NYSDOT contract D265434 bid tabulation
Highway Project; NY-242 & NY-353 in Little Valley. Let by New York State DOT on March 13, 2025, Cattaraugus, Region 05. 5 bids received; low bid $5,482,603 by Concrete Applied Technologies Corp/DBA:Catco.
- Owner
- New York State DOT
- Letting
- 13 MAR 2025
- Pay items
- 150
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Concrete Applied Technologies Corp/DBA:Catco | $5,482,603 | Low |
| 2 | Oakgrove Construction Inc | $5,538,797 | +1.0% |
| 3 | D&H Excavating Inc | $5,651,565 | +3.0% |
| 4 | Union Concrete & Construction Corp | $5,998,650 | +9.0% |
| 5 | Cold Spring Construction Company | $6,556,655 | +20% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Concrete Applied Technologies Corp/DBA:Catco | 2. Oakgrove Construction Inc | 3. D&H Excavating Inc | 4. Union Concrete & Construction Corp | 5. Cold Spring Construction Company |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $11,800 | $7,500.00 | $4,000.00 | $100,000 | $20,000 |
| 2 | Unclassified Excavation and Disposal (203.02) | CY | 11,907 | $32.00 | $20.00 | $33.00 | $23.00 | $45.00 |
| 3 | Embankment In Place (203.03) | CY | 508 | $18.00 | $10.00 | $35.00 | $10.00 | $55.00 |
| 4 | Select Granular Fill (203.07) | CY | 1,442 | $75.00 | $55.00 | $80.00 | $84.00 | $35.00 |
| 5 | (203.24010017) | 56 | $125.00 | $75.00 | $65.00 | $155.00 | $100.00 | |
| 6 | (205.0201) | LS | 1 | $2,500.00 | $1,000.00 | $2,200.00 | $920.00 | $1,000.00 |
| 7 | Field Organic Vapor Monitoring of Contaminated Soil (205.03) | HR | 8 | $116.00 | $155.00 | $150.00 | $205.00 | $150.00 |
| 8 | Petroleum Contamination Parameter Analysis (205.0401) | EACH | 2 | $290.00 | $350.00 | $140.00 | $325.00 | $500.00 |
| 9 | Laboratory Analysis for Hazardous Waste RCRA Toxicity Characteristic (205.0402) | EACH | 1 | $205.00 | $800.00 | $750.00 | $1,315.00 | $150.00 |
| 10 | Laboratory Analysis for Ignitability (205.0403) | EACH | 1 | $60.00 | $50.00 | $50.00 | $50.00 | $100.00 |
| 11 | Laboratory Analysis for ph (205.0404) | EACH | 1 | $30.00 | $30.00 | $25.00 | $40.00 | $50.00 |
| 12 | Laboratory Analysis for Polychlorinated Biphenyls (PCB's) (205.0405) | EACH | 1 | $100.00 | $125.00 | $100.00 | $100.00 | $50.00 |
| 13 | Laboratory Analysis for Total Petroleum Hydrocarbons– Gasoline Range Organics (205.0406) | EACH | 1 | $115.00 | $120.00 | $85.00 | $140.00 | $50.00 |
| 14 | Laboratory Analysis for Total Petroleum Hydrocarbons– Diesel Range Organics (205.0407) | EACH | 1 | $99.00 | $130.00 | $115.00 | $115.00 | $50.00 |
| 15 | (205.050201) | TON | 40 | $78.00 | $95.00 | $108.00 | $105.00 | $125.00 |
| 16 | Trench and Culvert Excavation (206.0201) | CY | 3,593 | $38.00 | $25.00 | $80.00 | $45.00 | $35.00 |
| 17 | (206.03060005) | 198 | $125.00 | $60.00 | $62.00 | $55.00 | $45.00 | |
| 18 | Test Pit Excavation (206.05) | EACH | 2 | $2,500.00 | $1,500.00 | $1,700.00 | $2,750.00 | $3,000.00 |
| 19 | Seed and Mulch – Temporary (209.1003) | SY | 3,609 | $1.00 | $1.00 | $0.01 | $0.75 | $0.50 |
| 20 | Check Dam (Ditch Bottom Width >6′ to 10′), Gravel Bag – Temporary (209.110203) | EACH | 4 | $1,100.00 | $600.00 | $2,000.00 | $205.00 | $500.00 |
| 21 | Drainage Structure Inlet Protection, Gravel Bag – Temporary (209.1702) | CY | 19 | $250.00 | $300.00 | $50.00 | $115.00 | $200.00 |
| 22 | (209.23010009) | 1,575 | $6.00 | $5.00 | $10.00 | $9.50 | $6.00 | |
| 23 | (304.15200005) | 5,992 | $70.00 | $70.00 | $76.00 | $105.00 | $65.00 | |
| 24 | (404.0001) | TON | 507 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| 25 | Pavement Density Quality Adjustment to Asphalt Items (404.0002) | QUALITY UNIT | 3 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| 26 | Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003) | QUALITY UNIT | 111 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| 27 | (404.0189) | TON | 12 | $210.00 | $250.00 | $285.00 | $310.00 | $250.00 |
| 28 | (404.0962) | TON | 3,705 | $110.00 | $120.00 | $106.00 | $120.00 | $140.00 |
| 29 | (404.0982) | TON | 217 | $300.00 | $250.00 | $295.00 | $215.00 | $225.00 |
| 30 | (404.1969) | TON | 1,617 | $105.00 | $110.00 | $105.00 | $110.00 | $130.00 |
| 31 | (404.1989) | TON | 3 | $1,160.00 | $700.00 | $450.00 | $310.00 | $750.00 |
| 32 | (404.3769) | TON | 4,595 | $89.00 | $85.00 | $91.00 | $105.00 | $120.00 |
| 33 | (404.3789) | TON | 5 | $720.00 | $500.00 | $300.00 | $310.00 | $750.00 |
| 34 | Diluted Tack Coat (407.0102) | GAL | 6,989 | $4.75 | $5.00 | $5.75 | $9.50 | $8.00 |
| 35 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 51,147 | $0.50 | $0.20 | $0.30 | $0.35 | $0.01 |
| 36 | Production Cold Milling of Bituminous Concrete (490.10) | SY | 33,965 | $2.00 | $1.25 | $1.75 | $3.25 | $3.25 |
| 37 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 2,682 | $9.00 | $20.00 | $17.00 | $19.00 | $20.00 |
| 38 | Shields and Shoring (552.17) | SF | 23,058 | $0.10 | $0.50 | $0.20 | $0.25 | $0.25 |
| 39 | Culvert-End Safety Grate (603.0101) | SF | 56 | $49.00 | $35.00 | $58.00 | $45.00 | $50.00 |
| 40 | (603.171416) | EACH | 1 | $1,030.00 | $1,000.00 | $860.00 | $400.00 | $1,000.00 |
| 41 | (603.6002) | LF | 705 | $77.00 | $80.00 | $110.00 | $53.00 | $115.00 |
| 42 | (603.6602) | LF | 175 | $207.00 | $125.00 | $165.00 | $134.00 | $225.00 |
| 43 | (603.67020008) | 2 | $5,200.00 | $3,000.00 | $12,500 | $3,750.00 | $5,000.00 | |
| 44 | Concrete Collars (603.77) | EACH | 1 | $3,100.00 | $5,000.00 | $4,300.00 | $1,500.00 | $2,500.00 |
| 45 | (603.9815) | LF | 66 | $128.00 | $200.00 | $103.00 | $15.00 | $80.00 |
| 46 | (603.9818) | LF | 1,772 | $25.00 | $50.00 | $47.00 | $18.00 | $65.00 |
| 47 | (604.070501) | EACH | 5 | $1,000.00 | $500.00 | $950.00 | $4,000.00 | $1,000.00 |
| 48 | (604.070502) | EACH | 32 | $2,500.00 | $3,500.00 | $2,200.00 | $4,000.00 | $5,500.00 |
| 49 | (604.070503) | EACH | 5 | $3,500.00 | $5,000.00 | $3,200.00 | $6,000.00 | $8,000.00 |
| 50 | (604.070504) | EACH | 1 | $8,200.00 | $8,000.00 | $6,200.00 | $9,000.00 | $8,000.00 |
| 51 | (604.302122) | LF | 5 | $750.00 | $950.00 | $530.00 | $635.00 | $750.00 |
| 52 | (604.500501) | LF | 98 | $700.00 | $750.00 | $485.00 | $505.00 | $750.00 |
| 53 | (604.500502) | LF | 8 | $800.00 | $575.00 | $720.00 | $505.00 | $750.00 |
| 54 | Underdrain Filter, Type II (605.1001) | CY | 701 | $72.00 | $80.00 | $82.00 | $114.00 | $110.00 |
| 55 | (605.1701) | LF | 6,547 | $6.00 | $5.00 | $5.00 | $1.84 | $1.50 |
| 56 | Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013) | QUALITY UNIT | 1 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| 57 | Concrete Sidewalks and Driveways (608.0101) | CY | 704 | $800.00 | $675.00 | $980.00 | $925.00 | $975.00 |
| 58 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 59 | $260.00 | $250.00 | $310.00 | $310.00 | $275.00 |
| 59 | (608.21000003) | 13 | $730.00 | $800.00 | $750.00 | $645.00 | $500.00 | |
| 60 | (609.0401) | LF | 6,381 | $45.00 | $35.00 | $37.00 | $43.00 | $50.00 |
| 61 | Fertilizer (610.0501) | LB | 350 | $3.50 | $3.50 | $4.00 | $3.85 | $3.75 |
| 62 | Compost (610.10) | CY | 14 | $140.00 | $115.00 | $141.00 | $137.50 | $130.00 |
| 63 | Topsoil - Roadside (610.1402) | CY | 982 | $116.00 | $65.00 | $116.00 | $88.00 | $110.00 |
| 64 | Turf Establishment -Lawns (610.1602) | SY | 7,407 | $2.50 | $2.00 | $2.50 | $2.50 | $2.50 |
| 65 | Watering Vegetation (610.19) | 1,000 GALLONS | 35 | $168.00 | $75.00 | $170.00 | $150.00 | $150.00 |
| 66 | Mowing (610.21) | SY | 3,548 | $0.60 | $0.50 | $0.25 | $0.70 | $0.75 |
| 67 | (611.0281) | EACH | 14 | $1,450.00 | $750.00 | $1,500.00 | $1,425.00 | $1,350.00 |
| 68 | Portable Drip Irrigation System (611.17) | EACH | 14 | $61.00 | $65.00 | $62.00 | $808.50 | $60.00 |
| 69 | (611.19020024) | 14 | $28.00 | $150.00 | $28.00 | $27.50 | $30.00 | |
| 70 | Pre-Existing Stump Removal up to 24” diameter at 6 inches above grade (614.0701) | EACH | 5 | $1,550.00 | $400.00 | $390.00 | $1,500.00 | $475.00 |
| 71 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $300,000 | $831,000 | $159,921 | $363,000 | $500,000 |
| 72 | Type III Construction Barricades (619.04) | EACH | 21 | $200.00 | $100.00 | $15.00 | $325.00 | $250.00 |
| 73 | (619.080101) | LF | 336 | $4.50 | $2.00 | $4.50 | $1.50 | $4.00 |
| 74 | (619.0901) | LF | 24,797 | $0.40 | $0.25 | $0.45 | $0.35 | $0.40 |
| 75 | (619.111112) | EACH | 4 | $9,800.00 | $6,000.00 | $7,000.00 | $12,000 | $13,000 |
| 76 | Maintain Traffic Signal Equipment (Requirement A) Intersection (619.1611) | MONTH | 36 | $400.00 | $25.00 | $170.00 | $22.00 | $400.00 |
| 77 | Mailboxes (619.27) | EACH | 1 | $570.00 | $300.00 | $490.00 | $300.00 | $350.00 |
| 78 | Survey Operations (625.01) | LS | 1 | $85,000 | $35,000 | $93,000 | $75,000 | $50,000 |
| 79 | Concrete Right of Way Markers Type L (Low) (625.04) | EACH | 6 | $535.00 | $500.00 | $750.00 | $900.00 | $1,000.00 |
| 80 | Steel Pin and Cap Right of Way Markers (625.05) | EACH | 2 | $1,890.00 | $200.00 | $350.00 | $300.00 | $250.00 |
| 81 | (625.09010015) | LS | 1 | $2,100.00 | $1,000.00 | $10,000 | $1.00 | $2,500.00 |
| 82 | (627.50140008) | 7,039 | $5.00 | $4.00 | $6.50 | $3.50 | $6.00 | |
| 83 | Removal and Repair of Deteriorated Asphalt Pavement - Less than or equal to 4 Square Yards (633.1401) | SY | 280 | $91.00 | $55.00 | $63.00 | $70.00 | $110.00 |
| 84 | Removal and Repair of Deteriorated Asphalt Pavement – Greater than 4 Square Yards and less than 20 Square Yards (633.1402) | SY | 280 | $71.00 | $45.00 | $51.00 | $50.00 | $75.00 |
| 85 | Removal and Repair of Deteriorated Asphalt Pavement – 20 Square Yards or Greater (633.1403) | SY | 280 | $51.00 | $35.00 | $46.00 | $30.00 | $60.00 |
| 86 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $3,800.00 | $1,500.00 | $5,150.00 | $500.00 | $500.00 |
| 87 | Engineer’s Field Office – Type 2 (637.12) | MONTH | 24 | $2,200.00 | $2,000.00 | $2,000.00 | $1,200.00 | $2,000.00 |
| 88 | Office Technology and Supplies (637.34) | DOL | 500 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 89 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 90 | White Paint Reflectorized Pavement Stripes – 20 mils (640.20) | LF | 27,862 | $0.25 | $0.30 | $0.30 | $0.27 | $0.30 |
| 91 | Yellow Paint Reflectorized Pavement Stripes - 20 mils (640.21) | LF | 27,338 | $0.25 | $0.30 | $0.30 | $0.27 | $0.30 |
| 92 | Ground-Mounted Sign Panels without Z-bars (645.5101) | SF | 125 | $35.00 | $35.00 | $35.00 | $35.00 | $35.00 |
| 93 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 2,042 | $40.00 | $40.00 | $40.00 | $40.00 | $40.00 |
| 94 | Type A Sign Posts (645.81) | EACH | 372 | $184.00 | $175.00 | $184.00 | $180.00 | $175.00 |
| 95 | High-Capacity Type A Sign Posts with Soil Plates Only (645.8106) | EACH | 6 | $988.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 96 | (645.81090003) | 106 | $70.00 | $65.00 | $70.00 | $69.00 | $75.00 | |
| 97 | Reference Marker Panel (646.21) | EACH | 40 | $44.00 | $35.00 | $45.00 | $44.00 | $45.00 |
| 98 | Steel Post, 2.0 lb/ft (646.32) | EACH | 40 | $80.00 | $100.00 | $81.00 | $80.00 | $80.00 |
| 99 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 211 | $34.00 | $35.00 | $35.00 | $35.00 | $35.00 |
| 100 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size II (30-100 Square Feet) (647.62) | EACH | 1 | $145.00 | $100.00 | $150.00 | $145.00 | $150.00 |
| 101 | (647.83001002) | 40 | $16.00 | $50.00 | $17.00 | $20.00 | $20.00 | |
| 102 | Centerline Audible Roadway Delineators (CARDs) (649.11) | LF | 80 | $56.00 | $50.00 | $60.00 | $55.00 | $60.00 |
| 103 | Cast Frame F2, UnMountable Curb Box CU2 & Parallel Bar Grate 7 PCB (655.0805) | EACH | 18 | $2,250.00 | $2,200.00 | $2,650.00 | $3,200.00 | $4,000.00 |
| 104 | Welded Frame & Rectangular Grate 22 (655.1022) | EACH | 2 | $1,900.00 | $2,500.00 | $2,450.00 | $2,800.00 | $3,000.00 |
| 105 | (660.21180008) | 64 | $345.00 | $500.00 | $303.00 | $260.00 | $300.00 | |
| 106 | (662.60000108) | 2,500 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 107 | (662.60000208) | 2,500 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 108 | (662.60000308) | 2,500 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 109 | (663.0108) | LF | 140 | $266.00 | $400.00 | $210.00 | $265.00 | $225.00 |
| 110 | (663.1208) | EACH | 2 | $3,200.00 | $3,500.00 | $3,500.00 | $4,000.00 | $4,000.00 |
| 111 | Iron Water Main Fittings (3 - 8 inch diameter) (663.2001) | LB | 1,773 | $3.50 | $5.00 | $11.00 | $14.00 | $10.00 |
| 112 | (663.2308) | LF | 140 | $6.00 | $8.00 | $3.00 | $3.00 | $4.00 |
| 113 | (663.25000010) | 2 | $3,800.00 | $3,500.00 | $2,000.00 | $1,250.00 | $2,000.00 | |
| 114 | (663.4108) | LF | 60 | $70.00 | $5.00 | $66.00 | $25.00 | $70.00 |
| 115 | (680.05010007) | 1 | $26,500 | $22,000 | $22,400 | $22,275 | $22,000 | |
| 116 | (680.05020007) | 1 | $5,000.00 | $5,000.00 | $4,400.00 | $5,500.00 | $5,000.00 | |
| 117 | Pole Excavation and Concrete Foundation (680.5001) | CY | 3 | $3,500.00 | $3,000.00 | $2,800.00 | $3,000.00 | $5,500.00 |
| 118 | Concrete Base for Controller Cabinet (680.5002) | EACH | 1 | $4,200.00 | $3,500.00 | $9,500.00 | $4,000.00 | $4,000.00 |
| 119 | (680.510201) | EACH | 2 | $2,400.00 | $2,000.00 | $1,900.00 | $2,200.00 | $2,500.00 |
| 120 | (680.510301) | EACH | 4 | $2,650.00 | $2,500.00 | $2,200.00 | $2,475.00 | $2,500.00 |
| 121 | (680.51100010) | 1 | $600.00 | $250.00 | $400.00 | $500.00 | $500.00 | |
| 122 | (680.520105) | LF | 19 | $70.00 | $25.00 | $18.00 | $22.00 | $30.00 |
| 123 | (680.520506) | LF | 10 | $35.00 | $25.00 | $17.00 | $22.00 | $60.00 |
| 124 | (680.520508) | LF | 329 | $20.00 | $25.00 | $25.00 | $28.00 | $35.00 |
| 125 | (680.6718) | EACH | 2 | $4,700.00 | $5,000.00 | $5,100.00 | $5,500.00 | $4,000.00 |
| 126 | Single Span Wire Assembly (680.7001) | EACH | 2 | $3,700.00 | $5,000.00 | $2,100.00 | $5,500.00 | $4,500.00 |
| 127 | Riser Assembly, 1-inch Diameter (680.700603) | EACH | 2 | $1,100.00 | $1,500.00 | $1,500.00 | $1,400.00 | $850.00 |
| 128 | (680.730514) | LF | 2,345 | $5.20 | $5.00 | $5.50 | $5.00 | $8.00 |
| 129 | (680.77000105) | 1 | $1,600.00 | $10,000 | $5,600.00 | $15,000 | $4,000.00 | |
| 130 | (680.78010005) | 1 | $1,000.00 | $500.00 | $560.00 | $500.00 | $1,250.00 | |
| 131 | (680.78030005) | 4 | $1,150.00 | $2,000.00 | $560.00 | $2,200.00 | $1,250.00 | |
| 132 | (680.78040005) | 1 | $2,500.00 | $2,500.00 | $3,300.00 | $2,500.00 | $2,000.00 | |
| 133 | (680.79000105) | 1 | $2,500.00 | $2,500.00 | $5,600.00 | $2,750.00 | $5,000.00 | |
| 134 | (680.80270001) | 2 | $1,200.00 | $1,500.00 | $5,100.00 | $1,375.00 | $1,000.00 | |
| 135 | (680.80324515) | 1 | $3,500.00 | $2,500.00 | $3,400.00 | $2,750.00 | $1,500.00 | |
| 136 | (680.80324708) | 1 | $2,100.00 | $3,000.00 | $1,900.00 | $2,750.00 | $2,500.00 | |
| 137 | (680.80620215) | 2 | $1,600.00 | $2,200.00 | $2,100.00 | $2,310.00 | $10,000 | |
| 138 | Flashing Beacon Sign Assembly (680.8220) | EACH | 2 | $2,500.00 | $3,500.00 | $5,000.00 | $3,575.00 | $7,000.00 |
| 139 | (680.82250801) | 7 | $500.00 | $350.00 | $550.00 | $385.00 | $350.00 | |
| 140 | (680.83010005) | 337 | $10.00 | $3.00 | $5.50 | $2.75 | $5.00 | |
| 141 | Meter Pan (680.9402) | EACH | 2 | $900.00 | $1,000.00 | $1,900.00 | $825.00 | $1,000.00 |
| 142 | Install Electrical Disconnect/Generator Transfer Switch (680.9499) | EACH | 2 | $1,000.00 | $1,000.00 | $2,400.00 | $1,100.00 | $1,500.00 |
| 143 | (680.950106) | LF | 404 | $7.50 | $5.00 | $5.50 | $3.30 | $10.00 |
| 144 | Performance Concrete Quality Adjustment (680.99) | QUALITY UNIT | 1 | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 |
| 145 | White Preformed Reflectorized Pavement Stripes (688.01) | LF | 9,375 | $4.50 | $4.00 | $5.00 | $4.57 | $4.50 |
| 146 | Field Change Payment (FCP) (697.03) | DOL | 221,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 147 | Asphalt Price Adjustment (698.04) | DOL | 11,093.31 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 148 | Fuel Price Adjustment (698.05) | DOL | 7,164 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 149 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 150 | Mobilization (699.040001) | LS | 1 | $209,000 | $213,000 | $200,000 | $224,000 | $251,938 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of March 13, 2025. Compiled by Mirage Metrics.