KYTC letting results, November 17, 2022
38 contracts let by Kentucky Transportation Cabinet on November 17, 2022, $115,639,764 in low bids, a median of 1 bidders per contract. On the 38 with an engineer's estimate, the low bid came in under it 8 times; median low bid +7.0% against the estimate.
- Owner
- Kentucky Transportation Cabinet
- Contracts
- 38
- Low bids, total
- $115,639,764
- Data through
- 22 OCT 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 22-1360 | GRADE, DRAIN & SURFACE WITH BRIDGE US25W | District 11 | 1 | L-M Asphalt Partners LTD D/B/A Ats Construction | $36,412,358 | +7.0% | KYTC | ||
| 22-1356 | GRADE & DRAIN WITH ASPHALT SURFACE OWENTON-CRITTENDEN ROAD (KY 22) | District 6 | 2 | Eaton Asphalt Paving Co Inc | $11,393,044 | $11,550,987 | +1.0% | +22% | KYTC |
| 22-1058 | ASPHALT SURFACE WITH GRADE & DRAIN US-60 | District 2 | 1 | Yager Materials Corp | $11,275,432 | +10% | KYTC | ||
| 22-4205 | ASPHALT PAVEMENT & ROADWAY REHAB ANNETA ROAD (KY 259) | District 4 | 1 | Scotty'S Contracting & Stone LLC | $10,515,129 | +28% | KYTC | ||
| 22-1057 | ASPHALT PAVEMENT & ROADWAY REHAB I-75 | District 7 | 1 | Nally & Gibson Georgetown LLC DBA Hamilton-Hinkle Paving Co | $6,882,289 | +13% | KYTC | ||
| 22-4330 | ASPHALT PAVEMENT & ROADWAY REHAB KY HIGHWAY 53 (KY 53) | District 5 | 3 | Louisville Paving Company Inc | $5,766,000 | $6,599,000 | +14% | +1.0% | KYTC |
| 22-4331 | ASPHALT PAVEMENT & ROADWAY REHAB BALD KNOB ROAD (US 421) | District 5 | 1 | Hinkle Environmental Services LLC | $3,948,606 | +60% | KYTC | ||
| 22-1358 | GRADE & DRAIN WITH ASPHALT SURFACE OLD MILL ROAD (KY44) | District 5 | 3 | Louisville Paving Company Inc | $3,298,000 | $3,600,000 | +9.0% | +8.0% | KYTC |
| 22-4447 | ASPHALT PAVEMENT & ROADWAY REHAB HARRODSBURG ROAD (US 68) | District 7 | 1 | The Allen Company Inc | $3,215,252 | +12% | KYTC | ||
| 22-4451 | ASPHALT PAVEMENT & ROADWAY REHAB KY HIGHWAY 36 (KY 36) | District 6 | 1 | Hinkle Contracting Company LLC | $2,890,567 | +63% | KYTC | ||
| 22-7020 | BRIDGE REPLACEMENT VARIOUS ROUTES IN DISTRICT 12 - 4 LOCATIONS | District 12 | 5 | Frederick & May Construction Co | $1,862,722 | $2,143,070 | +15% | +2.0% | KYTC |
| 22-7010 | BRIDGE REPLACEMENT 3 BRIDGES ON VARIOUS ROUTES IN PERRY COUNTY | District 10 | 6 | Frederick & May Construction Co | $1,711,334 | $1,972,860 | +15% | -17% | KYTC |
| 22-4101 | ASPHALT PAVEMENT & ROADWAY REHAB FEDERAL ROUTE 460 (US 460) | District 12 | 1 | Mountain Enterprises Inc | $1,568,448 | +19% | KYTC | ||
| 22-2543 | PAVEMENT (WITH ALTERNATES) RUSSELL SPRINGS TO LIBERTY ROAD (US 127) | District 8 | 2 | Strawser Construction Inc | $1,214,220 | $1,240,720 | +2.0% | +11% | KYTC |
| 22-2952 | BRIDGE PAINTING & CLEANING WEST MAIN STREET (US 150) & DANVILLE BY-PASS (US 127B) | District 7 | 3 | Euro Paint LLC | $1,091,230 | $1,269,505 | +16% | +3.0% | KYTC |
| 22-2083 | ASPHALT RESURFACING BARDSTOWN ROAD (US 31E) | District 5 | 4 | Louisville Paving Company Inc | $1,087,714 | $1,105,863 | +2.0% | -8.0% | KYTC |
| 22-4100 | ASPHALT PAVEMENT & ROADWAY REHAB KY HIGHWAY 80 (KY 80) | District 12 | 1 | Mountain Enterprises Inc | $1,079,989 | +14% | KYTC | ||
| 22-3115 | ASPHALT RESURFACING VARIOUS ROUTES IN CARTER COUNTY | District 9 | 1 | Mountain Enterprises Inc | $885,548 | +6.0% | KYTC | ||
| 22-3114 | ASPHALT RESURFACING VARIOUS ROUTES IN CALDWELL COUNTY | District 2 | 1 | Rogers Group Inc | $790,046 | +7.0% | KYTC | ||
| 22-3116 | ASPHALT RESURFACING VARIOUS ROUTES IN CASEY COUNTY | District 8 | 1 | Hinkle Contracting Company LLC | $751,645 | +3.0% | KYTC | ||
| 22-3112 | ASPHALT RESURFACING VARIOUS ROUTES IN CLAY COUNTY | District 11 | 1 | L-M Asphalt Partners LTD D/B/A Ats Construction | $746,340 | +8.0% | KYTC | ||
| 22-2542 | PAVEMENT (WITH ALTERNATES) WHITESBURG-HAZARD-JACKSON ROAD (KY 15) | District 10 | 2 | Strawser Construction Inc | $725,938 | $768,211 | +6.0% | +15% | KYTC |
| 22-2556 | FLOOD REPAIR FOR FEMA KY 469, 689, 1092, 1614, 1624, 3214, 3387 | District 12 | 1 | Hinkle Environmental Services LLC | $664,753 | -14% | KYTC | ||
| 22-3108 | ASPHALT RESURFACING KAYS / FAIRVIEW ROAD (KY1291) | District 7 | 1 | Mago Construction Company LLC | $551,308 | -6.0% | KYTC | ||
| 22-2435 | ASPHALT RESURFACING NEWBURGH ROAD (KY 1703) | District 5 | 4 | Flynn Brothers Contracting Inc | $543,671 | $613,000 | +13% | -24% | KYTC |
| 22-3111 | ASPHALT RESURFACING HOWARDS MILL ROAD (KY 1331) | District 7 | 1 | Walker Construction & Materials LLC | $529,896 | +7.0% | KYTC | ||
| 22-2535 | ASPHALT RESURFACING ST. ANDREWS CHURCH ROAD (KY 1931) | District 5 | 5 | Flynn Brothers Contracting Inc | $529,101 | $538,470 | +2.0% | -18% | KYTC |
| 22-3109 | ASPHALT RESURFACING VARIOUS ROADS IN BOYLE CO | District 7 | 1 | The Allen Company Inc | $519,967 | +6.0% | KYTC | ||
| 22-2534 | ASPHALT SURFACE WITH GRADE & DRAIN BARREN RIVER STATE PARK | District 3 | 1 | Scotty'S Contracting & Stone LLC | $513,269 | +2.0% | KYTC | ||
| 22-3110 | ASPHALT RESURFACING VARIOUS ROADS IN MERCER CO | District 7 | 1 | Mago Construction Company LLC | $498,563 | 0.0% | KYTC | ||
| 22-2536 | PAVEMENT (WITH ALTERNATES) FALMOUTH TO MT AUBURN ROAD (KY 159) | District 6 | 3 | Mago Construction Company LLC | $392,494 | $466,221 | +19% | -6.0% | KYTC |
| 22-2560 | ASPHALT RESURFACING JOHN JAMES AUDUBON STATE PARK CAMPGROUND | District 2 | 1 | E & B Paving LLC | $362,570 | +21% | KYTC | ||
| 22-2540 | PAVEMENT (WITH ALTERNATES) BEATYVILLE TO RED RIVER GORGE ROAD (KY 11) | District 10 | 2 | Hinkle Contracting Company LLC | $350,801 | $425,900 | +21% | +9.0% | KYTC |
| 22-3113 | ASPHALT RESURFACING GAVELTOWN ROAD (KY 1153) | District 3 | 1 | Scotty'S Contracting & Stone LLC | $341,224 | +1.0% | KYTC | ||
| 22-3117 | ASPHALT RESURFACING VARIOUS ROADS IN FAYETTE CO | District 7 | 1 | L-M Asphalt Partners LTD D/B/A Ats Construction | $229,971 | +6.0% | KYTC | ||
| 22-3118 | ASPHALT RESURFACING VARIOUS ROUTES IN ROCKCASTLE COUNTY | District 8 | 1 | L-M Asphalt Partners LTD D/B/A Ats Construction | $216,848 | +9.0% | KYTC | ||
| 22-2538 | ASPHALT RESURFACING PHILLIPS FORK ROAD (KY 1850) | District 11 | 1 | L-M Asphalt Partners LTD D/B/A Ats Construction | $180,839 | +4.0% | KYTC | ||
| 22-2559 | ASPHALT SURFACE WITH GRADE & DRAIN CAVE RUN LAKE ROAD (KY 826) | District 9 | 1 | Walker Construction & Materials LLC | $102,636 | -8.0% | KYTC |
Gap is the second bid over the low bid. Where a contract shows fewer bids than KYTC received, the others did not match their published totals and are left out.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.