Class A concrete (culvert), NCDOT 8196000000-E
Low bidders on NCDOT contracts carried a median of $1,203.73 per CY for this item, over the 24 months to 20 OCT 2026, across 29 low bids. Half of all 170 bids fell between $896.67 and $1,752.13.
- Owner
- North Carolina DOT
- Item
- 8196000000-E
- Unit
- CY
- Data through
- 20 OCT 2026
NCDOT prints this item as “CLASS A CONCRETE (CULV)”.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2013 | 17 | 17 | $575.00 | 85 | $598.05 |
| 2014 | 18 | 18 | $510.00 | 110 | $466.96 |
| 2015 | 14 | 14 | $631.60 | 94 | $600.00 |
| 2016 | 10 | 10 | $575.00 | 48 | $560.00 |
| 2017 | 16 | 16 | $656.70 | 97 | $550.00 |
| 2018 | 16 | 16 | $840.00 | 80 | $859.02 |
| 2019 | 13 | 13 | $773.73 | 63 | $935.00 |
| 2020 | 3 | 3 | $950.00 | 11 | $950.00 |
| 2021 | 11 | 11 | $692.00 | 48 | $746.36 |
| 2022 | 13 | 13 | $1,025.00 | 42 | $1,070.00 |
| 2023 | 9 | 9 | $1,204.30 | 43 | $1,175.00 |
| 2024 | 10 | 10 | $1,213.87 | 46 | $1,550.00 |
| 2025 | 13 | 13 | $1,050.00 | 67 | $1,100.00 |
| 2026 | 12 | 12 | $1,212.00 | 84 | $1,300.00 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 62.90 to 186.70 | 7 | $1,452.00 |
| 195.90 to 301.50 | 7 | $1,520.32 |
| 324.90 to 633.50 | 7 | $1,360.00 |
| 635.70 to 4,083.30 | 8 | $797.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Barnhill Contracting Company | 40 | 27 (68%) |
| Blythe Construction Inc | 44 | 18 (41%) |
| S T Wooten Corporation | 35 | 17 (49%) |
| Mountain Creek Contractors Inc | 22 | 13 (59%) |
| Balfour Beatty Infrastructure Inc | 18 | 10 (56%) |
| Triangle Grading & Paving Inc | 25 | 9 (36%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 20 OCT 2026 | C204338 | Wake | 94.60 | $1,612.37 | $1,768.00 | 8 | Blythe Construction Inc | NCDOT |
| 15 SEP 2026 | C204990 | Randolph | 186.70 | $972.00 | $1,155.00 | 9 | Apac - Atlantic, Inc. Thompson Arthur Division | NCDOT |
| 18 AUG 2026 | C205202 | Guilford | 366.60 | $900.00 | $900.00 | 5 | Triangle Grading & Paving Inc | NCDOT |
| 18 AUG 2026 | C204504 | Watauga | 330.30 | $2,060.00 | $1,620.00 | 3 | Branch Civil Inc | NCDOT |
| 16 JUN 2026 | C205157 | Randolph | 126.80 | $1,452.00 | $1,512.50 | 11 | Branch Civil Inc | NCDOT |
| 19 MAY 2026 | C204733 | Yadkin | 162.50 | $2,689.75 | $2,047.24 | 4 | Blythe Construction Inc | NCDOT |
| 19 MAY 2026 | C204773 | Gaston, Mecklenburg | 222.90 | $1,520.32 | $1,900.00 | 10 | Zachry Construction Corporation | NCDOT |
| 19 MAY 2026 | C205159 | Graham | 200.80 | $2,250.00 | $2,250.00 | 3 | Watson Contracting Inc | NCDOT |
| 17 FEB 2026 | C205036 | Robeson | 2,063.60 | $875.00 | $925.00 | 4 | Barnhill Contracting Company | NCDOT |
| 17 FEB 2026 | C205035 | Wayne | 594.30 | $813.00 | $857.07 | 8 | Branch Civil Inc | NCDOT |
| 17 FEB 2026 | C204765 | Wake | 125.70 | $897.00 | $900.00 | 9 | Sunrock Industries LLC DBA Carolina Sunrock LLC | NCDOT |
| 17 FEB 2026 | C205095 | Mecklenburg | 891.10 | $720.00 | $768.50 | 10 | Blythe Development Co. | NCDOT |
| 18 NOV 2025 | C205012 | Forsyth | 1,109.20 | $635.00 | $800.00 | 5 | Apac Atlantic Inc Smith Rowe LLC JV | NCDOT |
| 18 NOV 2025 | C205086 | Jackson | 1,011.30 | $1,344.00 | $1,762.00 | 4 | Buchanan and Sons Inc | NCDOT |
| 21 OCT 2025 | C205034 | Northampton | 336 | $2,000.00 | $2,500.00 | 2 | FSC II LLC DBA Fred Smith Company | NCDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.
How these prices were read
NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the NCDOT letting of 20 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way