NCDOT contract C205159 bid tabulation
GRADING, DRAINAGE, PAVING, AND STRUCTURES. NC-28 FROM WEST OF SR-1228 (STECOAH RD) TO SR-1235 (GUNTERS GAP RD). Let by North Carolina DOT on May 19, 2026, Graham. 3 bids received; low bid $42,945,300 by Watson Contracting Inc.
- Owner
- North Carolina DOT
- Letting
- 19 MAY 2026
- Pay items
- 197
- Data through
- 20 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Watson Contracting Inc | $42,945,300 | Low |
| 2 | Precision Pipeline LLC | $45,556,187 | +6.0% |
| 3 | Charles Blalock & Sons, Inc. | $46,958,715 | +9.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Watson Contracting Inc | 2. Precision Pipeline LLC | 3. Charles Blalock & Sons, Inc. |
|---|---|---|---|---|---|---|
| 0001 | Mobilization (0000100000-N) | LS | 1 | $2,145,000 | $500,000 | $2,350,000 |
| 0002 | Construction surveying (0000400000-N) | LS | 1 | $550,000 | $360,000 | $2,200,000 |
| 0003 | Clearing & grubbing (0001000000-E) | LS | 1 | $3,275,000 | $75,000 | $8,728,000 |
| 0004 | Supplementary clearing & grubbing (0008000000-E) | ACRE | 2 | $18,000 | $75,000 | $20,800 |
| 0005 | Unclassified excavation (0022000000-E) | CY | 410,000 | $33.00 | $40.00 | $31.00 |
| 0006 | Undercut excavation (0036000000-E) | CY | 22,680 | $12.00 | $35.00 | $31.20 |
| 0007 | Drainage ditch excavation (0134000000-E) | CY | 800 | $25.00 | $25.00 | $36.40 |
| 0008 | Removal of existing asphalt pavement (0156000000-E) | SY | 7,750 | $6.50 | $35.00 | $10.40 |
| 0009 | Select granular material, class III (0194000000-E) | CY | 13,630 | $55.00 | $70.00 | $93.60 |
| 0010 | Geotextile for soil stabilization (0196000000-E) | SY | 11,450 | $4.50 | $8.00 | $5.20 |
| 0011 | Temporary shoring (0199000000-E) | SF | 630 | $225.00 | $140.00 | $236.50 |
| 0012 | Geotextile for rock embankments (0222000000-E) | SY | 3,510 | $4.50 | $8.00 | $6.24 |
| 0013 | Generic grading item (SY) - geotextile for embankment stabilization (0241000000-E) | SY | 2,980 | $4.50 | $45.00 | $7.28 |
| 0014 | Generic grading item (SY) - geotextile for rock fill (0241000000-E) | SY | 300 | $4.50 | $8.00 | $12.48 |
| 0015 | Generic grading item (SY) - pre-splitting of rock (0241000000-E) | SY | 7,600 | $80.00 | $85.00 | $78.10 |
| 0016 | Generic grading item (SY) - wire mesh (type 1) (0241000000-E) | SY | 750 | $315.00 | $210.00 | $94.60 |
| 0017 | Generic grading item (SY) - wire mesh (type 2) (0241000000-E) | SY | 750 | $345.00 | $210.00 | $108.90 |
| 0018 | Generic grading item (TON) - hauling and disposal of petroleum contaminated soil (0255000000-E) | TON | 50 | $250.00 | $250.00 | $182.00 |
| 0019 | Generic grading item (TON) - rock fill for embankment stabilization (0255000000-E) | TON | 600 | $88.50 | $135.00 | $78.00 |
| 0020 | Generic grading item (TON) - select material, class IV for rock embankments (0255000000-E) | TON | 910 | $88.50 | $135.00 | $78.00 |
| 0021 | Generic grading item (TON) - select material, class VI for rock embankments (0255000000-E) | TON | 1,340 | $88.50 | $135.00 | $78.00 |
| 0022 | Generic grading item (TON) - select material, class VI for rock fill (0255000000-E) | TON | 150 | $88.50 | $135.00 | $78.00 |
| 0023 | Generic grading item (TON) - select material, class VII for rock embankments (0255000000-E) | TON | 5,270 | $88.50 | $135.00 | $83.20 |
| 0024 | Generic grading item (LF) - horizontal drains (0257000000-E) | LF | 210 | $575.00 | $45.00 | $59.95 |
| 0025 | Generic grading item (LF) - tensioned spot rock bolt - 75 kips (0257000000-E) | LF | 3,060 | $425.00 | $105.00 | $168.30 |
| 0026 | Generic grading item (LF) - untensioned rock anchor (0257000000-E) | LF | 3,000 | $630.00 | $90.00 | $138.60 |
| 0027 | Foundation conditioning material, minor structures (0318000000-E) | TON | 430 | $65.00 | $65.00 | $78.00 |
| 0028 | FND condit geotextile (4A) (0321000000-E) | SY | 1,340 | $4.50 | $8.00 | $5.20 |
| 0029 | 15" drainage pipe (0335200000-E) | LF | 732 | $140.00 | $77.00 | $156.00 |
| 0030 | 18" drainage pipe (0335300000-E) | LF | 452 | $144.00 | $84.00 | $208.00 |
| 0031 | **" drainage pipe elbow - (18") (0335850000-E) | EACH | 1 | $950.00 | $750.00 | $1,664.00 |
| 0032 | 30" RC pipe culverts, class III (0384000000-E) | LF | 80 | $235.00 | $165.00 | $348.40 |
| 0033 | 15" RC pipe culverts, class IV (0448200000-E) | LF | 1,428 | $130.00 | $120.00 | $182.00 |
| 0034 | 18" RC pipe culverts, class IV (0448300000-E) | LF | 704 | $210.00 | $155.00 | $208.00 |
| 0035 | 30" RC pipe culverts, class IV (0448500000-E) | LF | 76 | $275.00 | $200.00 | $364.00 |
| 0036 | **" caa pipe CLVT *****" - (60", 0.135") (0546000000-E) | LF | 100 | $1,400.00 | $575.00 | $1,024.40 |
| 0037 | 18" CS pipe culverts, 0.064" thick inlet used based on county (0588000000-E) | LF | 396 | $175.00 | $95.00 | $234.00 |
| 0038 | 30" CS pipe culverts, 0.079" thick (0600000000-E) | LF | 40 | $340.00 | $300.00 | $364.00 |
| 0039 | **" CS elbow *****" thick - (18", 0.064") (0636000000-E) | EACH | 6 | $1,600.00 | $1,000.00 | $1,664.00 |
| 0040 | **"WLD STL pipe grad B in soil - (60", 0.500") (0973100000-E) | LF | 73 | $2,500.00 | $680.00 | $2,528.90 |
| 0041 | **"WLD STL pipe grad B not in soil - (60", 0.500") (0973300000-E) | LF | 73 | $6,250.00 | $1,000.00 | $4,068.90 |
| 0042 | Pipe removal (0995000000-E) | LF | 1,093 | $50.00 | $40.00 | $20.80 |
| 0043 | Fine grading (1011000000-N) | LS | 1 | $2,250,000 | $5,339,216 | $884,000 |
| 0044 | Shallow undercut (1099500000-E) | CY | 300 | $35.00 | $35.00 | $52.00 |
| 0045 | Class IV subgrade stabilization (1099700000-E) | TON | 3,160 | $60.00 | $60.00 | $69.68 |
| 0046 | Stabilizer aggregate (1110000000-E) | TON | 150 | $88.50 | $60.00 | $69.68 |
| 0047 | Geotextile for subgrade stabilization (1112000000-E) | SY | 6,760 | $6.00 | $8.00 | $7.28 |
| 0048 | Aggregate base course (1121000000-E) | TON | 1,800 | $60.00 | $60.00 | $69.68 |
| 0049 | Incidental stone base (1220000000-E) | TON | 4,000 | $60.00 | $61.00 | $69.68 |
| 0050 | Mill asp PVMT *****" DTH - (1-1/2") (1297000000-E) | SY | 2,000 | $4.25 | $8.50 | $8.80 |
| 0051 | Milln asphalt PVMT ***** - ***** - (0" to 3") (1308000000-E) | SY | 1,000 | $4.25 | $18.00 | $16.50 |
| 0052 | Incidental milling (1330000000-E) | SY | 400 | $15.00 | $17.00 | $110.00 |
| 0053 | Asphalt conc base course, type B25.0C (1491000000-E) | TON | 8,900 | $140.00 | $190.00 | $138.60 |
| 0054 | Asphalt conc intermediate course, type I19.0C (1503000000-E) | TON | 6,300 | $142.00 | $190.00 | $140.80 |
| 0055 | Asphalt conc surface course, type S9.5C (1523000000-E) | TON | 8,100 | $135.00 | $220.00 | $148.50 |
| 0056 | Asphalt binder for plant mix (1575000000-E) | TON | 1,200 | $840.00 | $800.00 | $858.00 |
| 0057 | Asphalt plant mix, pavement repair (1693000000-E) | TON | 1,000 | $215.00 | $800.00 | $265.00 |
| 0058 | Subdrain excavation (2022000000-E) | CY | 268.80 | $30.00 | $37.00 | $31.20 |
| 0059 | Geotextile for subsurface drains (2026000000-E) | SY | 1,200 | $4.50 | $8.00 | $7.28 |
| 0060 | Subdrain coarse aggregate (2036000000-E) | CY | 201.60 | $120.00 | $100.00 | $114.40 |
| 0061 | 6" perforated subdrain pipe (2044000000-E) | LF | 1,200 | $53.00 | $22.00 | $17.68 |
| 0062 | Subdrain pipe outlet (2070000000-N) | EACH | 3 | $1,200.00 | $250.00 | $1,456.00 |
| 0063 | 6" outlet pipe (2077000000-E) | LF | 18 | $60.00 | $25.00 | $78.00 |
| 0064 | Temporary steel plate covers for masonry drainage structure (2190000000-N) | EACH | 3 | $975.00 | $2,000.00 | $624.00 |
| 0065 | Reinforced endwalls (2220000000-E) | CY | 5.90 | $3,000.00 | $1,800.00 | $4,420.00 |
| 0066 | Pipe collars (2253000000-E) | CY | 0.45 | $894.85 | $2,100.00 | $5,118.57 |
| 0067 | Pipe plugs (2264000000-E) | CY | 0.01 | $25,000 | $1,800.00 | $104,000 |
| 0068 | Flowable fill (2275000000-E) | CY | 146 | $450.00 | $572.00 | $665.60 |
| 0069 | Masonry drainage structures (2286000000-N) | EACH | 58 | $3,400.00 | $3,750.00 | $6,760.00 |
| 0070 | Masonry drainage structures (2297000000-E) | CY | 8.80 | $2,200.00 | $1,000.00 | $4,160.00 |
| 0071 | Masonry drainage structures (2308000000-E) | LF | 6.80 | $600.00 | $3,750.00 | $988.00 |
| 0072 | Frame with two grates, STD 840.16 (2364000000-N) | EACH | 2 | $700.00 | $900.00 | $1,560.00 |
| 0073 | Frame with two grates, STD 840.20 (2364200000-N) | EACH | 12 | $1,300.00 | $800.00 | $1,560.00 |
| 0074 | Frame with two grates, STD 840.22 (2365000000-N) | EACH | 5 | $1,975.00 | $800.00 | $1,560.00 |
| 0075 | Frame with two grates, STD 840.29 (2367000000-N) | EACH | 2 | $1,250.00 | $800.00 | $1,560.00 |
| 0076 | Frame-GRT-HD 840.03 ** - (E) (2374000000-N) | EACH | 2 | $1,100.00 | $800.00 | $1,664.00 |
| 0077 | Frame-GRT-HD 840.03 ** - (F) (2374000000-N) | EACH | 17 | $1,100.00 | $850.00 | $1,664.00 |
| 0078 | Frame-GRT-HD 840.03 ** - (G) (2374000000-N) | EACH | 22 | $1,100.00 | $850.00 | $1,664.00 |
| 0079 | Frame with cover, STD 840.54 (2396000000-N) | EACH | 1 | $700.00 | $1,600.00 | $1,456.00 |
| 0080 | Concrete transitional section for drop inlet (2451000000-N) | EACH | 4 | $2,650.00 | $4,000.00 | $1,650.00 |
| 0081 | **"X**" concrete curb - (8" X 12") (2535000000-E) | LF | 205 | $65.00 | $70.00 | $55.00 |
| 0082 | 2'-6" concrete curb & gutter (2549000000-E) | LF | 7,750 | $42.00 | $60.00 | $48.51 |
| 0083 | Shoulder berm gutter (2556000000-E) | LF | 340 | $50.00 | $80.00 | $60.78 |
| 0084 | Concrete curb ramps (2605000000-N) | EACH | 4 | $3,800.00 | $3,600.00 | $4,125.00 |
| 0085 | 6" concrete driveway (2612000000-E) | SY | 230 | $170.00 | $130.00 | $118.46 |
| 0086 | 4" concrete paved ditch (2619000000-E) | SY | 145 | $250.00 | $190.00 | $242.00 |
| 0087 | 5" monolithic concrete islands (surface mounted) (2647000000-E) | SY | 350 | $240.00 | $150.00 | $122.25 |
| 0088 | Var HT conc barrier ******* - (T-2) (2717000000-E) | LF | 1,470 | $525.00 | $600.00 | $772.26 |
| 0089 | Precast reinforced concrete barrier, single faced (2724000000-E) | LF | 225 | $360.00 | $360.00 | $236.41 |
| 0090 | Generic paving item (SY) - 4" concrete multi-use path (2738000000-E) | SY | 3,610 | $90.00 | $210.00 | $77.48 |
| 0091 | Adjustment of manholes (2830000000-N) | EACH | 1 | $2,500.00 | $1,200.00 | $1,560.00 |
| 0092 | Convert existing drop inlet to catch basin (2920000000-N) | EACH | 1 | $2,500.00 | $4,830.00 | $6,760.00 |
| 0093 | Convert existing junction box to catch basin (2965000000-N) | EACH | 4 | $2,500.00 | $5,000.00 | $6,760.00 |
| 0094 | Steel beam guardrail (3030000000-E) | LF | 7,700 | $28.00 | $35.00 | $25.72 |
| 0095 | Steel beam guardrail, shop curved (3045000000-E) | LF | 237.50 | $32.00 | $45.00 | $27.78 |
| 0096 | Additional guardrail posts (3150000000-N) | EACH | 10 | $90.00 | $108.00 | $61.11 |
| 0097 | Guardrail end units, type at-1 (3195000000-N) | EACH | 3 | $1,250.00 | $1,250.00 | $944.45 |
| 0098 | Guardrail end units, type cat-1 (3210000000-N) | EACH | 1 | $1,100.00 | $1,600.00 | $1,055.56 |
| 0099 | Guardrail end units, type TL-3 (3287000000-N) | EACH | 24 | $3,500.00 | $3,750.00 | $3,500.00 |
| 0100 | Guardrail end units, type TL-2 (3288000000-N) | EACH | 1 | $2,650.00 | $3,700.00 | $3,444.44 |
| 0101 | Guardrail anchor units, type B-77 (3317000000-N) | EACH | 6 | $3,500.00 | $3,400.00 | $2,722.22 |
| 0102 | Remove existing guardrail (3360000000-E) | LF | 3,310 | $2.50 | $2.00 | $1.11 |
| 0103 | Temporary steel beam guardrail (3380000000-E) | LF | 556.25 | $14.00 | $21.00 | $7.78 |
| 0104 | Temporary steel beam guardrail, shop curved (3382000000-E) | LF | 25 | $26.00 | $25.00 | $11.11 |
| 0105 | Temp GDRL end units ***** - (at-1) (3389150000-N) | EACH | 1 | $800.00 | $2,700.00 | $277.78 |
| 0106 | Temp GDRL end units ***** - (TL-3) (3389150000-N) | EACH | 5 | $1,300.00 | $2,700.00 | $1,944.44 |
| 0107 | Generic guardrail item (LF) - wood rub rail (3420000000-E) | LF | 2,750 | $8.50 | $20.00 | $16.11 |
| 0108 | Barbed wire fence reset (3569000000-E) | LF | 300 | $15.00 | $15.00 | $13.33 |
| 0109 | Generic fencing item (LF) - handrail on retaining wall (3575000000-E) | LF | 220 | $350.00 | $190.00 | $344.44 |
| 0110 | Generic fencing item (LF) - timber rail fence (3575000000-E) | LF | 3,250 | $50.00 | $175.00 | $56.89 |
| 0111 | Rip rap, class I (3628000000-E) | TON | 235 | $83.50 | $88.00 | $114.40 |
| 0112 | Rip rap, class II (3635000000-E) | TON | 125 | $83.50 | $62.00 | $114.40 |
| 0113 | Rip rap, class A (3642000000-E) | TON | 850 | $83.50 | $61.00 | $114.40 |
| 0114 | Rip rap, class B (3649000000-E) | TON | 1,050 | $83.50 | $72.00 | $114.40 |
| 0115 | Geotextile for drainage (3656000000-E) | SY | 2,700 | $4.50 | $8.00 | $5.20 |
| 0116 | Generic erosion control item (TON) - natural landscape stone (3684000000-E) | TON | 50 | $475.00 | $110.00 | $312.00 |
| 0117 | Supports, 3-LB steel U-channel (4072000000-E) | LF | 650 | $13.50 | $10.00 | $9.90 |
| 0118 | Sign erection, type D (4096000000-N) | EACH | 7 | $350.00 | $258.00 | $247.50 |
| 0119 | Sign erection, type E (4102000000-N) | EACH | 22 | $300.00 | $200.00 | $137.50 |
| 0120 | Sign erect, reloc ** GRD MTD - (E) (4116100000-N) | EACH | 2 | $175.00 | $300.00 | $137.50 |
| 0121 | Sign erect, reloc ** GRD MTD - (F) (4116100000-N) | EACH | 1 | $175.00 | $300.00 | $165.00 |
| 0122 | Disposal of sign system, U-channel (4155000000-N) | EACH | 30 | $25.00 | $27.00 | $22.00 |
| 0123 | Disposal of support, U-channel (4192000000-N) | EACH | 1 | $25.00 | $20.00 | $22.00 |
| 0124 | Generic signing item (EA) - rectangular rapid flashing beacon assembly (RRFB) removal (4360000000-N) | EACH | 4 | $1,601.00 | $1,000.00 | $1,650.00 |
| 0125 | Work zone signs (stationary) (4400000000-E) | SF | 366 | $12.50 | $9.00 | $9.35 |
| 0126 | Work zone signs (portable) (4405000000-E) | SF | 288 | $30.00 | $16.00 | $9.35 |
| 0127 | Work zone signs (barricade mounted) (4410000000-E) | SF | 54 | $10.00 | $10.00 | $8.80 |
| 0128 | Flashing arrow board (4415000000-N) | EACH | 1 | $5,000.00 | $4,000.00 | $880.00 |
| 0129 | Portable changeable message sign (4420000000-N) | EACH | 1 | $21,500 | $15,000 | $21,450 |
| 0130 | Drums (4430000000-N) | EACH | 345 | $52.00 | $65.00 | $57.75 |
| 0131 | Cones (4435000000-N) | EACH | 50 | $47.00 | $33.00 | $22.00 |
| 0132 | Barricades (type III) (4445000000-E) | LF | 82 | $30.00 | $36.00 | $30.80 |
| 0133 | Pedestrian channelizing devices (4447000000-E) | LF | 50 | $65.00 | $28.00 | $71.50 |
| 0134 | Flagger (4455000000-N) | DAY | 800 | $550.00 | $450.00 | $416.00 |
| 0135 | Temporary crash cushions (4465000000-N) | EACH | 2 | $10,500 | $8,500.00 | $10,450 |
| 0136 | Remove & reset temporary crash cushion (4470000000-N) | EACH | 2 | $4,000.00 | $2,875.00 | $3,850.00 |
| 0137 | TMA (4480000000-N) | EACH | 1 | $30,000 | $30,000 | $6,050.00 |
| 0138 | Portable concrete barrier (anchored) (4490000000-E) | LF | 365 | $85.00 | $75.00 | $104.00 |
| 0139 | Remove & reset portable concrete barrier (anchored) (4505000000-E) | LF | 225 | $40.00 | $46.00 | $52.00 |
| 0140 | Temporary raised pavement markers (4650000000-N) | EACH | 283 | $16.50 | $18.00 | $15.95 |
| 0141 | Thermoplastic pavement marking lines (4", 90 mils) (4685000000-E) | LF | 31,338 | $1.75 | $2.00 | $1.71 |
| 0142 | Thermoplastic pavement marking lines (12", 90 mils) (4700000000-E) | LF | 885 | $8.70 | $10.00 | $8.25 |
| 0143 | Thermoplastic pavement marking lines (24", 90 mils) (4709000000-E) | LF | 171 | $17.25 | $20.00 | $17.05 |
| 0144 | Thermoplastic pavement marking symbol (90 mils) (4725000000-E) | EACH | 10 | $315.00 | $300.00 | $302.50 |
| 0145 | Paint pavement marking lines (4") (4810000000-E) | LF | 44,214 | $0.75 | $1.00 | $0.55 |
| 0146 | Paint pavement marking lines (24") (4835000000-E) | LF | 146 | $6.50 | $8.00 | $6.33 |
| 0147 | Removal of pavement marking lines (4") (4850000000-E) | LF | 2,998 | $1.00 | $2.00 | $1.10 |
| 0148 | Removal of pavement marking lines (12") (4865000000-E) | LF | 280 | $2.60 | $2.50 | $2.48 |
| 0149 | Removal of pavement marking lines (24") (4870000000-E) | LF | 20 | $4.00 | $10.50 | $3.85 |
| 0150 | Removal of pavement marking symbols & characters (4875000000-N) | EACH | 1 | $115.00 | $120.00 | $110.00 |
| 0151 | Generic pavement marking item (EA) - polycarbonate H-shaped markers (4895000000-N) | EACH | 256 | $57.00 | $97.00 | $54.45 |
| 0152 | Temporary silt fence (6000000000-E) | LF | 39,600 | $2.75 | $5.00 | $2.59 |
| 0153 | Stone for erosion control, class A (6006000000-E) | TON | 1,325 | $80.00 | $79.00 | $104.00 |
| 0154 | Stone for erosion control, class B (6009000000-E) | TON | 8,500 | $80.00 | $74.00 | $104.00 |
| 0155 | Sediment control stone (6012000000-E) | TON | 4,100 | $75.00 | $65.00 | $104.00 |
| 0156 | Temporary mulching (6015000000-E) | ACRE | 54 | $1,800.00 | $2,100.00 | $1,760.00 |
| 0157 | Seed for temporary seeding (6018000000-E) | LB | 2,100 | $5.75 | $6.00 | $5.50 |
| 0158 | Fertilizer for temporary seeding (6021000000-E) | TON | 12 | $1,470.00 | $1,800.00 | $1,402.50 |
| 0159 | Temporary slope drains (6024000000-E) | LF | 2,750 | $40.00 | $32.00 | $36.40 |
| 0160 | Safety fence (6029000000-E) | LF | 10,600 | $1.75 | $5.00 | $1.65 |
| 0161 | Silt excavation (6030000000-E) | CY | 23,050 | $20.00 | $17.00 | $0.01 |
| 0162 | Matting for erosion control (6036000000-E) | SY | 114,255 | $1.25 | $5.00 | $1.10 |
| 0163 | Coir fiber mat (6037000000-E) | SY | 57,420 | $5.50 | $8.00 | $5.23 |
| 0164 | 1/4" hardware cloth (6042000000-E) | LF | 6,550 | $6.60 | $7.00 | $6.33 |
| 0165 | Low permeability geotextile (6043000000-E) | SY | 2,400 | $11.50 | $8.00 | $11.00 |
| 0166 | **" temporary pipe - (36") (6045000000-E) | LF | 55 | $125.00 | $75.00 | $132.00 |
| 0167 | Special stilling basins (6070000000-N) | EACH | 16 | $3,250.00 | $1,050.00 | $1,248.00 |
| 0168 | Flocculant (6071002000-E) | LB | 1,300 | $9.00 | $30.00 | $8.80 |
| 0169 | Coir fiber wattle (6071012000-E) | LF | 30 | $34.50 | $15.00 | $33.00 |
| 0170 | Wattle barrier (6071013000-E) | LF | 4,250 | $7.00 | $16.00 | $6.60 |
| 0171 | Coir fiber baffle (6071030000-E) | LF | 3,725 | $7.20 | $13.00 | $6.88 |
| 0172 | **" skimmer - (1-1/2") (6071050000-E) | EACH | 19 | $1,800.00 | $2,000.00 | $660.00 |
| 0173 | Seeding and mulching (6084000000-E) | ACRE | 54 | $3,700.00 | $3,000.00 | $3,575.00 |
| 0174 | Mowing (6087000000-E) | ACRE | 60 | $460.00 | $300.00 | $440.00 |
| 0175 | Seed for repair seeding (6090000000-E) | LB | 550 | $1.15 | $8.50 | $2.20 |
| 0176 | Fertilizer for repair seeding (6093000000-E) | TON | 2.50 | $615.00 | $2,200.00 | $660.00 |
| 0177 | Seed for supplemental seeding (6096000000-E) | LB | 1,250 | $7.00 | $9.00 | $6.60 |
| 0178 | Fertilizer topdressing (6108000000-E) | TON | 37 | $2,050.00 | $2,200.00 | $1,980.00 |
| 0179 | Impervious dike (6111000000-E) | LF | 650 | $100.00 | $190.00 | $234.00 |
| 0180 | Specialized hand mowing (6114500000-N) | MHR | 50 | $75.00 | $90.00 | $71.50 |
| 0181 | Manual litter removal (6114800000-N) | MHR | 30 | $86.00 | $85.00 | $82.50 |
| 0182 | Litter disposal (6114900000-E) | TON | 3 | $575.00 | $650.00 | $550.00 |
| 0183 | Response for erosion control (6117000000-N) | EACH | 150 | $85.00 | $350.00 | $82.50 |
| 0184 | Concrete washout structure (6117500000-N) | EACH | 3 | $1,150.00 | $2,000.00 | $1,100.00 |
| 0185 | Reforestation (6123000000-E) | ACRE | 0.50 | $11,500 | $12,500 | $11,000 |
| 0186 | Streambank reforestation (6126000000-E) | ACRE | 0.17 | $17,000 | $20,000 | $16,500 |
| 0187 | Generic erosion control item (EA) - fabric insert inlet protection cleanout (6132000000-N) | EACH | 400 | $50.00 | $680.00 | $55.00 |
| 0188 | Generic erosion control item (EA) - fabric insert inlet protection, type 1 (6132000000-N) | EACH | 135 | $100.00 | $680.00 | $22.00 |
| 0189 | Generic erosion control item (EA) - prefabricated concrete washout (6132000000-N) | EACH | 15 | $1,000.00 | $680.00 | $1,456.00 |
| 0190 | Box culv excav @ ******** - (10+67.00 -Y3A-) (8130000000-N) | LS | 1 | $120,000 | $125,000 | $200,000 |
| 0191 | Box culv excav @ ******** - (99+82.00 -Y2-) (8130000000-N) | LS | 1 | $120,000 | $125,000 | $99,000 |
| 0192 | Foundation conditioning material, box culvert (8133000000-E) | TON | 157 | $150.00 | $80.00 | $154.00 |
| 0193 | Class A concrete (culvert) (8196000000-E) | CY | 200.80 | $2,250.00 | $1,500.00 | $2,398.00 |
| 0194 | Reinforcing steel (culvert) (8245000000-E) | LB | 21,230 | $4.10 | $3.00 | $4.40 |
| 0195 | Soil nail retaining walls (8802010000-E) | SF | 1,440 | $275.00 | $225.00 | $247.50 |
| 0196 | Soil nail verification tests (8802015100-N) | EACH | 1 | $1,100.00 | $1,600.00 | $1,100.00 |
| 0197 | Soil nail proof tests (8802015110-N) | EACH | 5 | $550.00 | $1,500.00 | $550.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NCDOT's tabulation for this contract. NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
Every contract let that day: NCDOT letting of May 19, 2026. Compiled by Mirage Metrics.