MoDOT contract 251212-D04 bid tabulation
JCD0074 - ROUTE 179 - COLE COUNTY. Let by Missouri DOT on December 12, 2025, Cole, Central. 7 bids received; low bid $492,322 by E & C Bridge, LLC.
- Owner
- Missouri DOT
- Letting
- 12 DEC 2025
- Pay items
- 41
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | E & C Bridge, LLC | $492,322 | Low |
| 2 | Widel, Inc. | $591,661 | +20% |
| 3 | Gene Haile Excavating, Inc. | $626,985 | +27% |
| 4 | Don Schnieders Excavating Company, Inc. | $663,895 | +35% |
| 5 | West Plains Bridge & Grading, LLC | $725,000 | +47% |
| 6 | Mera Excavating, LLC | $815,640 | +66% |
| 7 | Gemstone, LLC dba Gemstone, LLC MO | $997,528 | +103% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. E & C Bridge, LLC | 2. Widel, Inc. | 3. Gene Haile Excavating, Inc. | 4. Don Schnieders Excavating Company, Inc. | 5. West Plains Bridge & Grading, LLC | 6. Mera Excavating, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Clearing and grubbing (2013000) | ACRE | 1 | $6,500.00 | $3,300.00 | $7,500.00 | $4,160.00 | $9,000.00 | $6,800.85 |
| 0020 | Removal of improvements (2022010) | LS | 1 | $20,000 | $15,000 | $7,500.00 | $5,955.00 | $5,000.00 | $2,150.87 |
| 0030 | Subgrading and shouldering class 1 (2121000A) | 100F | 1 | $2,500.00 | $1,100.00 | $2,500.00 | $3,000.00 | $2,250.00 | $7,692.33 |
| 0040 | Furnishing rock fill (2142000) | CY | 366 | $35.00 | $80.00 | $35.00 | $40.15 | $47.00 | $41.42 |
| 0050 | Placing rock fill (2143000) | CY | 366 | $25.00 | $12.00 | $15.00 | $24.60 | $28.00 | $40.37 |
| 0060 | Shaping slopes, class III (2153000) | 100F | 7 | $1,500.00 | $630.00 | $1,500.00 | $1,484.63 | $1,484.63 | $927.69 |
| 0070 | Type 1 aggregate for base (4 in. thick) (3040143) | SY | 128 | $35.00 | $8.00 | $45.00 | $18.35 | $30.00 | $50.57 |
| 0080 | Gravel (A) or crushed stone (B) (3105002) | TON | 5 | $75.00 | $100.00 | $150.00 | $100.00 | $120.00 | $157.77 |
| 0090 | Misc.optional pavement (4019905) | SY | 128 | $166.00 | $240.00 | $185.00 | $166.00 | $166.00 | $212.65 |
| 0100 | Furnishing type 2 rock blanket (6113020) | CY | 187 | $58.00 | $99.00 | $57.50 | $67.00 | $65.00 | $64.43 |
| 0110 | Placing type 2 rock blanket (6113040) | CY | 187 | $25.00 | $24.00 | $20.00 | $28.90 | $32.00 | $59.20 |
| 0120 | Construction signs (6161005) | SF | 1,157 | $6.50 | $7.50 | $7.50 | $5.25 | $6.50 | $8.40 |
| 0130 | Type 3 moveable barricade (6161030) | EACH | 8 | $145.00 | $188.00 | $160.00 | $105.00 | $145.00 | $200.88 |
| 0140 | Changeable message sign without communication interface, contractor furnished retained (6161098A) | EACH | 2 | $1,750.00 | $4,500.00 | $2,000.00 | $2,100.00 | $1,750.00 | $2,295.28 |
| 0150 | Mobilization (6181000) | LS | 1 | $40,000 | $55,000 | $85,000 | $67,500 | $81,485 | $81,346 |
| 0160 | 4 in. white class 1 pavement marking paint (18-mil, type P beads) (6206000D) | LF | 384 | $0.53 | $0.95 | $2.00 | $0.75 | $0.53 | $1.01 |
| 0170 | 4 in. yellow class 1 pavement marking paint (18-mil, type P beads) (6206001D) | LF | 384 | $0.53 | $0.95 | $2.00 | $0.75 | $0.53 | $1.01 |
| 0180 | Permanent erosion control geotextile (6240103A) | SY | 280 | $5.00 | $14.00 | $3.00 | $8.55 | $7.00 | $2.63 |
| 0190 | Contractor furnished surveying and staking (6274000) | LS | 1 | $2,500.00 | $5,000.00 | $15,000 | $4,000.00 | $12,000 | $9,690.56 |
| 0200 | Misc.seeding and mulching - cool season grasses (8059901) | LS | 1 | $3,000.00 | $5,250.00 | $3,500.00 | $3,000.00 | $3,000.00 | $8,096.81 |
| 0210 | Rock ditch check (8061005) | LF | 36 | $20.00 | $100.00 | $25.00 | $30.00 | $24.00 | $16.66 |
| 0220 | Sediment removal (8061016) | CY | 13 | $5.00 | $85.00 | $20.00 | $20.00 | $10.00 | $15.04 |
| 0230 | Silt fence (8061019) | LF | 941 | $3.00 | $3.25 | $3.50 | $3.00 | $3.00 | $3.96 |
| 0240 | MGS guardrail (6061060) | LF | 325 | $28.11 | $30.00 | $31.00 | $28.11 | $28.11 | $36.23 |
| 0250 | Bridge anchor section, 6.5 FT. posts (safety barrier curb) (new construction only) (6062204A) | EACH | 4 | $2,628.80 | $2,900.00 | $3,000.00 | $2,628.80 | $2,628.80 | $3,383.74 |
| 0260 | Asymmetrical transition section, 6.5 FT. posts (6062303) | EACH | 4 | $522.66 | $590.00 | $575.00 | $522.66 | $522.66 | $698.41 |
| 0270 | Type A crashworthy end terminal (MASH) (6063014) | EACH | 4 | $3,210.01 | $3,700.00 | $3,500.00 | $3,210.01 | $3,210.01 | $4,124.78 |
| 0280 | Breakaway assembly (perforated square steel tube) (9031241) | EACH | 2 | $487.73 | $550.00 | $525.00 | $350.00 | $487.73 | $685.89 |
| 0290 | 2.5 in. PSST post - 12 GA. (9031280) | LF | 96 | $18.23 | $21.00 | $21.00 | $20.00 | $18.23 | $24.58 |
| 0300 | Concrete post anchor for 2.5 in. PSST. - 7 GA. (9031285) | EACH | 6 | $499.80 | $565.00 | $550.00 | $300.00 | $499.80 | $658.59 |
| 0310 | SHF-flat sheet fluorescent (9035069A) | SF | 6 | $101.10 | $114.00 | $125.00 | $25.00 | $101.10 | $150.25 |
| 0320 | Removal of existing bridge deck (2162500) | SF | 2,755 | $10.50 | $15.00 | $20.00 | $18.15 | $20.00 | $16.24 |
| 0330 | Bridge approach slab (minor road) (5031011A) | SY | 118 | $0.18 | $200.00 | $200.00 | $205.00 | $280.00 | $276.02 |
| 0340 | Slab on steel (7034212) | SY | 322 | $430.00 | $395.00 | $460.00 | $592.00 | $695.00 | $654.11 |
| 0350 | Type D barrier (7034219A) | LF | 202 | $150.00 | $175.00 | $132.00 | $171.00 | $215.00 | $238.11 |
| 0360 | Protective coating - concrete bents and piers (urethane) (7110100) | LS | 1 | $12,335 | $14,000 | $3,300.00 | $12,335 | $12,335 | $12,424 |
| 0370 | Shear connectors (7121159) | EACH | 856 | $14.00 | $25.00 | $15.00 | $15.95 | $12.00 | $58.30 |
| 0380 | Strengthening existing beams (7121250) | LS | 1 | $23,000 | $30,000 | $57,250 | $73,431 | $70,000 | $84,343 |
| 0390 | Slab drain (7123610) | EACH | 10 | $350.00 | $425.00 | $485.00 | $728.00 | $500.00 | $596.60 |
| 0400 | Surface preparation for applying epoxy-mastic primer (7125102) | LS | 1 | $11,010 | $12,275 | $23,500 | $11,010 | $11,010 | $21,013 |
| 0410 | Gray epoxy-mastic primer (7125961) | LS | 1 | $25,691 | $27,000 | $11,000 | $25,691 | $7,340.29 | $21,013 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of December 12, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.