3.09 | $2.00 | $1.00 | $4.00 | $2.96 |
| 0033 | Asphalt for tack coat (406-05521) | SYS | 480 | $0.01 | $1.53 | $1.00 | $0.01 | $3.85 | $0.01 |
| 0034 | Fence, chain link, 48 in. (603-06045) | LFT | 100 | $87.00 | $87.00 | $87.00 | $87.00 | $87.00 | $87.00 |
| 0035 | PCCP for approaches, 9 in. (610-09108) | SYS | 33 | $250.00 | $237.01 | $157.00 | $115.00 | $175.00 | $96.13 |
| 0036 | Riprap, class 1 (616-05688) | TON | 49 | $85.00 | $95.72 | $155.00 | $185.00 | $130.00 | $127.79 |
| 0037 | Riprap, class 2 (616-05689) | TON | 19 | $80.00 | $104.24 | $171.00 | $195.00 | $150.00 | $152.74 |
| 0038 | Geotextile for riprap, type 1A (616-12246) | SYS | 96 | $4.80 | $5.83 | $10.00 | $5.00 | $6.00 | $9.16 |
| 0039 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $250.00 | $346.29 | $250.00 | $250.00 | $475.00 | $250.00 |
| 0040 | Mulched seeding, type R (621-06559) | SYS | 715 | $4.25 | $4.24 | $4.25 | $20.00 | $7.91 | $4.25 |
| 0041 | Field office, type C (628-09403) | MOS | 12 | $2,433.33 | $1,424.58 | $2,780.13 | $2,400.00 | $2,798.33 | $3,872.63 |
| 0042 | Waterproofing membrane, type 2 (714-000086) | SFT | 2,140 | $2.50 | $7.27 | $2.00 | $3.00 | $3.50 | $2.57 |
| 0043 | Structure, coated reinforced concrete, box sections, 8 FT X 4 FT (714-11705) | LFT | 107 | $600.00 | $964.21 | $950.00 | $1,050.00 | $900.00 | $784.79 |
| 0044 | Pipe, type 2, circular, diameter 15 in. (715-05151) | LFT | 46 | $125.00 | $154.06 | $110.00 | $160.00 | $170.00 | $92.64 |
| 0045 | Inlet, type F7 (720-45035) | EACH | 1 | $2,800.00 | $3,955.18 | $3,990.00 | $4,600.00 | $3,000.00 | $3,198.80 |
| 0046 | Perpetuation, existing pipe (725-10245) | EACH | 1 | $2,000.00 | $1,192.17 | $1,100.00 | $1,000.00 | $2,000.00 | $1,903.04 |
| 0047 | Road closure sign assembly (801-04308) | EACH | 4 | $175.00 | $175.00 | $325.00 | $325.00 | $175.00 | $325.00 |
| 0048 | Detour route marker assembly (801-06625) | EACH | 23 | $75.00 | $75.00 | $135.00 | $135.00 | $75.00 | $135.00 |
| 0049 | Construction sign, type A (801-06640) | EACH | 10 | $175.00 | $175.00 | $190.00 | $190.00 | $175.00 | $190.00 |
| 0050 | Maintaining traffic (801-06775) | LS | 1 | $8,282.38 | $6,113.71 | $7,500.00 | $5,369.20 | $10,000 | $6,379.99 |
| 0051 | Barricade, type III-A (801-07118) | LFT | 48 | $18.00 | $18.00 | $17.00 | $17.00 | $18.00 | $17.00 |
| 0052 | Barricade, type III-B (801-07119) | LFT | 48 | $18.00 | $18.00 | $17.00 | $17.00 | $18.00 | $17.00 |
| 0053 | Line, paint, solid, white, 6 in. (808-75007) | LFT | 280 | $2.50 | $2.50 | $1.00 | $1.00 | $2.50 | $1.00 |
| 0054 | Line, paint, solid, yellow, 6 in. (808-75047) | LFT | 280 | $2.50 | $2.50 | $1.00 | $1.00 | $2.50 | $1.55 |
| 0055 | Compacted aggregate, no. 8 (301-12233) | CYS | 74 | $180.00 | $102.21 | $40.00 | $130.00 | $100.63 | $114.88 |
| 0056 | Geotextile for riprap, type 2A (616-12248) | SYS | 329 | $2.00 | $3.88 | $2.00 | $3.00 | $3.94 | $4.99 |
| 0057 | Service point, type II (807-86810) | EACH | 2 | $9,500.00 | $9,500.00 | $9,500.00 | $18,100 | $19,000 | $9,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of October 8, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.