INDOT contract R-43507-A bid tabulation
INTERSECTION IMPROVEMENT, ROUNDABOUT. Let by Indiana DOT on March 12, 2025, Henry, Greenfield. 8 bids received; low bid $1,687,170 by Midwest Paving LLC.
- Owner
- Indiana DOT
- Letting
- 12 MAR 2025
- Pay items
- 102
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Midwest Paving LLC | $1,687,170 | Low |
| 2 | His Constructors Inc | $1,805,137 | +7.0% |
| 3 | E & B Paving LLC | $1,883,201 | +12% |
| 4 | Morphey Construction Inc. | $1,998,000 | +18% |
| 5 | Milestone Contractors LP | $2,046,470 | +21% |
| 6 | Yarberry Companies Inc | $2,270,392 | +35% |
| 7 | Calumet Civil Contractors Inc | $2,484,000 | +47% |
| 8 | Olco Inc | $2,494,328 | +48% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Midwest Paving LLC | 2. His Constructors Inc | 3. E & B Paving LLC | 4. Morphey Construction Inc. | 5. Milestone Contractors LP | 6. Yarberry Companies Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $26,284 | $20,078 | $28,583 | $20,000 | $39,500 | $50,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, PCCP (109-08441) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Mobilization and demobilization (110-01001) | LS | 1 | $84,000 | $107,535 | $94,160 | $99,900 | $100,000 | $110,000 |
| 0011 | Clearing right-of-way (201-52370) | LS | 1 | $5,000.00 | $35,000 | $36,812 | $39,960 | $38,980 | $25,000 |
| 0012 | Paved side ditch, remove (202-02272) | LFT | 60 | $30.81 | $44.35 | $26.62 | $80.00 | $13.80 | $50.00 |
| 0013 | Sign, remove (202-74035) | EACH | 4 | $72.90 | $76.64 | $72.90 | $100.00 | $265.00 | $150.00 |
| 0014 | Manhole, remove (202-93047) | EACH | 1 | $1,074.19 | $2,661.14 | $2,278.00 | $1,000.00 | $840.00 | $700.00 |
| 0015 | Pipe, remove (202-96133) | LFT | 222 | $35.74 | $11.99 | $38.98 | $20.00 | $66.50 | $25.00 |
| 0016 | Excavation, common (203-02000) | CYS | 3,354 | $40.00 | $42.89 | $44.90 | $30.00 | $26.00 | $80.00 |
| 0017 | Stormwater management budget (205-12108) | DOL | 54,195 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0018 | Stormwater management implementation (205-12616) | LS | 1 | $23,750 | $11,101 | $16,957 | $5,000.00 | $7,300.00 | $24,000 |
| 0019 | SWQCP preparation (205-12618) | LS | 1 | $2,800.00 | $2,312.69 | $2,200.00 | $2,100.00 | $3,700.00 | $8,000.00 |
| 0020 | Subgrade treatment, type II (207-08264) | SYS | 147 | $45.00 | $44.49 | $43.48 | $35.00 | $59.00 | $35.00 |
| 0021 | Subgrade treatment, type ibc (207-12635) | SYS | 7,723 | $12.00 | $13.05 | $11.80 | $12.00 | $12.00 | $13.00 |
| 0022 | Structure backfill, type 1 (211-09264) | CYS | 98 | $52.00 | $94.09 | $74.69 | $100.00 | $70.00 | $140.00 |
| 0023 | Geotextile for pavement, type 2B (214-12239) | SYS | 1,099 | $3.25 | $5.42 | $4.80 | $5.00 | $5.30 | $10.00 |
| 0024 | Compacted aggregate, no. 2 (301-12231) | CYS | 1 | $47.00 | $497.17 | $123.22 | $150.00 | $120.00 | $400.00 |
| 0025 | Compacted aggregate, no. 8 (301-12233) | CYS | 149 | $35.00 | $85.35 | $87.60 | $100.00 | $110.00 | $65.00 |
| 0026 | Compacted aggregate, no. 53 (301-12234) | CYS | 1,545 | $55.00 | $69.71 | $68.85 | $100.00 | $66.00 | $52.00 |
| 0027 | Dense graded subbase (302-07455) | CYS | 25 | $110.00 | $147.46 | $135.29 | $18.00 | $112.00 | $175.00 |
| 0028 | Compacted aggregate, no. 53 (303-01180) | TON | 120 | $75.00 | $60.84 | $55.00 | $100.00 | $64.00 | $45.00 |
| 0029 | Milling, asphalt, 2 in. (306-08036) | SYS | 434 | $15.00 | $20.22 | $15.00 | $15.00 | $28.00 | $17.00 |
| 0030 | QC/QA-HMA, 3, 58E, surface, 9.5 MM (401-000008) | TON | 650 | $100.00 | $110.38 | $105.00 | $105.00 | $155.00 | $125.00 |
| 0031 | QC/QA-HMA, 3, 58E, intermediate, 19.0 MM (401-000044) | TON | 753 | $95.00 | $99.87 | $95.00 | $95.00 | $142.00 | $115.00 |
| 0032 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 2,338 | $85.00 | $89.35 | $85.00 | $85.00 | $119.00 | $95.00 |
| 0033 | Joint adhesive, surface (401-10258) | LFT | 3,032 | $0.50 | $0.21 | $0.20 | $0.20 | $2.50 | $0.50 |
| 0034 | Joint adhesive, intermediate (401-10259) | LFT | 3,032 | $0.50 | $0.32 | $0.30 | $0.30 | $2.50 | $0.50 |
| 0035 | Asphalt for tack coat (406-05520) | TON | 6 | $1.00 | $0.01 | $0.01 | $0.01 | $910.00 | $1.00 |
| 0036 | PCCP, 8 in. (502-06999) | SYS | 1,494 | $80.00 | $96.71 | $100.00 | $120.00 | $119.00 | $100.00 |
| 0037 | Aluminum to steel splice connector, type A S (601-03467) | EACH | 1 | $300.00 | $315.37 | $300.00 | $300.00 | $316.00 | $550.00 |
| 0038 | Guardrail height transition, MGS (601-12289) | EACH | 1 | $1,200.00 | $1,261.47 | $1,200.00 | $1,300.00 | $1,380.00 | $2,600.00 |
| 0039 | Guardrail end treatment, type OS (601-94689) | EACH | 1 | $3,355.00 | $3,526.85 | $3,355.00 | $4,550.00 | $4,350.00 | $6,050.00 |
| 0040 | Curb, integral concrete (605-06090) | LFT | 235 | $38.00 | $33.64 | $40.00 | $32.00 | $55.00 | $45.00 |
| 0041 | Curb and gutter, concrete (605-06140) | LFT | 1,344 | $38.00 | $34.69 | $49.00 | $50.00 | $33.00 | $47.00 |
| 0042 | Curb and gutter, concrete, type B (605-06145) | LFT | 722 | $38.00 | $35.74 | $35.00 | $50.00 | $31.00 | $35.00 |
| 0043 | Curb and gutter, concrete, type B , modified (605-06145) | LFT | 315 | $30.00 | $35.74 | $37.00 | $50.00 | $61.00 | $37.00 |
| 0044 | Curb and gutter, concrete, type B , modified, 2 inch reveal (605-06145) | LFT | 1,788 | $30.00 | $35.74 | $37.00 | $50.00 | $38.00 | $37.00 |
| 0045 | PCCP for approaches, 6 in. (610-08446) | SYS | 147 | $100.00 | $94.61 | $95.00 | $120.00 | $136.00 | $100.00 |
| 0046 | Mailbox assembly, reset, single (611-08232) | EACH | 2 | $225.00 | $236.53 | $225.00 | $270.00 | $285.00 | $660.00 |
| 0047 | Right-of-way marker (615-06490) | EACH | 23 | $175.00 | $183.96 | $175.00 | $200.00 | $211.00 | $330.00 |
| 0048 | Monument, type B (615-06505) | EACH | 11 | $975.00 | $1,024.94 | $975.00 | $1,100.00 | $1,160.00 | $1,260.00 |
| 0049 | Monument, type C (615-06510) | EACH | 1 | $675.00 | $709.57 | $675.00 | $2,000.00 | $2,110.00 | $660.00 |
| 0050 | Monument, type D (615-06515) | EACH | 21 | $170.00 | $178.71 | $170.00 | $130.00 | $138.00 | $225.00 |
| 0051 | Benchmark post, reset (615-06535) | EACH | 1 | $950.00 | $998.66 | $950.00 | $250.00 | $2,640.00 | $1,100.00 |
| 0052 | Riprap, revetment (616-06405) | TON | 528 | $50.00 | $79.88 | $61.70 | $150.00 | $75.00 | $120.00 |
| 0053 | Geotextile for riprap, type 1A (616-12246) | SYS | 347 | $2.00 | $3.99 | $3.49 | $3.00 | $5.10 | $15.00 |
| 0054 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $950.00 | $998.66 | $950.00 | $950.00 | $212.00 | $750.00 |
| 0055 | Fertilizer , for permanent seed (621-06545) | TON | 1 | $7.67 | $8.06 | $7.67 | $767.00 | $10.60 | $1,500.00 |
| 0056 | Seed mixture, type R (621-06553) | LBS | 249 | $8.07 | $10.13 | $8.07 | $20.00 | $21.10 | $25.00 |
| 0057 | Mulching material (621-06565) | TON | 3 | $409.00 | $429.95 | $409.00 | $409.00 | $690.00 | $900.00 |
| 0058 | Water (621-06567) | KGAL | 5 | $5.00 | $5.26 | $5.00 | $5.00 | $10.60 | $1.00 |
| 0059 | Sodding (621-06574) | SYS | 1,460 | $7.53 | $7.92 | $7.53 | $15.00 | $6.90 | $11.00 |
| 0060 | Field office, type C (628-09403) | MOS | 18 | $3,350.00 | $1,500.00 | $3,200.00 | $2,000.00 | $5,000.00 | $3,500.00 |
| 0061 | Computer system equipment (628-11976) | EACH | 1 | $800.00 | $917.63 | $810.00 | $500.00 | $600.00 | $2,000.00 |
| 0062 | Pipe, type 1, circular, diameter 24 in. (715-05123) | LFT | 184 | $85.00 | $118.99 | $121.98 | $100.00 | $165.00 | $150.00 |
| 0064 | Pipe, type 2, circular, diameter 12 in. (715-05149) | LFT | 121 | $60.00 | $78.94 | $64.64 | $85.00 | $156.00 | $110.00 |
| 0065 | Pipe, type 3, circular, diameter 15 in. (715-05169) | LFT | 90 | $80.00 | $102.08 | $101.15 | $100.00 | $142.00 | $140.00 |
| 0066 | Pipe end section, diameter 12 in. (715-46000) | EACH | 4 | $850.00 | $1,644.81 | $1,255.00 | $2,000.00 | $555.00 | $2,000.00 |
| 0067 | Pipe end section, diameter 15 in. (715-46005) | EACH | 6 | $880.00 | $1,711.65 | $1,368.00 | $2,200.00 | $600.00 | $2,500.00 |
| 0068 | Pipe end section, diameter 24 in. (715-46020) | EACH | 4 | $1,200.00 | $1,998.27 | $1,890.00 | $3,000.00 | $1,080.00 | $3,500.00 |
| 0070 | Inlet, type J10 (720-45045) | EACH | 4 | $2,600.00 | $2,862.11 | $4,847.00 | $5,000.00 | $4,130.00 | $5,500.00 |
| 0071 | Road closure sign assembly (801-04308) | EACH | 12 | $268.00 | $240.73 | $229.00 | $229.00 | $242.00 | $192.00 |
| 0072 | Detour route marker assembly (801-06625) | EACH | 65 | $162.00 | $186.07 | $177.00 | $177.00 | $188.00 | $94.00 |
| 0073 | Construction sign, type A (801-06640) | EACH | 13 | $214.00 | $312.21 | $297.00 | $297.00 | $315.00 | $220.00 |
| 0074 | Construction sign, type B (801-06645) | EACH | 6 | $107.00 | $74.64 | $71.00 | $71.00 | $75.00 | $110.00 |
| 0075 | Maintaining traffic (801-06775) | LS | 1 | $80,000 | $25,735 | $94,160 | $16,561 | $17,000 | $85,000 |
| 0076 | Barricade, type III-A (801-07118) | LFT | 264 | $15.64 | $12.61 | $12.00 | $12.00 | $12.70 | $18.00 |
| 0077 | Barricade, type III-B (801-07119) | LFT | 60 | $15.64 | $13.67 | $13.00 | $13.00 | $13.80 | $18.00 |
| 0078 | Sign, panel, relocate (802-02475) | EACH | 7 | $957.00 | $1,006.02 | $957.00 | $100.00 | $1,050.00 | $550.00 |
| 0079 | Sign post, square, type 1, unreinforced anchor base (802-05704) | LFT | 401 | $35.00 | $36.79 | $35.00 | $18.00 | $34.00 | $50.00 |
| 0080 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 183 | $32.00 | $33.64 | $32.00 | $31.00 | $34.00 | $50.00 |
| 0081 | Sign, sheet, with legend, 0.100 in. thickness (802-09840) | SFT | 76 | $35.20 | $37.00 | $35.20 | $20.00 | $35.00 | $55.00 |
| 0082 | Traffic signal equipment, remove (805-01300) | EACH | 1 | $7,375.00 | $7,752.76 | $7,375.00 | $1,000.00 | $7,400.00 | $8,800.00 |
| 0083 | Conduit, steel, galvanized, 3 in. (805-90267) | LFT | 941 | $44.80 | $47.09 | $44.80 | $60.00 | $58.00 | $90.00 |
| 0084 | Handhole, lighting (807-02191) | EACH | 6 | $1,612.00 | $1,694.57 | $1,612.00 | $3,500.00 | $1,590.00 | $3,080.00 |
| 0085 | Wire, no. 4 copper, in plastic duct, in trench, 4 1/C (807-07580) | LFT | 941 | $18.90 | $19.87 | $18.90 | $47.00 | $23.30 | $28.00 |
| 0086 | Lighting foundation, conventional pole, concrete, with grounding (807-12791) | EACH | 9 | $2,260.00 | $2,375.76 | $2,260.00 | $4,000.00 | $3,400.00 | $3,300.00 |
| 0087 | Light pole, 30 FT E.M.H., 15 FT mast arm, breakaway base (807-85502) | EACH | 9 | $4,115.00 | $4,325.78 | $4,115.00 | $5,800.00 | $3,700.00 | $5,000.00 |
| 0088 | Service point, type I (807-86805) | EACH | 1 | $12,060 | $12,678 | $12,060 | $11,500 | $10,600 | $13,200 |
| 0089 | Line, thermoplastic, dotted, white, 12 in. (808-11691) | LFT | 163 | $8.01 | $8.46 | $8.05 | $9.00 | $8.50 | $9.00 |
| 0090 | Transverse marking, thermoplastic, yield line, white, 27 in. (808-11698) | LFT | 163 | $18.67 | $17.57 | $16.71 | $17.00 | $17.70 | $33.00 |
| 0091 | Grooving for pavement markings (808-12032) | LFT | 3,695 | $0.88 | $2.28 | $2.17 | $3.00 | $2.28 | $3.00 |
| 0092 | Line, thermoplastic, solid, white, 6 in. (808-75043) | LFT | 790 | $1.23 | $1.96 | $1.86 | $2.00 | $1.95 | $4.00 |
| 0093 | Line, thermoplastic, solid, yellow, 6 in. (808-75247) | LFT | 1,170 | $1.23 | $1.96 | $1.86 | $2.00 | $1.95 | $4.00 |
| 0094 | Transverse marking, thermoplastic, crosshatch line, yellow, 12 in. (808-75278) | LFT | 271 | $8.42 | $3.90 | $3.71 | $4.00 | $3.90 | $11.00 |
| 0095 | Pavement message marking, thermoplastic, lane indication arrow (808-75320) | EACH | 4 | $212.00 | $155.58 | $148.00 | $148.00 | $156.00 | $330.00 |
| 0096 | Line, thermoplastic, solid, yellow, 8 in. (808-92027) | LFT | 1,138 | $2.45 | $2.60 | $2.47 | $3.00 | $2.60 | $5.00 |
| 0097 | Guardrail, remove (601-02241) | LFT | 73 | $14.00 | $14.72 | $14.00 | $1.00 | $6.35 | $14.00 |
| 0098 | Topsoil (621-06570) | CYS | 98 | $85.00 | $90.67 | $78.80 | $50.00 | $110.00 | $100.00 |
| 0099 | Pipe, type 4, circular, diameter 6 in. (715-05048) | LFT | 452 | $19.19 | $18.40 | $18.93 | $18.00 | $15.00 | $15.00 |
| 0100 | Pipe, underdrain outlet, diameter 6 in. (715-05053) | LFT | 60 | $29.34 | $47.31 | $46.88 | $45.00 | $81.00 | $40.00 |
| 0101 | Outlet protector, type 3 (718-06531) | EACH | 1 | $90.00 | $5,256.11 | $2,500.00 | $5,000.00 | $3,900.00 | $1,000.00 |
| 0102 | Geotextile for underdrains, type 2A (718-12307) | SYS | 386 | $1.36 | $11.30 | $2.70 | $11.00 | $2.50 | $12.00 |
| 0103 | Aggregate for underdrains (718-52610) | CYS | 40 | $50.30 | $78.84 | $81.50 | $75.00 | $180.00 | $80.00 |
| 0104 | Luminaire, low lumen roadway (807-12202) | EACH | 9 | $718.00 | $754.78 | $718.00 | $1,700.00 | $740.00 | $660.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of March 12, 2025. Compiled by Mirage Metrics.