NCDOT contract C205099 bid tabulation
GRADING, DRAINAGE, PAVING, AND SIGNALS. NC-89 (WEST PINE ST) AT SR-1397 (ROUND PEAK CHURCH RD) INTERSECTION. Let by North Carolina DOT on September 16, 2025, Surry. 4 bids received; low bid $7,490,894 by Smith-Rowe, LLC.
- Owner
- North Carolina DOT
- Letting
- 16 SEP 2025
- Pay items
- 200
- Data through
- 20 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Smith-Rowe, LLC | $7,490,894 | Low |
| 2 | Blythe Construction Inc | $8,152,848 | +9.0% |
| 3 | Mountaineer Contractors Inc and Subsidiaries | $8,270,804 | +10% |
| 4 | Hei Civil Carolinas LLC | $8,421,626 | +12% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Smith-Rowe, LLC | 2. Blythe Construction Inc | 3. Mountaineer Contractors Inc and Subsidiaries | 4. Hei Civil Carolinas LLC |
|---|---|---|---|---|---|---|---|
| 0001 | Mobilization (0000100000-N) | LS | 1 | $374,500 | $407,000 | $388,000 | $420,000 |
| 0002 | Construction surveying (0000400000-N) | LS | 1 | $43,400 | $120,000 | $145,000 | $78,000 |
| 0003 | Generic miscellaneous item (LS) - pre-construction surveys (0000900000-N) | LS | 1 | $4,135.00 | $8,300.00 | $15,000 | $25,000 |
| 0004 | Unclassified excavation (0022000000-E) | CY | 23,000 | $1.00 | $40.00 | $42.00 | $21.50 |
| 0005 | Undercut excavation (0036000000-E) | CY | 450 | $31.44 | $16.00 | $75.00 | $44.00 |
| 0006 | Supplementary clearing & grubbing (0050000000-E) | ACRE | 1 | $1.00 | $10,000 | $15,000 | $5,363.00 |
| 0007 | Grading (0063000000-N) | LS | 1 | $1,707,355 | $1,365,000 | $575,100 | $575,000 |
| 0008 | Drainage ditch excavation (0134000000-E) | CY | 310 | $24.18 | $25.00 | $55.00 | $69.50 |
| 0009 | Select granular material (0195000000-E) | CY | 400 | $0.01 | $64.00 | $155.00 | $69.00 |
| 0010 | Geotextile for soil stabilization (0196000000-E) | SY | 700 | $5.37 | $3.11 | $5.00 | $8.25 |
| 0011 | Temporary shoring (0199000000-E) | SF | 434 | $63.15 | $50.00 | $86.00 | $292.00 |
| 0012 | Foundation conditioning material, minor structures (0318000000-E) | TON | 271 | $46.98 | $37.00 | $100.00 | $69.00 |
| 0013 | FND condit geotextile (4A) (0321000000-E) | SY | 7,324 | $0.05 | $3.30 | $3.50 | $6.75 |
| 0014 | 15" drainage pipe (0335200000-E) | LF | 552 | $93.17 | $65.00 | $145.00 | $72.50 |
| 0015 | 18" drainage pipe (0335300000-E) | LF | 162 | $93.96 | $91.00 | $148.00 | $118.00 |
| 0016 | 15" RC pipe culverts, class III (0366000000-E) | LF | 24 | $130.05 | $65.00 | $150.00 | $166.00 |
| 0017 | 18" RC pipe culverts, class III (0372000000-E) | LF | 104 | $141.61 | $91.00 | $155.00 | $171.00 |
| 0018 | 15" RC pipe culverts, class IV (0448200000-E) | LF | 1,300 | $122.42 | $68.00 | $145.00 | $122.00 |
| 0019 | 18" RC pipe culverts, class IV (0448300000-E) | LF | 240 | $153.47 | $81.00 | $160.00 | $172.00 |
| 0020 | **"WLD STL pipe grad B in soil - (24", 0.250") (0973100000-E) | LF | 310 | $905.40 | $1,000.00 | $1,100.00 | $752.00 |
| 0021 | **"WLD STL pipe grad B not in soil - (24", 0.250") (0973300000-E) | LF | 310 | $1,977.41 | $1,870.00 | $2,000.00 | $1,752.00 |
| 0022 | Pipe removal (0995000000-E) | LF | 872 | $26.87 | $18.00 | $56.00 | $59.50 |
| 0023 | Shallow undercut (1099500000-E) | CY | 200 | $25.15 | $14.00 | $69.00 | $15.00 |
| 0024 | Class IV subgrade stabilization (1099700000-E) | TON | 400 | $52.50 | $39.00 | $66.00 | $68.00 |
| 0025 | Geotextile for subgrade stabilization (1112000000-E) | SY | 600 | $6.25 | $3.40 | $6.00 | $12.00 |
| 0026 | Aggregate base course (1121000000-E) | TON | 3,395 | $47.34 | $35.00 | $55.00 | $116.00 |
| 0027 | Incidental stone base (1220000000-E) | TON | 100 | $62.75 | $52.00 | $89.00 | $78.00 |
| 0028 | Prime coat (1275000000-E) | GAL | 3,198 | $5.00 | $5.00 | $5.25 | $5.00 |
| 0029 | Incidental milling (1330000000-E) | SY | 1,800 | $20.00 | $11.00 | $15.00 | $24.50 |
| 0030 | Asphalt conc base course, type B25.0C (1491000000-E) | TON | 2,700 | $125.00 | $132.61 | $132.61 | $134.00 |
| 0031 | Asphalt conc intermediate course, type I19.0C (1503000000-E) | TON | 2,470 | $125.00 | $132.61 | $132.61 | $134.00 |
| 0032 | Asphalt conc surface course, type S9.5C (1523000000-E) | TON | 3,400 | $130.00 | $132.61 | $132.61 | $134.00 |
| 0033 | Asphalt binder for plant mix (1575000000-E) | TON | 445 | $725.00 | $720.00 | $720.00 | $728.00 |
| 0034 | Right-of-way markers (2000000000-N) | EACH | 17 | $275.00 | $340.00 | $425.00 | $322.00 |
| 0035 | Control-of-access markers (2020000000-N) | EACH | 6 | $325.00 | $340.00 | $505.00 | $322.00 |
| 0036 | Subdrain excavation (2022000000-E) | CY | 103 | $29.50 | $35.00 | $98.00 | $71.00 |
| 0037 | Geotextile for subsurface drains (2026000000-E) | SY | 460 | $7.17 | $12.00 | $3.25 | $8.25 |
| 0038 | Subdrain coarse aggregate (2036000000-E) | CY | 77.30 | $89.77 | $85.00 | $155.00 | $152.00 |
| 0039 | 6" perforated subdrain pipe (2044000000-E) | LF | 460 | $10.10 | $17.00 | $35.00 | $67.50 |
| 0040 | Subdrain pipe outlet (2070000000-N) | EACH | 1 | $545.37 | $480.00 | $1,100.00 | $3,897.00 |
| 0041 | 6" outlet pipe (2077000000-E) | LF | 6 | $70.67 | $40.00 | $71.00 | $140.00 |
| 0042 | Temporary steel plate covers for masonry drainage structure (2190000000-N) | EACH | 2 | $1,799.31 | $2,340.00 | $450.00 | $8,483.00 |
| 0043 | Pipe collars (2253000000-E) | CY | 0.40 | $6,552.08 | $2,900.00 | $2,550.00 | $11,860 |
| 0044 | Pipe plugs (2264000000-E) | CY | 0.14 | $15,483 | $7,400.00 | $6,800.00 | $23,800 |
| 0045 | Flowable fill (2275000000-E) | CY | 38 | $943.26 | $370.00 | $475.00 | $880.00 |
| 0046 | Masonry drainage structures (2286000000-N) | EACH | 37 | $4,507.22 | $2,200.00 | $3,725.00 | $5,605.00 |
| 0047 | Masonry drainage structures (2308000000-E) | LF | 0.70 | $634.21 | $605.00 | $1,125.00 | $361.60 |
| 0048 | Frame with two grates, STD 840.16 (2364000000-N) | EACH | 3 | $1,911.09 | $1,425.00 | $850.00 | $3,127.00 |
| 0049 | Frame with two grates, STD 840.20 (2364200000-N) | EACH | 12 | $1,434.64 | $1,150.00 | $750.00 | $3,127.00 |
| 0050 | Frame with two grates, STD 840.22 (2365000000-N) | EACH | 1 | $1,305.17 | $1,300.00 | $700.00 | $3,127.00 |
| 0051 | Frame-GRT-HD 840.03 ** - (E) (2374000000-N) | EACH | 2 | $1,439.82 | $1,430.00 | $960.00 | $2,754.00 |
| 0052 | Frame-GRT-HD 840.03 ** - (F) (2374000000-N) | EACH | 13 | $1,439.82 | $1,480.00 | $970.00 | $2,831.00 |
| 0053 | Frame-GRT-HD 840.03 ** - (G) (2374000000-N) | EACH | 3 | $1,439.82 | $1,470.00 | $970.00 | $2,831.00 |
| 0054 | Frame with cover, STD 840.54 (2396000000-N) | EACH | 1 | $1,134.27 | $1,200.00 | $570.00 | $2,181.00 |
| 0055 | Concrete transitional section for drop inlet (2451000000-N) | EACH | 3 | $2,500.00 | $2,500.00 | $2,500.00 | $1,326.00 |
| 0056 | **"X**" concrete curb - (8" X 18") (2535000000-E) | LF | 280 | $40.00 | $28.00 | $45.00 | $41.00 |
| 0057 | 1'-6" concrete curb & gutter (2542000000-E) | LF | 1,870 | $28.00 | $30.00 | $45.00 | $23.00 |
| 0058 | 2'-6" concrete curb & gutter (2549000000-E) | LF | 2,350 | $32.00 | $35.00 | $47.00 | $27.50 |
| 0059 | Concrete expressway gutter (2577000000-E) | LF | 390 | $90.00 | $50.00 | $74.00 | $56.00 |
| 0060 | 4" concrete island cover (2627000000-E) | SY | 300 | $100.00 | $72.00 | $72.00 | $91.50 |
| 0061 | 5" monolithic concrete islands (keyed in) (2655000000-E) | SY | 700 | $100.00 | $130.00 | $130.00 | $87.00 |
| 0062 | Generic paving item (SY) - 12" concrete truck apron (2738000000-E) | SY | 530 | $180.00 | $210.00 | $210.00 | $176.00 |
| 0063 | Steel beam guardrail (3030000000-E) | LF | 1,275 | $23.50 | $23.50 | $23.50 | $24.50 |
| 0064 | Additional guardrail posts (3150000000-N) | EACH | 10 | $1.00 | $1.00 | $1.00 | $44.00 |
| 0065 | Guardrail end units, type cat-1 (3210000000-N) | EACH | 2 | $950.00 | $950.00 | $950.00 | $1,250.00 |
| 0066 | Guardrail end units, type TL-3 (3287000000-N) | EACH | 1 | $3,200.00 | $3,200.00 | $3,200.00 | $3,450.00 |
| 0067 | Remove existing guardrail (3360000000-E) | LF | 812.50 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0068 | Temporary steel beam guardrail (3380000000-E) | LF | 525 | $12.00 | $12.00 | $12.00 | $12.00 |
| 0069 | Temp GDRL end units ***** - (TL-3) (3389150000-N) | EACH | 1 | $3,000.00 | $3,000.00 | $3,000.00 | $2,500.00 |
| 0070 | Temporary additional guardrail posts (3389160000-N) | EACH | 5 | $1.00 | $1.00 | $1.00 | $11.00 |
| 0071 | Woven wire fence, 47" fabric (3503000000-E) | LF | 2,460 | $7.00 | $7.00 | $7.00 | $5.50 |
| 0072 | 4" timber fence posts, 7'-6" long (3509000000-E) | EACH | 155 | $32.00 | $32.00 | $32.00 | $45.00 |
| 0073 | 5" timber fence posts, 8'-0" long (3515000000-E) | EACH | 39 | $42.00 | $42.00 | $42.00 | $55.00 |
| 0074 | Temp **" WW fence W/posts - (48") (3563000000-E) | LF | 1,145 | $7.00 | $7.00 | $7.00 | $9.00 |
| 0075 | Rip rap, class II (3635000000-E) | TON | 97 | $66.13 | $45.00 | $160.00 | $124.00 |
| 0076 | Rip rap, class B (3649000000-E) | TON | 467 | $58.31 | $38.00 | $155.00 | $240.00 |
| 0077 | Geotextile for drainage (3656000000-E) | SY | 1,979 | $4.35 | $3.00 | $2.00 | $8.75 |
| 0078 | Contr furn, type ***sign - (D) (4025000000-E) | SF | 60 | $18.00 | $18.00 | $100.00 | $21.00 |
| 0079 | Contr furn, type ***sign - (E) (4025000000-E) | SF | 257 | $18.00 | $18.00 | $85.00 | $18.50 |
| 0080 | Contr furn, type ***sign - (F) (4025000000-E) | SF | 50 | $18.00 | $18.00 | $75.00 | $25.00 |
| 0081 | Reinforced concrete sign foundations (4048000000-E) | CY | 1 | $10.00 | $10.00 | $3,200.00 | $2,500.00 |
| 0082 | Plain concrete sign foundations (4054000000-E) | CY | 1 | $10.00 | $10.00 | $2,800.00 | $2,500.00 |
| 0083 | Supports, breakaway steel beam (4060000000-E) | LB | 1,100 | $9.75 | $9.75 | $7.50 | $25.00 |
| 0084 | Supports, 3-LB steel U-channel (4072000000-E) | LF | 1,071 | $8.00 | $8.00 | $10.00 | $9.50 |
| 0085 | Supports, steel square tube (4080200000-E) | LF | 9 | $20.00 | $20.00 | $10.00 | $25.00 |
| 0086 | Sign erection, type D (4096000000-N) | EACH | 6 | $175.00 | $175.00 | $100.00 | $300.00 |
| 0087 | Sign erection, type E (4102000000-N) | EACH | 47 | $75.00 | $75.00 | $85.00 | $250.00 |
| 0088 | Sign erection, type F (4108000000-N) | EACH | 4 | $175.00 | $175.00 | $75.00 | $275.00 |
| 0089 | Sign erect, reloc ** GRD MTD - (A) (4116100000-N) | EACH | 1 | $1,200.00 | $1,200.00 | $65.00 | $225.00 |
| 0090 | Sign erect, reloc ** GRD MTD - (B) (4116100000-N) | EACH | 1 | $900.00 | $900.00 | $65.00 | $225.00 |
| 0091 | Sign erect, reloc ** GRD MTD - (D) (4116100000-N) | EACH | 10 | $250.00 | $250.00 | $100.00 | $225.00 |
| 0092 | Sign erect, reloc ** GRD MTD - (F) (4116100000-N) | EACH | 1 | $300.00 | $300.00 | $75.00 | $175.00 |
| 0093 | Disposal of support, steel beam (4138000000-N) | EACH | 2 | $400.00 | $400.00 | $55.00 | $5.00 |
| 0094 | Disposal of sign system, U-channel (4155000000-N) | EACH | 25 | $5.00 | $5.00 | $35.00 | $5.00 |
| 0095 | Disposal of support, U-channel (4192000000-N) | EACH | 10 | $5.00 | $5.00 | $35.00 | $5.00 |
| 0096 | Work zone signs (stationary) (4400000000-E) | SF | 1,243 | $9.00 | $9.00 | $6.45 | $6.50 |
| 0097 | Work zone signs (portable) (4405000000-E) | SF | 16 | $60.60 | $50.00 | $14.26 | $8.50 |
| 0098 | Work zone signs (barricade mounted) (4410000000-E) | SF | 723 | $8.75 | $8.75 | $8.75 | $8.75 |
| 0099 | Flashing arrow board (4415000000-N) | EACH | 1 | $2,775.00 | $2,900.00 | $2,900.00 | $2,900.00 |
| 0100 | Portable changeable message sign (4420000000-N) | EACH | 2 | $9,625.00 | $12,600 | $8,300.00 | $8,300.00 |
| 0101 | Drums (4430000000-N) | EACH | 150 | $76.15 | $48.00 | $9.00 | $46.00 |
| 0102 | Barricades (type III) (4445000000-E) | LF | 624 | $36.00 | $36.00 | $15.00 | $24.00 |
| 0103 | Flagger (4455000000-N) | DAY | 374 | $497.50 | $349.04 | $350.00 | $787.00 |
| 0104 | Temporary crash cushions (4465000000-N) | EACH | 10 | $5,100.00 | $7,950.00 | $5,200.00 | $16,700 |
| 0105 | Remove & reset temporary crash cushion (4470000000-N) | EACH | 3 | $4,860.00 | $3,250.00 | $6,300.00 | $5,350.00 |
| 0106 | Portable concrete barrier (anchored) (4490000000-E) | LF | 2,638 | $49.40 | $72.91 | $15.00 | $73.00 |
| 0107 | Remove & reset portable concrete barrier (anchored) (4505000000-E) | LF | 725 | $41.75 | $23.84 | $20.00 | $24.00 |
| 0108 | Law enforcement (4510000000-N) | HR | 80 | $72.85 | $65.00 | $96.00 | $125.00 |
| 0109 | Tubular markers (fixed) (4520000000-N) | EACH | 25 | $125.00 | $125.00 | $65.00 | $55.00 |
| 0110 | Temporary raised pavement markers (4650000000-N) | EACH | 3,350 | $8.00 | $6.00 | $6.00 | $7.00 |
| 0111 | Thermoplastic pavement marking lines (4", 90 mils) (4685000000-E) | LF | 18,700 | $1.50 | $2.00 | $2.25 | $0.80 |
| 0112 | Thermoplastic pavement marking lines (8", 90 mils) (4695000000-E) | LF | 1,000 | $4.00 | $3.00 | $3.00 | $2.00 |
| 0113 | Thermoplastic pavement marking lines (24", 90 mils) (4709000000-E) | LF | 20 | $10.00 | $20.00 | $20.00 | $20.00 |
| 0114 | Thermoplastic pavement marking symbol (90 mils) (4725000000-E) | EACH | 18 | $125.00 | $175.00 | $175.00 | $150.00 |
| 0115 | Paint pavement marking lines (4") (4810000000-E) | LF | 15,315 | $0.15 | $0.40 | $0.40 | $0.20 |
| 0116 | Paint pavement marking lines (6") (4815000000-E) | LF | 158,432 | $0.16 | $0.42 | $0.42 | $0.20 |
| 0117 | Paint pavement marking lines (8") (4820000000-E) | LF | 570 | $0.30 | $0.75 | $0.75 | $0.80 |
| 0118 | Paint pavement marking lines (12") (4825000000-E) | LF | 4,163 | $1.00 | $2.00 | $2.00 | $1.00 |
| 0119 | Paint pavement marking lines (24") (4835000000-E) | LF | 180 | $3.00 | $7.00 | $7.00 | $3.00 |
| 0120 | Paint pavement marking character (4840000000-N) | EACH | 48 | $60.00 | $70.00 | $70.00 | $50.00 |
| 0121 | Paint pavement marking symbol (4845000000-N) | EACH | 66 | $60.00 | $70.00 | $70.00 | $50.00 |
| 0122 | Removal of pavement marking lines (4") (4850000000-E) | LF | 15,315 | $0.35 | $0.20 | $0.20 | $0.10 |
| 0123 | Removal of pavement marking lines (6") (4855000000-E) | LF | 158,432 | $0.35 | $0.26 | $0.26 | $0.12 |
| 0124 | Removal of pavement marking lines (12") (4865000000-E) | LF | 4,163 | $0.45 | $4.00 | $4.00 | $3.00 |
| 0125 | Removal of pavement marking lines (24") (4870000000-E) | LF | 180 | $1.00 | $7.00 | $7.00 | $5.00 |
| 0126 | Removal of pavement marking symbols & characters (4875000000-N) | EACH | 114 | $60.00 | $100.00 | $100.00 | $95.00 |
| 0127 | Generic pavement marking item (LF) - yield line paint pavement marking, 24" (4890000000-E) | LF | 80 | $10.00 | $7.00 | $7.00 | $10.00 |
| 0128 | Generic pavement marking item (LF) - yield line thermoplastic pavement marking (24", 90 mils) (4890000000-E) | LF | 80 | $10.00 | $20.00 | $20.00 | $40.00 |
| 0129 | Generic pavement marking item (EA) - polycarbonate H-shaped markers (4895000000-N) | EACH | 200 | $65.00 | $95.00 | $95.00 | $130.00 |
| 0130 | Object markers (type **) - (1) (4957000000-N) | EACH | 8 | $125.00 | $60.00 | $60.00 | $125.00 |
| 0131 | Class B concrete for encasing utility lines (5319000000-E) | CY | 8 | $1,511.50 | $1,500.00 | $525.00 | $1,702.00 |
| 0132 | 8" water line (5325800000-E) | LF | 791 | $121.69 | $145.00 | $135.00 | $155.00 |
| 0133 | DI H2O pipe fittings (5329000000-E) | LB | 1,800 | $18.60 | $15.00 | $7.00 | $10.00 |
| 0134 | **" insertion valve - (6") (5562000000-E) | EACH | 1 | $24,128 | $14,500 | $25,000 | $31,580 |
| 0135 | 6" tapping sleeve & valve (5571600000-E) | EACH | 1 | $11,420 | $4,800.00 | $13,000 | $16,209 |
| 0136 | 8" tapping sleeve & valve (5571800000-E) | EACH | 2 | $14,525 | $5,200.00 | $14,500 | $31,589 |
| 0137 | 8" air release valve (5589800000-E) | EACH | 1 | $8,327.10 | $9,200.00 | $11,000 | $7,107.00 |
| 0138 | 2" blow off (5606000000-E) | EACH | 2 | $10,772 | $1,250.00 | $13,250 | $16,582 |
| 0139 | Fire hydrant (5666000000-N) | EACH | 1 | $11,569 | $11,200 | $13,650 | $25,144 |
| 0140 | 8" line stop (5678600000-E) | EACH | 1 | $19,370 | $15,500 | $13,500 | $5,575.00 |
| 0141 | 8" sanitary gravity sewer (5691300000-E) | LF | 142 | $467.30 | $125.00 | $250.00 | $248.00 |
| 0142 | 5' dia utility manhole (5776000000-E) | EACH | 2 | $11,143 | $7,500.00 | $12,155 | $13,200 |
| 0143 | Utility manhole wall 5' dia (5782000000-E) | LF | 19 | $894.71 | $1,500.00 | $510.00 | $1,184.00 |
| 0144 | Abandon 6" utility pipe (5800000000-E) | LF | 71 | $33.21 | $16.00 | $40.00 | $48.00 |
| 0145 | Abandon 8" utility pipe (5801000000-E) | LF | 539 | $45.68 | $16.00 | $21.00 | $48.00 |
| 0146 | Abandon 10" utility pipe (5802000000-E) | LF | 251 | $34.99 | $18.00 | $26.00 | $47.50 |
| 0147 | Remove fire hydrant (5815500000-N) | EACH | 1 | $1,973.48 | $1,500.00 | $1,500.00 | $2,385.00 |
| 0148 | Remove utility manhole (5828000000-N) | EACH | 2 | $1,691.86 | $3,200.00 | $4,500.00 | $3,146.00 |
| 0149 | 16" encasement pipe (5835700000-E) | LF | 341 | $228.77 | $240.00 | $206.00 | $223.00 |
| 0150 | Bore & jack **" - (16") (5872500000-E) | LF | 95 | $2,130.18 | $2,120.00 | $2,500.00 | $2,434.00 |
| 0151 | Temporary silt fence (6000000000-E) | LF | 3,305 | $3.05 | $2.90 | $2.70 | $2.75 |
| 0152 | Stone for erosion control, class A (6006000000-E) | TON | 450 | $0.01 | $39.17 | $117.00 | $77.50 |
| 0153 | Stone for erosion control, class B (6009000000-E) | TON | 1,000 | $0.01 | $42.20 | $115.00 | $123.00 |
| 0154 | Sediment control stone (6012000000-E) | TON | 840 | $0.01 | $44.78 | $118.00 | $102.00 |
| 0155 | Temporary mulching (6015000000-E) | ACRE | 17.50 | $200.00 | $1,600.00 | $1,350.00 | $1,350.00 |
| 0156 | Seed for temporary seeding (6018000000-E) | LB | 900 | $2.00 | $2.00 | $2.50 | $2.50 |
| 0157 | Fertilizer for temporary seeding (6021000000-E) | TON | 6.50 | $1,100.00 | $900.00 | $1,800.00 | $1,800.00 |
| 0158 | Temporary slope drains (6024000000-E) | LF | 200 | $27.85 | $21.79 | $35.00 | $119.00 |
| 0159 | Safety fence (6029000000-E) | LF | 260 | $3.75 | $3.00 | $2.00 | $2.00 |
| 0160 | Silt excavation (6030000000-E) | CY | 3,670 | $0.01 | $15.85 | $35.00 | $51.50 |
| 0161 | Matting for erosion control (6036000000-E) | SY | 15,050 | $1.35 | $1.65 | $2.00 | $1.75 |
| 0162 | Coir fiber mat (6037000000-E) | SY | 100 | $10.00 | $6.00 | $5.40 | $5.50 |
| 0163 | 1/4" hardware cloth (6042000000-E) | LF | 2,180 | $4.00 | $5.00 | $5.40 | $5.50 |
| 0164 | Low permeability geotextile (6043000000-E) | SY | 300 | $4.35 | $6.00 | $4.20 | $5.00 |
| 0165 | Flocculant (6071002000-E) | LB | 245 | $1.00 | $5.00 | $5.00 | $25.00 |
| 0166 | Coir fiber baffle (6071030000-E) | LF | 30 | $50.00 | $9.00 | $20.00 | $20.00 |
| 0167 | **" skimmer - (1-1/2") (6071050000-E) | EACH | 2 | $1,707.78 | $1,163.30 | $1,500.00 | $3,384.00 |
| 0168 | **" skimmer - (2") (6071050000-E) | EACH | 1 | $2,078.55 | $2,482.64 | $2,500.00 | $2,460.00 |
| 0169 | Seeding and mulching (6084000000-E) | ACRE | 15 | $2,810.00 | $2,850.00 | $2,700.00 | $27.00 |
| 0170 | Mowing (6087000000-E) | ACRE | 12 | $150.00 | $250.00 | $100.00 | $100.00 |
| 0171 | Seed for repair seeding (6090000000-E) | LB | 200 | $5.00 | $4.50 | $2.50 | $2.50 |
| 0172 | Fertilizer for repair seeding (6093000000-E) | TON | 0.50 | $900.00 | $1,400.00 | $1,800.00 | $1,800.00 |
| 0173 | Seed for supplemental seeding (6096000000-E) | LB | 325 | $4.00 | $4.50 | $2.50 | $2.50 |
| 0174 | Fertilizer topdressing (6108000000-E) | TON | 9.50 | $950.00 | $925.00 | $1,800.00 | $1,800.00 |
| 0175 | Specialized hand mowing (6114500000-N) | MHR | 10 | $200.00 | $175.00 | $50.00 | $50.00 |
| 0176 | Manual litter removal (6114800000-N) | MHR | 7 | $236.75 | $175.00 | $300.00 | $150.00 |
| 0177 | Litter disposal (6114900000-E) | TON | 1 | $500.00 | $200.00 | $1,000.00 | $1,000.00 |
| 0178 | Response for erosion control (6117000000-N) | EACH | 88 | $1.00 | $200.00 | $100.00 | $100.00 |
| 0179 | Concrete washout structure (6117500000-N) | EACH | 1 | $1,115.10 | $1,279.25 | $450.00 | $1,719.00 |
| 0180 | Generic erosion control item (EA) - fabric insert inlet protection cleanout (6132000000-N) | EACH | 12 | $239.63 | $199.72 | $400.00 | $250.00 |
| 0181 | Generic erosion control item (EA) - fabric insert inlet protection, type 1 (6132000000-N) | EACH | 4 | $378.88 | $199.72 | $415.00 | $250.00 |
| 0182 | Generic erosion control item (EA) - prefabricated concrete washout (6132000000-N) | EACH | 6 | $789.58 | $535.81 | $1,200.00 | $4,457.00 |
| 0183 | Generic erosion control item (SY) - permanent soil reinforcement mat, type 2 (6141000000-E) | SY | 55 | $10.00 | $6.00 | $30.00 | $8.00 |
| 0184 | Signal cable (7060000000-E) | LF | 375 | $4.25 | $5.00 | $5.00 | $5.00 |
| 0185 | Vehicle signal head (12", 3 section) (7120000000-E) | EACH | 6 | $1,000.00 | $1,550.00 | $1,550.00 | $1,550.00 |
| 0186 | Vehicle signal head (12", 5 section) (7144000000-E) | EACH | 1 | $1,700.00 | $2,460.00 | $2,460.00 | $2,460.00 |
| 0187 | Messenger cable (3/8") (7264000000-E) | LF | 150 | $4.25 | $11.00 | $11.00 | $11.00 |
| 0188 | Unpaved trench (***********) - (2, 2") (7300000000-E) | LF | 10 | $150.00 | $61.00 | $61.00 | $61.00 |
| 0189 | Junction box (over-sized, heavy duty) (7348000000-N) | EACH | 1 | $1,600.00 | $2,000.00 | $2,000.00 | $2,000.00 |
| 0190 | Wood pole (7360000000-N) | EACH | 2 | $1,800.00 | $2,810.00 | $2,810.00 | $2,810.00 |
| 0191 | Guy assembly (7372000000-N) | EACH | 2 | $700.00 | $1,160.00 | $1,160.00 | $1,160.00 |
| 0192 | 2" riser with weatherhead (7420000000-E) | EACH | 1 | $1,200.00 | $1,500.00 | $1,500.00 | $1,500.00 |
| 0193 | Site survey (7481000000-N) | EACH | 1 | $1,500.00 | $1,450.00 | $1,450.00 | $1,450.00 |
| 0194 | Camera without internal loop emulator processing unit (7481240000-N) | EACH | 4 | $7,640.00 | $2,850.00 | $2,850.00 | $2,850.00 |
| 0195 | External loop emulator processing unit (7481260000-N) | EACH | 1 | $1,630.00 | $17,200 | $17,200 | $17,200 |
| 0196 | Sign for signals (7636000000-N) | EACH | 2 | $500.00 | $1,450.00 | $900.00 | $900.00 |
| 0197 | Signal cabinet foundation (7684000000-N) | EACH | 1 | $1,400.00 | $4,805.00 | $4,805.00 | $4,805.00 |
| 0198 | Contlrs with CBNT (**************) - (type 2070LX, base mounted) (7696000000-N) | EACH | 1 | $19,000 | $31,000 | $31,000 | $31,000 |
| 0199 | Cabinet base extender (7901000000-N) | EACH | 1 | $1,100.00 | $910.00 | $910.00 | $910.00 |
| 0200 | Generic signal item (EA) - luminaire arm for temporary video system (7980000000-N) | EACH | 4 | $1,000.00 | $1,150.00 | $1,150.00 | $1,150.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NCDOT's tabulation for this contract. NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
Every contract let that day: NCDOT letting of September 16, 2025. Compiled by Mirage Metrics.