Jimmy R. Lynch & Sons, Inc.: NCDOT bid record
Jimmy R. Lynch & Sons, Inc. submitted 15 bids on North Carolina DOT contracts in the data, from 19 NOV 2013 to 15 APR 2025, and was the low bidder on 2 of them (13%). When it was not low, its total sat a median +17% above the low bid.
- Owner
- North Carolina DOT
- Low bid volume
- $28,086,093
- Latest bid
- 15 APR 2025
- Data through
- 20 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2013 | 3 | 0 | 0% |
| 2014 | 4 | 0 | 0% |
| 2015 | 4 | 1 | 25% |
| 2017 | 1 | 0 | 0% |
| 2018 | 2 | 1 | 50% |
| 2025 | 1 | 0 | 0% |
By county
| County | Bids | Low bids | Win rate |
|---|---|---|---|
| Guilford | 5 | 0 | 0% |
| Forsyth | 4 | 1 | 25% |
| Stokes | 1 | 0 | 0% |
| Surry | 1 | 0 | 0% |
| Iredell | 1 | 1 | 100% |
| Rockingham | 1 | 0 | 0% |
| Rowan | 1 | 0 | 0% |
| Alamance | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Rip rap, class B | 3649000000-E | TON | 12 | 5 (42%) | $39.85 | $64.00 |
| Pipe removal | 0995000000-E | LF | 13 | 4 (31%) | $10.00 | $20.00 |
| 6" outlet pipe | 2077000000-E | LF | 12 | 4 (33%) | $16.76 | $35.00 |
| Sediment control stone | 6012000000-E | TON | 15 | 3 (20%) | $31.48 | $42.00 |
| Fertilizer for repair seeding | 6093000000-E | TON | 15 | 3 (20%) | $963.00 | $1,110.00 |
| Stone for erosion control, class A | 6006000000-E | TON | 15 | 3 (20%) | $37.00 | $48.00 |
| Fertilizer topdressing | 6108000000-E | TON | 15 | 3 (20%) | $856.00 | $1,000.00 |
| Geotextile for soil stabilization | 0196000000-E | SY | 15 | 3 (20%) | $2.00 | $2.50 |
| Specialized hand mowing | 6114500000-N | MHR | 15 | 3 (20%) | $57.75 | $64.75 |
| Foundation conditioning geo-textile | 0320000000-E | SY | 14 | 3 (21%) | $2.00 | $3.00 |
| Subdrain excavation | 2022000000-E | CY | 12 | 3 (25%) | $20.00 | $25.00 |
| Shoulder berm gutter | 2556000000-E | LF | 12 | 3 (25%) | $22.50 | $42.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Blythe Construction Inc | 10 | 3 of 10 |
| Smith-Rowe, LLC | 9 | 8 of 9 |
| W C English Incorporated | 7 | 2 of 7 |
| Triangle Grading & Paving Inc | 5 | 4 of 5 |
| Yates Construction Co., Inc. | 5 | 4 of 5 |
| Branch Highways, Inc. | 5 | 4 of 5 |
| Eastern Structures LLC | 4 | 4 of 4 |
| Blythe Development Co. | 4 | 1 of 4 |
| Dane Construction, Inc. | 4 | 3 of 4 |
| Apac - Atlantic, Inc. Thompson Arthur Division | 4 | 3 of 4 |
Latest bids
| Let | Contract | County | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 15 APR 2025 | C205059 | Stokes | GRADING, DRAINAGE, PAVING, AND STRUCTURE. BRIDGE #840286 OVER LITTLE YADKIN RIVER ON SR-1236 (NORTH OLD 52) | 6 of 7 | $8,927,051 | +37% |
| 17 JUL 2018 | C204106 | Alamance | Grading, drainage, paving, and structure. NC-119 RELOCATION NORTH OF SR-1921 (MEBANE ROGERS RD) TO SOUTH OF SR-1918 (MRS WHITE RD). | 6 of 8 | $10,425,547 | +28% |
| 19 JUN 2018 | C204124 | Forsyth | Grading, drainage, paving, signals, and structures. SR-2601 (MACY GROVE RD EXT) FROM SR-1005 (E MOUNTAIN ST) TO NC-150 (N MAIN ST) IN KERNER | 1 of 8 | $12,819,746 | Low, 8.0% under the second |
| 21 NOV 2017 | C203979 | Forsyth | Widen, grading, paving, drainage, signing, signals & strs. WINSTON-SALEM NORTHERN BELTWAY (EASTERN SECTION) FROM US-311 TO US-158 (FUTURE I- | 6 of 10 | $38,810,422 | +17% |
| 15 SEP 2015 | C203652 | Rowan | Grading, drainage, paving & structures. SR-1221 (OLD BEATTY FORD RD) FROM SR-1210/SR-1221 TO SR-1337 (LANTZ RD). | 8 of 10 | $11,972,392 | +17% |
| 16 JUN 2015 | C203645 | Rockingham | Grading, drainage, paving, & structure. US-220/FUTURE I-73 AT NC-68 - CONVERT AT-GRADE INTERSECTION TO INTERCHANGE. | 5 of 6 | $15,264,995 | +34% |
| 21 APR 2015 | C203566 | Iredell | Rest area. I-77 REST AREA PAIR ON NEW LOCATION AT MILE MARKER #58. | 1 of 6 | $15,266,347 | Low, 4.0% under the second |
| 20 JAN 2015 | C203256 | Guilford | Grading, drainage, paving, signals & structures. SR-1820 (SKEET CLUB RD) FROM EAST OF SR-1818 (JOHNSON ST) TO WEST OF NC-68 (EASTCHESTER DR) | 4 of 7 | $31,771,685 | +3.0% |
| 18 NOV 2014 | C203493 | Forsyth | Grading, drainage, paving, and structure. BRIDGE #201 OVER KERNER'S MILL CREEK ON SR-2667. | 8 of 9 | $1,267,443 | +39% |
| 16 SEP 2014 | C203489 | Guilford | Grading, drainage, paving, and structure. SR-2819 (MCLEANSVILLE RD) GRADE SEPARATION OVER NS/NCRR RAILROAD FROM SR-2826 TO NORTH OF SR-2746. | 5 of 13 | $7,999,017 | +13% |
| 17 JUN 2014 | C203412 | Guilford | Grading, drainage, paving, and structures. US-421 AT SR-3418 (NEELLEY RD) SOUTH OF GREENSBORO. | 6 of 6 | $20,999,547 | +55% |
| 20 MAY 2014 | C203415 | Guilford | Grading, drainage, and paving. NC-68 FROM SOUTH OF SR-2111 (E HARRELL RD) TO SR-4831 (BARTONSHIRE DR). | 4 of 4 | $2,382,554 | +31% |
| 17 DEC 2013 | C203287 | Surry | Grading, drainage, paving, and structure. BRIDGE #88 OVER PAUL'S CREEK ON SR-1621 (SPARGER RD). | 3 of 5 | $1,127,168 | +14% |
| 19 NOV 2013 | C203306 | Guilford | Grading, drainage, paving, and structure. BRIDGE #120 OVER REEDY FORK CREEK ON SR-2128. | 4 of 5 | $1,231,261 | +15% |
| 19 NOV 2013 | C203262 | Forsyth | Grading, drainage, paving, and structure. BRIDGE #34 OVER ABBOTT'S CREEK ON SR-1003. | 4 of 5 | $1,582,315 | +7.0% |
How this record was read
NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
- Every bid counted here matched its published total to within one dollar; NCDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.