INDOT contract R-43310-A bid tabulation
HMA OVERLAY, BRIDGE DECK OVERLAY AND SIDEWALK CONSTRUCTION. Let by Indiana DOT on July 9, 2025, Noble, Fort Wayne. 4 bids received; low bid $6,203,766 by E & B Paving LLC.
- Owner
- Indiana DOT
- Letting
- 09 JUL 2025
- Pay items
- 162
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | E & B Paving LLC | $6,203,766 | Low |
| 2 | Phend & Brown Inc | $6,208,652 | 0.0% |
| 3 | Brooks Construction Company Inc | $6,316,101 | +2.0% |
| 4 | Milestone Contractors LP | $6,684,900 | +8.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. E & B Paving LLC | 2. Phend & Brown Inc | 3. Brooks Construction Company Inc | 4. Milestone Contractors LP |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $78,271 | $75,000 | $50,000 | $109,462 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, pavement traffic markings (109-09377) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0011 | Mobilization and demobilization (110-01001) | LS | 1 | $309,822 | $265,000 | $315,000 | $334,245 |
| 0012 | Clearing right-of-way (201-52370) | LS | 1 | $61,964 | $40,000 | $30,000 | $44,562 |
| 0013 | Pavement removal (202-02240) | SYS | 843 | $57.84 | $50.00 | $77.00 | $95.00 |
| 0014 | Headwall, remove (202-02271) | EACH | 2 | $497.57 | $1,500.00 | $400.00 | $450.00 |
| 0015 | Curb and gutter, remove (202-02279) | LFT | 192 | $24.00 | $25.00 | $24.00 | $24.00 |
| 0016 | Present structure, remove portions, structure no. 1 (202-51328) | LS | 1 | $150,000 | $177,000 | $125,000 | $278,562 |
| 0017 | Sidewalk concrete, remove (202-52710) | SYS | 159 | $31.00 | $30.50 | $31.00 | $31.00 |
| 0018 | Inlet, remove (202-91385) | EACH | 1 | $1,900.00 | $1,287.00 | $1,900.00 | $1,900.00 |
| 0019 | Guardrail end treatment, remove (202-93741) | EACH | 16 | $156.84 | $350.00 | $350.00 | $350.00 |
| 0020 | Pipe, remove (202-96133) | LFT | 30 | $85.00 | $85.00 | $85.00 | $85.00 |
| 0021 | Pipe end section, remove (202-98488) | EACH | 2 | $234.34 | $1,224.82 | $160.00 | $160.00 |
| 0022 | Excavation, common (203-02000) | CYS | 1,385 | $65.00 | $36.00 | $65.00 | $65.00 |
| 0023 | Linear grading (203-08607) | LFT | 2,679 | $27.23 | $15.00 | $16.00 | $16.00 |
| 0024 | Temporary turbidity curtain (205-09387) | LFT | 120 | $62.50 | $150.00 | $62.50 | $62.50 |
| 0025 | Pump around (205-11626) | EACH | 2 | $11,719 | $21,000 | $7,200.00 | $7,200.00 |
| 0026 | Stormwater management budget (205-12108) | DOL | 12,700 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0027 | Stormwater management implementation (205-12616) | LS | 1 | $10,000 | $15,000 | $6,500.00 | $5,000.00 |
| 0028 | Excavation, foundation, unclassified (206-51230) | CYS | 15 | $155.00 | $145.00 | $155.00 | $155.00 |
| 0029 | Subgrade treatment, type III (207-08266) | SYS | 153 | $31.50 | $25.00 | $31.50 | $31.50 |
| 0030 | Subgrade treatment, type IC (207-09935) | SYS | 3,761 | $50.00 | $55.00 | $68.00 | $68.00 |
| 0031 | Structure backfill, type 2 (211-09265) | CYS | 109 | $96.15 | $75.00 | $170.00 | $170.00 |
| 0032 | Structure backfill, type 3 (211-09266) | CYS | 690 | $140.00 | $120.00 | $140.00 | $140.00 |
| 0033 | Flowable backfill, removable (213-09270) | CYS | 14 | $380.00 | $200.00 | $380.00 | $380.00 |
| 0034 | Geogrid, type IB (214-11796) | SYS | 2,006 | $4.53 | $4.00 | $2.50 | $6.50 |
| 0035 | Geotextile for pavement, type 2A (214-12238) | SYS | 10 | $81.97 | $130.00 | $8.00 | $8.00 |
| 0036 | Geotextile for pavement, type 2B (214-12239) | SYS | 1,829 | $4.00 | $5.00 | $4.00 | $4.00 |
| 0037 | Compacted aggregate, no. 8 (301-12233) | CYS | 21 | $155.00 | $188.00 | $155.00 | $155.00 |
| 0038 | Compacted aggregate, no. 53 (301-12234) | CYS | 365 | $115.00 | $157.00 | $115.00 | $115.00 |
| 0039 | Subbase for PCCP (302-06464) | CYS | 50 | $380.00 | $315.00 | $380.00 | $380.00 |
| 0040 | Compacted aggregate, no. 53 (303-01180) | TON | 877 | $61.68 | $42.00 | $50.00 | $50.00 |
| 0041 | HMA patching, full depth, type C (304-12625) | TON | 1,335 | $250.00 | $240.00 | $290.00 | $290.00 |
| 0042 | HMA patching, partial depth, type C (304-12626) | TON | 67 | $920.00 | $240.00 | $295.00 | $295.00 |
| 0043 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 24,469 | $2.17 | $2.70 | $2.00 | $2.23 |
| 0044 | Milling, transition (306-08043) | SYS | 465 | $16.20 | $12.00 | $16.00 | $23.50 |
| 0045 | Milling, approach (306-08432) | SYS | 2,674 | $7.51 | $6.00 | $8.00 | $8.00 |
| 0046 | Milling, asphalt, 5 in. (306-11619) | SYS | 36,603 | $5.25 | $4.20 | $5.50 | $5.50 |
| 0047 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 5,889 | $110.00 | $105.00 | $90.50 | $90.50 |
| 0048 | QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041) | TON | 7,225 | $90.00 | $92.00 | $85.25 | $85.25 |
| 0049 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 751 | $130.00 | $110.00 | $125.00 | $125.00 |
| 0050 | Joint adhesive, surface (401-10258) | LFT | 23,723 | $0.50 | $0.50 | $0.21 | $0.21 |
| 0051 | Joint adhesive, intermediate (401-10259) | LFT | 13,955 | $0.70 | $0.50 | $0.43 | $0.43 |
| 0052 | Inertial profiler, HMA (401-12169) | LS | 1 | $9,870.00 | $6,500.00 | $4,000.00 | $4,000.00 |
| 0053 | HMA for temporary pavement, type C (402-10086) | TON | 50 | $150.00 | $120.00 | $330.00 | $330.00 |
| 0054 | Asphalt for tack coat (406-05520) | TON | 44 | $650.00 | $700.00 | $850.00 | $850.00 |
| 0055 | PCCP, 4 in. (502-11543) | SYS | 144 | $120.00 | $65.00 | $120.00 | $120.00 |
| 0056 | D-1 contraction joint (503-05240) | LFT | 33 | $65.00 | $37.00 | $65.00 | $65.00 |
| 0057 | Terminal joint, type HMA (503-12477) | LFT | 104 | $480.00 | $430.00 | $480.00 | $480.00 |
| 0058 | Guardrail, remove (601-02241) | LFT | 1,965 | $3.00 | $3.00 | $3.00 | $3.00 |
| 0059 | Guardrail, reset (601-06035) | LFT | 313 | $16.00 | $16.00 | $16.00 | $16.00 |
| 0060 | Hand dig guardrail post holes (601-09238) | EACH | 100 | $100.00 | $100.00 | $100.00 | $100.00 |
| 0061 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 1,330 | $24.00 | $24.00 | $24.00 | $24.00 |
| 0062 | Guardrail, MGS W-beam, 3 FT 1.5 in. spacing (601-12282) | LFT | 50 | $44.50 | $44.50 | $44.50 | $44.50 |
| 0063 | Guardrail transition, MGS without curb (601-12292) | EACH | 2 | $3,700.00 | $3,700.00 | $3,700.00 | $3,700.00 |
| 0064 | Guardrail end treatment, type OS (601-94689) | EACH | 16 | $3,150.00 | $3,150.00 | $3,150.00 | $3,150.00 |
| 0065 | Guardrail, W-beam, 6 FT 3 in. spacing (601-99105) | LFT | 393.75 | $26.00 | $26.00 | $26.00 | $26.00 |
| 0066 | Barrier delineator (602-06729) | EACH | 19 | $22.00 | $25.00 | $22.00 | $22.00 |
| 0067 | Fence, farm field, reset (603-06060) | LFT | 50 | $81.00 | $81.00 | $81.00 | $81.00 |
| 0068 | Hand rail, steel (604-92237) | LFT | 79 | $295.00 | $295.00 | $295.00 | $295.00 |
| 0069 | Curb, concrete, type B , modified (605-06121) | LFT | 63 | $110.00 | $98.00 | $110.00 | $110.00 |
| 0070 | Curb and gutter, concrete (605-06140) | LFT | 96 | $95.00 | $96.00 | $95.00 | $95.00 |
| 0071 | Curb and gutter, concrete , modified (605-06140) | LFT | 129 | $95.00 | $85.00 | $95.00 | $95.00 |
| 0072 | Milled HMA corrugations, sinusoidal (606-12400) | LFT | 39,856 | $0.80 | $0.50 | $0.90 | $0.90 |
| 0073 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 246 | $225.00 | $220.00 | $225.00 | $225.00 |
| 0074 | HMA for approaches, type C (610-07488) | TON | 436 | $160.00 | $160.00 | $175.00 | $175.00 |
| 0075 | Mailbox assembly, reset, single (611-08232) | EACH | 2 | $450.00 | $450.00 | $450.00 | $450.00 |
| 0076 | Right-of-way marker (615-06490) | EACH | 7 | $275.00 | $275.00 | $275.00 | $275.00 |
| 0077 | River rock (616-03096) | TON | 21 | $220.00 | $156.00 | $220.00 | $220.00 |
| 0078 | Riprap, revetment (616-06405) | TON | 29 | $100.17 | $210.37 | $135.00 | $135.00 |
| 0079 | Riprap, uniform (616-06451) | TON | 1 | $95.97 | $1,098.82 | $240.00 | $240.00 |
| 0080 | Geotextile for riprap, type 1A (616-12246) | SYS | 112 | $8.00 | $10.00 | $8.00 | $8.00 |
| 0081 | Slopewall, concrete, 4 in. (616-51367) | SYS | 6 | $300.00 | $500.00 | $300.00 | $300.00 |
| 0082 | Mobilization and demobilization for seeding (621-01004) | EACH | 11 | $500.00 | $725.00 | $500.00 | $725.00 |
| 0083 | Erosion control blanket (621-02770) | SYS | 908 | $2.65 | $4.30 | $2.65 | $4.30 |
| 0084 | Mulched seeding, type R (621-06559) | SYS | 2,668 | $2.35 | $8.98 | $2.35 | $8.98 |
| 0085 | Water (621-06567) | KGAL | 4 | $1.00 | $25.00 | $1.00 | $25.00 |
| 0086 | Sodding (621-06574) | SYS | 5 | $165.00 | $399.00 | $165.00 | $399.00 |
| 0087 | Seed mixture, emergent wetland (621-06737) | LBS | 0.03 | $10,000 | $17,305 | $10,000 | $17,305 |
| 0088 | Field office, type D (628-12683) | MOS | 20 | $4,400.00 | $4,900.00 | $4,400.00 | $3,917.06 |
| 0089 | Dynamic pile load test (701-06011) | EACH | 6 | $2,500.00 | $1,750.00 | $2,500.00 | $2,500.00 |
| 0090 | Test pile, dynamic, production (701-09557) | LFT | 427 | $205.00 | $155.00 | $205.00 | $205.00 |
| 0091 | Test pile, dynamic, restrike (701-09559) | EACH | 6 | $2,500.00 | $3,500.00 | $2,500.00 | $2,500.00 |
| 0092 | Vibration monitoring (701-12304) | LS | 1 | $50,000 | $45,000 | $50,000 | $50,000 |
| 0093 | Concrete, A, substructure (702-51005) | CYS | 43.70 | $2,600.00 | $2,750.00 | $2,800.00 | $2,600.00 |
| 0094 | Concrete, B, footings (702-51015) | CYS | 96 | $650.00 | $510.00 | $650.00 | $650.00 |
| 0095 | Field drilled hole in concrete (702-51863) | EACH | 534 | $14.00 | $23.00 | $14.00 | $14.00 |
| 0096 | Concrete, C, substructure (702-92857) | CYS | 6.50 | $4,500.00 | $2,000.00 | $4,500.00 | $4,500.00 |
| 0097 | Reinforcing bars, epoxy coated (703-06029) | LBS | 87,224 | $2.50 | $1.90 | $2.53 | $2.50 |
| 0098 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 104 | $50.00 | $66.00 | $50.00 | $50.00 |
| 0099 | Concrete, C, superstructure (704-51002) | CYS | 215.30 | $1,700.00 | $1,850.00 | $1,700.00 | $1,700.00 |
| 0100 | Concrete bridge railing transition, type TPS-1 , modified (706-06353) | EACH | 1 | $4,000.00 | $7,000.00 | $4,000.00 | $4,000.00 |
| 0101 | Reinforced concrete moment slab, 12 in. (706-08496) | SYS | 85 | $285.00 | $330.00 | $285.00 | $285.00 |
| 0102 | Railing, steel type PF-1 (706-11404) | LFT | 69 | $159.00 | $140.00 | $159.00 | $160.00 |
| 0103 | Railing, steel type PS-1 (706-11418) | LFT | 196 | $159.00 | $140.00 | $159.00 | $160.00 |
| 0104 | Railing, concrete type PF-1 (706-11602) | CYS | 4.20 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 |
| 0105 | Railing, concrete type PS-1 (706-11604) | CYS | 17.50 | $2,000.00 | $1,960.00 | $2,000.00 | $2,000.00 |
| 0106 | Concrete bridge railing transition, type TFC , modified (706-11620) | EACH | 2 | $4,000.00 | $4,925.00 | $4,000.00 | $4,000.00 |
| 0107 | Surface seal (709-51821) | LS | 1 | $3,000.00 | $16,500 | $3,000.00 | $3,000.00 |
| 0108 | Patching concrete structures (710-09158) | SFT | 50 | $125.00 | $40.00 | $125.00 | $125.00 |
| 0109 | Waterproofing membrane type 2 (714-000086) | SFT | 729 | $5.25 | $15.00 | $7.00 | $7.00 |
| 0110 | Pipe, type 4, circular, diameter 6 in. (715-05048) | LFT | 163 | $20.00 | $10.00 | $20.00 | $20.00 |
| 0111 | Pipe, underdrain outlet, diameter 6 in. (715-05053) | LFT | 13 | $36.00 | $41.00 | $36.00 | $36.00 |
| 0112 | Pipe, type 1, circular, diameter 15 in. (715-05119) | LFT | 68 | $118.29 | $480.00 | $160.00 | $160.00 |
| 0113 | Pipe, type 1, circular, diameter 18 in. (715-05121) | LFT | 97 | $126.17 | $490.00 | $230.00 | $230.00 |
| 0114 | HMA for structure installation, type C (715-08306) | TON | 45 | $400.00 | $300.00 | $260.00 | $260.00 |
| 0115 | Video inspection for pipe (715-09064) | LFT | 165 | $19.70 | $19.70 | $19.70 | $19.70 |
| 0116 | Pipe end section, diameter 18 in. (715-46010) | EACH | 1 | $880.22 | $1,600.00 | $1,500.00 | $1,500.00 |
| 0117 | Pipe end section, diameter 18 in. , modified (715-46010) | EACH | 1 | $1,031.31 | $2,000.00 | $2,000.00 | $2,000.00 |
| 0118 | Geotextile for underdrains, type 1A (718-12305) | SYS | 176 | $5.00 | $7.00 | $5.00 | $5.00 |
| 0119 | Aggregate for underdrains (718-52610) | CYS | 25 | $135.00 | $130.00 | $135.00 | $135.00 |
| 0120 | Hydrodemolition (722-01066) | SYS | 775 | $110.00 | $105.00 | $110.00 | $110.00 |
| 0121 | Bridge deck overlay budget (722-12380) | DOL | 16,985 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0122 | Bridge deck, remove concrete surface (722-12464) | SYS | 775 | $15.00 | $15.00 | $15.00 | $15.00 |
| 0123 | Longitudinal grooving (722-12732) | SYS | 1,021 | $5.00 | $9.00 | $5.00 | $5.00 |
| 0124 | Bridge deck patching, full depth (722-51401) | SFT | 347 | $80.00 | $55.00 | $80.00 | $80.00 |
| 0125 | Overlay dam (722-51874) | SFT | 80 | $90.00 | $60.00 | $90.00 | $90.00 |
| 0126 | Bearing assembly, elastomeric (726-92406) | EACH | 7 | $1,500.00 | $1,500.00 | $1,500.00 | $1,500.00 |
| 0127 | Road closure sign assembly (801-04308) | EACH | 13 | $284.00 | $284.00 | $284.00 | $284.00 |
| 0128 | Temporary pavement marking, 6 in. (801-06206) | LFT | 46,861 | $0.36 | $0.36 | $0.36 | $1.00 |
| 0129 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 51,011 | $1.88 | $1.88 | $1.88 | $2.25 |
| 0130 | Temporary transverse pavement marking, 24 in. (801-06216) | LFT | 36 | $12.49 | $12.49 | $12.49 | $15.00 |
| 0131 | Detour route marker assembly (801-06625) | EACH | 43 | $177.00 | $177.00 | $177.00 | $177.00 |
| 0132 | Construction sign, type A (801-06640) | EACH | 84 | $229.00 | $229.00 | $229.00 | $229.00 |
| 0133 | Construction sign, type B (801-06645) | EACH | 16 | $116.00 | $116.00 | $116.00 | $116.00 |
| 0134 | Maintaining traffic (801-06775) | LS | 1 | $123,817 | $265,000 | $312,929 | $350,000 |
| 0135 | Energy absorbing terminal, CZ, TL-2 (801-07023) | EACH | 8 | $4,800.00 | $4,800.00 | $4,800.00 | $4,800.00 |
| 0136 | Barricade, type III-A (801-07118) | LFT | 48 | $15.61 | $15.61 | $15.61 | $15.61 |
| 0137 | Barricade, type III-B (801-07119) | LFT | 280 | $15.61 | $15.61 | $15.61 | $15.61 |
| 0138 | Temporary traffic barrier, anchored, type 2 (801-08508) | LFT | 1,330 | $65.00 | $70.00 | $65.00 | $65.00 |
| 0139 | Portable signal (801-12081) | LS | 1 | $13,000 | $38,952 | $53,000 | $75,000 |
| 0140 | Law enforcement officer (801-12324) | HRS | 300 | $60.00 | $60.00 | $60.00 | $60.00 |
| 0141 | Driveway assistance device (801-12482) | EACH | 3 | $2,981.00 | $2,981.00 | $12,000 | $2,981.00 |
| 0142 | Temporary accessible pedestrian path (801-12641) | SYS | 57 | $180.00 | $145.00 | $260.00 | $180.00 |
| 0143 | Temporary pedestrian channelizer (801-12862) | LFT | 220 | $34.29 | $40.00 | $34.29 | $34.29 |
| 0144 | Temporary worksite speed limit sign assembly, continuous (801-12883) | EACH | 3 | $984.00 | $984.00 | $984.00 | $984.00 |
| 0145 | Construction signs mobile (801-92448) | DAY | 360 | $10.00 | $9.00 | $1.00 | $15.00 |
| 0146 | Sign, ground mounted, reset (802-91122) | EACH | 5 | $325.00 | $650.00 | $325.00 | $325.00 |
| 0147 | Delineator post, flexible, type I (804-11920) | EACH | 4 | $75.00 | $75.00 | $75.00 | $75.00 |
| 0148 | Pedestrian push button, APS (805-11817) | EACH | 4 | $1,800.00 | $3,500.00 | $4,000.00 | $3,100.00 |
| 0149 | Line, remove (808-06716) | LFT | 1,640 | $2.09 | $2.09 | $2.09 | $2.09 |
| 0150 | Retro-reflectivity testing (808-09381) | LS | 1 | $6,000.00 | $3,000.00 | $3,000.00 | $3,000.00 |
| 0151 | Transverse marking, multi-component, crosshatch line, yellow, 12 in. (808-10042) | LFT | 7 | $8.61 | $8.61 | $8.61 | $8.61 |
| 0152 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 35,385 | $0.96 | $0.96 | $0.96 | $0.96 |
| 0153 | Transverse marking, multi-component, stop line, white, 24 in. (808-10051) | LFT | 20 | $14.64 | $14.64 | $14.64 | $14.64 |
| 0154 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 12,812 | $0.96 | $0.96 | $0.96 | $0.96 |
| 0155 | Grooving for pavement markings (808-12032) | LFT | 49,027 | $0.66 | $0.66 | $0.66 | $0.66 |
| 0156 | Line, multi-component, solid, white, 10 in. (808-12781) | LFT | 26 | $7.55 | $7.55 | $7.55 | $7.55 |
| 0157 | Line, multi-component, broken, yellow, 6 in. (808-12841) | LFT | 3,610 | $1.88 | $1.88 | $1.88 | $1.88 |
| 0158 | Line, multi-component, solid, yellow, 10 in. (808-12859) | LFT | 414 | $7.55 | $7.55 | $7.55 | $7.55 |
| 0159 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 387 | $13.10 | $15.00 | $20.00 | $24.07 |
| 0160 | Snowplowable raised pavement marker (808-75998) | EACH | 184 | $38.55 | $38.55 | $38.55 | $39.00 |
| 0162 | Bridge deck overlay, silica fume modified (722-01061) | SYS | 775 | $115.00 | $150.00 | $115.00 | $115.00 |
| 0163 | Geotextile for pavement, interlayer (214-12456) | SYS | 36,603 | $6.25 | $6.25 | $6.00 | $6.25 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of July 9, 2025. Compiled by Mirage Metrics.