INDOT contract R-43310-A bid tabulation

HMA OVERLAY, BRIDGE DECK OVERLAY AND SIDEWALK CONSTRUCTION. Let by Indiana DOT on July 9, 2025, Noble, Fort Wayne. 4 bids received; low bid $6,203,766 by E & B Paving LLC.

Owner
Indiana DOT
Letting
09 JUL 2025
Pay items
162
Data through
05 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1E & B Paving LLC$6,203,766Low
2Phend & Brown Inc$6,208,6520.0%
3Brooks Construction Company Inc$6,316,101+2.0%
4Milestone Contractors LP$6,684,900+8.0%
INDOT contract R-43310-A: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. E & B Paving LLC2. Phend & Brown Inc3. Brooks Construction Company Inc4. Milestone Contractors LP
0001Construction engineering (105-06845)LS1$78,271$75,000$50,000$109,462
0002Liquidated damages (109-08359)DOL1$1.00$1.00$1.00$1.00
0003Contract liens (109-08360)DOL1$1.00$1.00$1.00$1.00
0004Quality adjustments, HMA (109-08440)DOL1$1.00$1.00$1.00$1.00
0005Quality adjustments, temporary traffic control devices (109-08443)DOL1$1.00$1.00$1.00$1.00
0006Quality adjustments, failed materials (109-08444)DOL1$1.00$1.00$1.00$1.00
0007Project estimate adjustment (109-08463)DOL1$1.00$1.00$1.00$1.00
0008Quality adjustments, pavement traffic markings (109-09377)DOL1$1.00$1.00$1.00$1.00
0009Payment adjustment, PG asphalt binder (109-09489)DOL1$1.00$1.00$1.00$1.00
0010Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362)DOL1$1.00$1.00$1.00$1.00
0011Mobilization and demobilization (110-01001)LS1$309,822$265,000$315,000$334,245
0012Clearing right-of-way (201-52370)LS1$61,964$40,000$30,000$44,562
0013Pavement removal (202-02240)SYS843$57.84$50.00$77.00$95.00
0014Headwall, remove (202-02271)EACH2$497.57$1,500.00$400.00$450.00
0015Curb and gutter, remove (202-02279)LFT192$24.00$25.00$24.00$24.00
0016Present structure, remove portions, structure no. 1 (202-51328)LS1$150,000$177,000$125,000$278,562
0017Sidewalk concrete, remove (202-52710)SYS159$31.00$30.50$31.00$31.00
0018Inlet, remove (202-91385)EACH1$1,900.00$1,287.00$1,900.00$1,900.00
0019Guardrail end treatment, remove (202-93741)EACH16$156.84$350.00$350.00$350.00
0020Pipe, remove (202-96133)LFT30$85.00$85.00$85.00$85.00
0021Pipe end section, remove (202-98488)EACH2$234.34$1,224.82$160.00$160.00
0022Excavation, common (203-02000)CYS1,385$65.00$36.00$65.00$65.00
0023Linear grading (203-08607)LFT2,679$27.23$15.00$16.00$16.00
0024Temporary turbidity curtain (205-09387)LFT120$62.50$150.00$62.50$62.50
0025Pump around (205-11626)EACH2$11,719$21,000$7,200.00$7,200.00
0026Stormwater management budget (205-12108)DOL12,700$1.00$1.00$1.00$1.00
0027Stormwater management implementation (205-12616)LS1$10,000$15,000$6,500.00$5,000.00
0028Excavation, foundation, unclassified (206-51230)CYS15$155.00$145.00$155.00$155.00
0029Subgrade treatment, type III (207-08266)SYS153$31.50$25.00$31.50$31.50
0030Subgrade treatment, type IC (207-09935)SYS3,761$50.00$55.00$68.00$68.00
0031Structure backfill, type 2 (211-09265)CYS109$96.15$75.00$170.00$170.00
0032Structure backfill, type 3 (211-09266)CYS690$140.00$120.00$140.00$140.00
0033Flowable backfill, removable (213-09270)CYS14$380.00$200.00$380.00$380.00
0034Geogrid, type IB (214-11796)SYS2,006$4.53$4.00$2.50$6.50
0035Geotextile for pavement, type 2A (214-12238)SYS10$81.97$130.00$8.00$8.00
0036Geotextile for pavement, type 2B (214-12239)SYS1,829$4.00$5.00$4.00$4.00
0037Compacted aggregate, no. 8 (301-12233)CYS21$155.00$188.00$155.00$155.00
0038Compacted aggregate, no. 53 (301-12234)CYS365$115.00$157.00$115.00$115.00
0039Subbase for PCCP (302-06464)CYS50$380.00$315.00$380.00$380.00
0040Compacted aggregate, no. 53 (303-01180)TON877$61.68$42.00$50.00$50.00
0041HMA patching, full depth, type C (304-12625)TON1,335$250.00$240.00$290.00$290.00
0042HMA patching, partial depth, type C (304-12626)TON67$920.00$240.00$295.00$295.00
0043Milling, asphalt, 1 1/2 in. (306-08034)SYS24,469$2.17$2.70$2.00$2.23
0044Milling, transition (306-08043)SYS465$16.20$12.00$16.00$23.50
0045Milling, approach (306-08432)SYS2,674$7.51$6.00$8.00$8.00
0046Milling, asphalt, 5 in. (306-11619)SYS36,603$5.25$4.20$5.50$5.50
0047QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005)TON5,889$110.00$105.00$90.50$90.50
0048QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041)TON7,225$90.00$92.00$85.25$85.25
0049QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047)TON751$130.00$110.00$125.00$125.00
0050Joint adhesive, surface (401-10258)LFT23,723$0.50$0.50$0.21$0.21
0051Joint adhesive, intermediate (401-10259)LFT13,955$0.70$0.50$0.43$0.43
0052Inertial profiler, HMA (401-12169)LS1$9,870.00$6,500.00$4,000.00$4,000.00
0053HMA for temporary pavement, type C (402-10086)TON50$150.00$120.00$330.00$330.00
0054Asphalt for tack coat (406-05520)TON44$650.00$700.00$850.00$850.00
0055PCCP, 4 in. (502-11543)SYS144$120.00$65.00$120.00$120.00
0056D-1 contraction joint (503-05240)LFT33$65.00$37.00$65.00$65.00
0057Terminal joint, type HMA (503-12477)LFT104$480.00$430.00$480.00$480.00
0058Guardrail, remove (601-02241)LFT1,965$3.00$3.00$3.00$3.00
0059Guardrail, reset (601-06035)LFT313$16.00$16.00$16.00$16.00
0060Hand dig guardrail post holes (601-09238)EACH100$100.00$100.00$100.00$100.00
0061Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281)LFT1,330$24.00$24.00$24.00$24.00
0062Guardrail, MGS W-beam, 3 FT 1.5 in. spacing (601-12282)LFT50$44.50$44.50$44.50$44.50
0063Guardrail transition, MGS without curb (601-12292)EACH2$3,700.00$3,700.00$3,700.00$3,700.00
0064Guardrail end treatment, type OS (601-94689)EACH16$3,150.00$3,150.00$3,150.00$3,150.00
0065Guardrail, W-beam, 6 FT 3 in. spacing (601-99105)LFT393.75$26.00$26.00$26.00$26.00
0066Barrier delineator (602-06729)EACH19$22.00$25.00$22.00$22.00
0067Fence, farm field, reset (603-06060)LFT50$81.00$81.00$81.00$81.00
0068Hand rail, steel (604-92237)LFT79$295.00$295.00$295.00$295.00
0069Curb, concrete, type B , modified (605-06121)LFT63$110.00$98.00$110.00$110.00
0070Curb and gutter, concrete (605-06140)LFT96$95.00$96.00$95.00$95.00
0071Curb and gutter, concrete , modified (605-06140)LFT129$95.00$85.00$95.00$95.00
0072Milled HMA corrugations, sinusoidal (606-12400)LFT39,856$0.80$0.50$0.90$0.90
0073Reinforced concrete bridge approach, 12 in. (609-06259)SYS246$225.00$220.00$225.00$225.00
0074HMA for approaches, type C (610-07488)TON436$160.00$160.00$175.00$175.00
0075Mailbox assembly, reset, single (611-08232)EACH2$450.00$450.00$450.00$450.00
0076Right-of-way marker (615-06490)EACH7$275.00$275.00$275.00$275.00
0077River rock (616-03096)TON21$220.00$156.00$220.00$220.00
0078Riprap, revetment (616-06405)TON29$100.17$210.37$135.00$135.00
0079Riprap, uniform (616-06451)TON1$95.97$1,098.82$240.00$240.00
0080Geotextile for riprap, type 1A (616-12246)SYS112$8.00$10.00$8.00$8.00
0081Slopewall, concrete, 4 in. (616-51367)SYS6$300.00$500.00$300.00$300.00
0082Mobilization and demobilization for seeding (621-01004)EACH11$500.00$725.00$500.00$725.00
0083Erosion control blanket (621-02770)SYS908$2.65$4.30$2.65$4.30
0084Mulched seeding, type R (621-06559)SYS2,668$2.35$8.98$2.35$8.98
0085Water (621-06567)KGAL4$1.00$25.00$1.00$25.00
0086Sodding (621-06574)SYS5$165.00$399.00$165.00$399.00
0087Seed mixture, emergent wetland (621-06737)LBS0.03$10,000$17,305$10,000$17,305
0088Field office, type D (628-12683)MOS20$4,400.00$4,900.00$4,400.00$3,917.06
0089Dynamic pile load test (701-06011)EACH6$2,500.00$1,750.00$2,500.00$2,500.00
0090Test pile, dynamic, production (701-09557)LFT427$205.00$155.00$205.00$205.00
0091Test pile, dynamic, restrike (701-09559)EACH6$2,500.00$3,500.00$2,500.00$2,500.00
0092Vibration monitoring (701-12304)LS1$50,000$45,000$50,000$50,000
0093Concrete, A, substructure (702-51005)CYS43.70$2,600.00$2,750.00$2,800.00$2,600.00
0094Concrete, B, footings (702-51015)CYS96$650.00$510.00$650.00$650.00
0095Field drilled hole in concrete (702-51863)EACH534$14.00$23.00$14.00$14.00
0096Concrete, C, substructure (702-92857)CYS6.50$4,500.00$2,000.00$4,500.00$4,500.00
0097Reinforcing bars, epoxy coated (703-06029)LBS87,224$2.50$1.90$2.53$2.50
0098Threaded tie bar assembly, epoxy coated (703-97936)EACH104$50.00$66.00$50.00$50.00
0099Concrete, C, superstructure (704-51002)CYS215.30$1,700.00$1,850.00$1,700.00$1,700.00
0100Concrete bridge railing transition, type TPS-1 , modified (706-06353)EACH1$4,000.00$7,000.00$4,000.00$4,000.00
0101Reinforced concrete moment slab, 12 in. (706-08496)SYS85$285.00$330.00$285.00$285.00
0102Railing, steel type PF-1 (706-11404)LFT69$159.00$140.00$159.00$160.00
0103Railing, steel type PS-1 (706-11418)LFT196$159.00$140.00$159.00$160.00
0104Railing, concrete type PF-1 (706-11602)CYS4.20$2,500.00$2,500.00$2,500.00$2,500.00
0105Railing, concrete type PS-1 (706-11604)CYS17.50$2,000.00$1,960.00$2,000.00$2,000.00
0106Concrete bridge railing transition, type TFC , modified (706-11620)EACH2$4,000.00$4,925.00$4,000.00$4,000.00
0107Surface seal (709-51821)LS1$3,000.00$16,500$3,000.00$3,000.00
0108Patching concrete structures (710-09158)SFT50$125.00$40.00$125.00$125.00
0109Waterproofing membrane type 2 (714-000086)SFT729$5.25$15.00$7.00$7.00
0110Pipe, type 4, circular, diameter 6 in. (715-05048)LFT163$20.00$10.00$20.00$20.00
0111Pipe, underdrain outlet, diameter 6 in. (715-05053)LFT13$36.00$41.00$36.00$36.00
0112Pipe, type 1, circular, diameter 15 in. (715-05119)LFT68$118.29$480.00$160.00$160.00
0113Pipe, type 1, circular, diameter 18 in. (715-05121)LFT97$126.17$490.00$230.00$230.00
0114HMA for structure installation, type C (715-08306)TON45$400.00$300.00$260.00$260.00
0115Video inspection for pipe (715-09064)LFT165$19.70$19.70$19.70$19.70
0116Pipe end section, diameter 18 in. (715-46010)EACH1$880.22$1,600.00$1,500.00$1,500.00
0117Pipe end section, diameter 18 in. , modified (715-46010)EACH1$1,031.31$2,000.00$2,000.00$2,000.00
0118Geotextile for underdrains, type 1A (718-12305)SYS176$5.00$7.00$5.00$5.00
0119Aggregate for underdrains (718-52610)CYS25$135.00$130.00$135.00$135.00
0120Hydrodemolition (722-01066)SYS775$110.00$105.00$110.00$110.00
0121Bridge deck overlay budget (722-12380)DOL16,985$1.00$1.00$1.00$1.00
0122Bridge deck, remove concrete surface (722-12464)SYS775$15.00$15.00$15.00$15.00
0123Longitudinal grooving (722-12732)SYS1,021$5.00$9.00$5.00$5.00
0124Bridge deck patching, full depth (722-51401)SFT347$80.00$55.00$80.00$80.00
0125Overlay dam (722-51874)SFT80$90.00$60.00$90.00$90.00
0126Bearing assembly, elastomeric (726-92406)EACH7$1,500.00$1,500.00$1,500.00$1,500.00
0127Road closure sign assembly (801-04308)EACH13$284.00$284.00$284.00$284.00
0128Temporary pavement marking, 6 in. (801-06206)LFT46,861$0.36$0.36$0.36$1.00
0129Temporary pavement marking, removable, 6 in. (801-06209)LFT51,011$1.88$1.88$1.88$2.25
0130Temporary transverse pavement marking, 24 in. (801-06216)LFT36$12.49$12.49$12.49$15.00
0131Detour route marker assembly (801-06625)EACH43$177.00$177.00$177.00$177.00
0132Construction sign, type A (801-06640)EACH84$229.00$229.00$229.00$229.00
0133Construction sign, type B (801-06645)EACH16$116.00$116.00$116.00$116.00
0134Maintaining traffic (801-06775)LS1$123,817$265,000$312,929$350,000
0135Energy absorbing terminal, CZ, TL-2 (801-07023)EACH8$4,800.00$4,800.00$4,800.00$4,800.00
0136Barricade, type III-A (801-07118)LFT48$15.61$15.61$15.61$15.61
0137Barricade, type III-B (801-07119)LFT280$15.61$15.61$15.61$15.61
0138Temporary traffic barrier, anchored, type 2 (801-08508)LFT1,330$65.00$70.00$65.00$65.00
0139Portable signal (801-12081)LS1$13,000$38,952$53,000$75,000
0140Law enforcement officer (801-12324)HRS300$60.00$60.00$60.00$60.00
0141Driveway assistance device (801-12482)EACH3$2,981.00$2,981.00$12,000$2,981.00
0142Temporary accessible pedestrian path (801-12641)SYS57$180.00$145.00$260.00$180.00
0143Temporary pedestrian channelizer (801-12862)LFT220$34.29$40.00$34.29$34.29
0144Temporary worksite speed limit sign assembly, continuous (801-12883)EACH3$984.00$984.00$984.00$984.00
0145Construction signs mobile (801-92448)DAY360$10.00$9.00$1.00$15.00
0146Sign, ground mounted, reset (802-91122)EACH5$325.00$650.00$325.00$325.00
0147Delineator post, flexible, type I (804-11920)EACH4$75.00$75.00$75.00$75.00
0148Pedestrian push button, APS (805-11817)EACH4$1,800.00$3,500.00$4,000.00$3,100.00
0149Line, remove (808-06716)LFT1,640$2.09$2.09$2.09$2.09
0150Retro-reflectivity testing (808-09381)LS1$6,000.00$3,000.00$3,000.00$3,000.00
0151Transverse marking, multi-component, crosshatch line, yellow, 12 in. (808-10042)LFT7$8.61$8.61$8.61$8.61
0152Line, multi-component, solid, white, 6 in. (808-10049)LFT35,385$0.96$0.96$0.96$0.96
0153Transverse marking, multi-component, stop line, white, 24 in. (808-10051)LFT20$14.64$14.64$14.64$14.64
0154Line, multi-component, solid, yellow, 6 in. (808-10057)LFT12,812$0.96$0.96$0.96$0.96
0155Grooving for pavement markings (808-12032)LFT49,027$0.66$0.66$0.66$0.66
0156Line, multi-component, solid, white, 10 in. (808-12781)LFT26$7.55$7.55$7.55$7.55
0157Line, multi-component, broken, yellow, 6 in. (808-12841)LFT3,610$1.88$1.88$1.88$1.88
0158Line, multi-component, solid, yellow, 10 in. (808-12859)LFT414$7.55$7.55$7.55$7.55
0159Snowplowable raised pavement marker, remove (808-75996)EACH387$13.10$15.00$20.00$24.07
0160Snowplowable raised pavement marker (808-75998)EACH184$38.55$38.55$38.55$39.00
0162Bridge deck overlay, silica fume modified (722-01061)SYS775$115.00$150.00$115.00$115.00
0163Geotextile for pavement, interlayer (214-12456)SYS36,603$6.25$6.25$6.00$6.25
INDOT contract R-43310-A: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.

Every contract let that day: INDOT letting of July 9, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy