NCDOT contract C204765 bid tabulation
GRADING, DRAINAGE, PAVING, SIGNALS, AND CULVERT. SR-3126 (AIRPORT BLVD) FROM GARDEN SQUARE LANE TO SR-1637 (CHURCH ST) IN MORRISVILLE. Let by North Carolina DOT on February 17, 2026, Wake. 9 bids received; low bid $9,867,642 by Sunrock Industries LLC DBA Carolina Sunrock LLC.
- Owner
- North Carolina DOT
- Letting
- 17 FEB 2026
- Pay items
- 202
- Data through
- 20 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Sunrock Industries LLC DBA Carolina Sunrock LLC | $9,867,642 | Low |
| 2 | Conti Civil LLC | $10,380,442 | +5.0% |
| 3 | FSC II LLC DBA Fred Smith Company | $10,437,373 | +6.0% |
| 4 | Cardinal Civil Contracting LLC | $10,438,655 | +6.0% |
| 5 | Branch Civil Inc | $10,517,850 | +7.0% |
| 6 | Chatham Civil Contracting LLC | $10,954,000 | +11% |
| 7 | K West Group LLC DBA Kwest Group LLC | $11,039,224 | +12% |
| 8 | S T Wooten Corporation | $12,007,381 | +22% |
| 9 | Blythe Construction Inc | $12,305,659 | +25% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Sunrock Industries LLC DBA Carolina Sunrock LLC | 2. Conti Civil LLC | 3. FSC II LLC DBA Fred Smith Company | 4. Cardinal Civil Contracting LLC | 5. Branch Civil Inc | 6. Chatham Civil Contracting LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Mobilization (0000100000-N) | LS | 1 | $542,547 | $515,000 | $520,000 | $488,926 | $460,830 | $547,700 |
| 0002 | Construction surveying (0000400000-N) | LS | 1 | $97,665 | $140,000 | $100,000 | $145,772 | $95,570 | $212,887 |
| 0003 | Unclassified excavation (0022000000-E) | CY | 28,550 | $26.00 | $38.00 | $44.00 | $59.00 | $34.00 | $15.00 |
| 0004 | Supplementary clearing & grubbing (0050000000-E) | ACRE | 1 | $3,800.00 | $2,500.00 | $1.00 | $121,477 | $22,000 | $1.00 |
| 0005 | Undercut excavation (0057000000-E) | CY | 5,300 | $34.00 | $50.00 | $13.00 | $1.34 | $46.00 | $22.00 |
| 0006 | Grading (0063000000-N) | LS | 1 | $1,470,090 | $1,184,124 | $1,766,000 | $1,105,161 | $860,994 | $2,336,165 |
| 0007 | Drainage ditch excavation (0134000000-E) | CY | 100 | $45.00 | $42.00 | $20.00 | $15.00 | $21.00 | $26.00 |
| 0008 | Select granular material (0195000000-E) | CY | 5,650 | $84.00 | $25.00 | $9.00 | $37.00 | $79.00 | $46.00 |
| 0009 | Geotextile for soil stabilization (0196000000-E) | SY | 6,550 | $5.00 | $3.50 | $2.00 | $2.75 | $3.70 | $3.00 |
| 0010 | Foundation conditioning material, minor structures (0318000000-E) | TON | 769 | $61.50 | $58.00 | $8.00 | $48.75 | $58.75 | $50.00 |
| 0011 | FND condit geotextile (4A) (0321000000-E) | SY | 2,372 | $6.00 | $3.50 | $2.00 | $5.15 | $3.95 | $3.00 |
| 0012 | 15" drainage pipe (0335200000-E) | LF | 120 | $79.00 | $110.00 | $80.00 | $79.00 | $84.75 | $60.00 |
| 0013 | 15" RC pipe culverts, class III (0366000000-E) | LF | 52 | $72.50 | $98.00 | $90.00 | $152.00 | $109.50 | $77.00 |
| 0014 | 30" RC pipe culverts, class III (0384000000-E) | LF | 48 | $255.00 | $185.00 | $235.00 | $243.00 | $239.00 | $171.00 |
| 0015 | ***" RCP culv class IV - (78") (0448000000-E) | LF | 140 | $1,231.00 | $1,290.00 | $980.00 | $928.00 | $1,260.00 | $867.00 |
| 0016 | 15" RC pipe culverts, class IV (0448200000-E) | LF | 3,656 | $79.50 | $100.00 | $85.00 | $91.00 | $110.50 | $92.00 |
| 0017 | 18" RC pipe culverts, class IV (0448300000-E) | LF | 716 | $90.00 | $126.00 | $100.00 | $144.00 | $167.00 | $102.00 |
| 0018 | 24" RC pipe culverts, class IV (0448400000-E) | LF | 88 | $137.00 | $160.00 | $148.00 | $171.00 | $170.50 | $136.00 |
| 0019 | 30" RC pipe culverts, class IV (0448500000-E) | LF | 184 | $278.00 | $250.00 | $200.00 | $227.00 | $407.00 | $176.00 |
| 0020 | Pipe removal (0995000000-E) | LF | 1,577 | $28.00 | $32.00 | $30.00 | $17.00 | $74.25 | $28.00 |
| 0021 | Shallow undercut (1099500000-E) | CY | 225 | $44.50 | $120.00 | $33.00 | $79.00 | $53.00 | $28.00 |
| 0022 | Class IV subgrade stabilization (1099700000-E) | TON | 450 | $38.50 | $50.00 | $40.00 | $35.00 | $53.50 | $29.00 |
| 0023 | Geotextile for subgrade stabilization (1112000000-E) | SY | 300 | $4.40 | $4.15 | $6.00 | $5.93 | $4.25 | $5.00 |
| 0024 | Aggregate base course (1121000000-E) | TON | 149 | $52.00 | $42.00 | $60.00 | $45.00 | $57.50 | $33.00 |
| 0025 | Incidental stone base (1220000000-E) | TON | 50 | $72.00 | $75.00 | $95.00 | $49.00 | $62.75 | $38.00 |
| 0026 | Mill asp PVMT *****" DTH - (1-1/2") (1297000000-E) | SY | 9,130 | $3.10 | $3.80 | $5.00 | $4.62 | $3.15 | $5.00 |
| 0027 | Incidental milling (1330000000-E) | SY | 1,720 | $5.20 | $11.84 | $16.00 | $16.44 | $11.05 | $13.00 |
| 0028 | Asphalt conc base course, type B25.0C (1491000000-E) | TON | 6,290 | $76.00 | $103.93 | $79.00 | $64.38 | $107.00 | $104.00 |
| 0029 | Asphalt conc intermediate course, type I19.0C (1503000000-E) | TON | 6,070 | $64.50 | $87.32 | $85.00 | $65.00 | $90.00 | $87.00 |
| 0030 | Asphalt conc surface course, type S9.5B (1519000000-E) | TON | 6,100 | $52.00 | $73.39 | $90.00 | $63.43 | $76.00 | $73.00 |
| 0031 | Asphalt binder for plant mix (1575000000-E) | TON | 975 | $500.00 | $535.71 | $600.00 | $634.00 | $551.00 | $535.00 |
| 0032 | Asphalt plant mix, pavement repair (1693000000-E) | TON | 200 | $131.00 | $344.22 | $140.00 | $179.41 | $95.00 | $963.00 |
| 0033 | Right-of-way markers (2000000000-N) | EACH | 66 | $500.00 | $350.00 | $290.00 | $432.00 | $59.00 | $364.00 |
| 0034 | Subdrain excavation (2022000000-E) | CY | 157 | $35.00 | $62.00 | $25.00 | $18.41 | $25.45 | $38.00 |
| 0035 | Geotextile for subsurface drains (2026000000-E) | SY | 700 | $10.00 | $1.00 | $8.00 | $7.28 | $6.80 | $2.00 |
| 0036 | Subdrain coarse aggregate (2036000000-E) | CY | 118 | $75.00 | $70.00 | $65.00 | $74.13 | $127.50 | $58.00 |
| 0037 | 6" perforated subdrain pipe (2044000000-E) | LF | 700 | $16.00 | $10.25 | $12.00 | $13.81 | $17.95 | $13.00 |
| 0038 | Subdrain pipe outlet (2070000000-N) | EACH | 2 | $500.00 | $450.00 | $400.00 | $324.00 | $3,373.00 | $279.00 |
| 0039 | 6" outlet pipe (2077000000-E) | LF | 12 | $40.00 | $32.00 | $40.00 | $38.41 | $97.50 | $23.00 |
| 0040 | Reinforced endwalls (2220000000-E) | CY | 7.90 | $3,582.00 | $3,760.00 | $3,100.00 | $6,347.00 | $3,123.00 | $2,663.00 |
| 0041 | Pipe collars (2253000000-E) | CY | 1.31 | $1,475.00 | $2,790.00 | $4,500.00 | $2,898.00 | $4,412.00 | $2,571.00 |
| 0042 | Flowable fill (2275000000-E) | CY | 20 | $1,175.00 | $445.00 | $450.00 | $557.00 | $1,359.00 | $297.00 |
| 0043 | Masonry drainage structures (2286000000-N) | EACH | 64 | $2,585.00 | $3,300.00 | $4,500.00 | $2,258.00 | $3,846.00 | $2,918.00 |
| 0044 | Masonry drainage structures (2308000000-E) | LF | 6 | $1,005.00 | $475.00 | $450.00 | $1,179.00 | $2,044.00 | $372.00 |
| 0045 | Frame with two grates, STD 840.16 (2364000000-N) | EACH | 12 | $1,370.00 | $1,925.00 | $1,175.00 | $1,919.00 | $1,989.00 | $923.00 |
| 0046 | Frame-GRT-HD 840.03 ** - (E) (2374000000-N) | EACH | 4 | $1,465.00 | $2,000.00 | $1,250.00 | $1,636.00 | $2,108.00 | $1,007.00 |
| 0047 | Frame-GRT-HD 840.03 ** - (F) (2374000000-N) | EACH | 21 | $1,500.00 | $2,000.00 | $1,300.00 | $1,398.00 | $2,267.00 | $1,047.00 |
| 0048 | Frame-GRT-HD 840.03 ** - (G) (2374000000-N) | EACH | 26 | $1,500.00 | $2,000.00 | $1,300.00 | $1,398.00 | $2,175.00 | $1,047.00 |
| 0049 | Frame with cover, STD 840.54 (2396000000-N) | EACH | 1 | $1,120.00 | $1,650.00 | $925.00 | $2,342.00 | $1,699.00 | $705.00 |
| 0050 | Concrete transitional section for catch basin (2440000000-N) | EACH | 6 | $1,150.00 | $1,710.00 | $1,770.00 | $1,026.00 | $1,741.00 | $1,231.00 |
| 0051 | Concrete transitional section for drop inlet (2451000000-N) | EACH | 10 | $1,450.00 | $1,710.00 | $2,075.00 | $1,296.00 | $1,741.00 | $1,552.00 |
| 0052 | 1'-6" concrete curb & gutter (2542000000-E) | LF | 2,210 | $23.45 | $31.00 | $24.00 | $25.50 | $29.75 | $31.00 |
| 0053 | 2'-6" concrete curb & gutter (2549000000-E) | LF | 6,990 | $27.35 | $33.50 | $28.00 | $32.00 | $32.55 | $35.00 |
| 0054 | 4" concrete sidewalk (2591000000-E) | SY | 2,710 | $52.20 | $71.00 | $54.00 | $61.50 | $54.00 | $79.00 |
| 0055 | Concrete curb ramps (2605000000-N) | EACH | 10 | $4,150.00 | $3,525.00 | $4,200.00 | $2,970.00 | $3,004.00 | $4,441.00 |
| 0056 | 6" concrete driveway (2612000000-E) | SY | 30 | $133.65 | $160.00 | $135.00 | $114.00 | $149.25 | $143.00 |
| 0057 | 5" monolithic concrete islands (keyed in) (2655000000-E) | SY | 510 | $115.65 | $97.00 | $118.00 | $89.00 | $103.25 | $124.00 |
| 0058 | Generic paving item (SY) - 10' multi-use path (2738000000-E) | SY | 2,060 | $60.75 | $71.00 | $62.00 | $94.00 | $65.25 | $78.00 |
| 0059 | Adjustment of catch basins (2800000000-N) | EACH | 2 | $2,365.00 | $1,000.00 | $1,100.00 | $1,121.00 | $2,428.00 | $2,659.00 |
| 0060 | Adjustment of meter boxes or valve boxes (2845000000-N) | EACH | 10 | $1,250.00 | $180.00 | $1,100.00 | $987.00 | $28.90 | $652.00 |
| 0061 | Steel beam guardrail (3030000000-E) | LF | 875 | $23.00 | $24.15 | $23.00 | $41.00 | $25.85 | $25.00 |
| 0062 | 25' clear span guardrail sections (3140000000-E) | EACH | 2 | $1,775.00 | $1,863.75 | $1,775.00 | $108.00 | $1,993.00 | $1,900.00 |
| 0063 | Additional guardrail posts (3150000000-N) | EACH | 5 | $50.00 | $52.50 | $50.00 | $47.50 | $56.25 | $54.00 |
| 0064 | Guardrail end units, type cat-1 (3210000000-N) | EACH | 4 | $1,100.00 | $1,155.00 | $1,100.00 | $1,026.00 | $1,235.00 | $1,177.00 |
| 0065 | Guardrail end units, type TL-3 (3287000000-N) | EACH | 4 | $3,300.00 | $3,465.00 | $3,300.00 | $3,617.00 | $3,706.00 | $3,531.00 |
| 0066 | Generic guardrail item (LF) - wood rub rail (3420000000-E) | LF | 260 | $23.00 | $24.15 | $23.00 | $43.20 | $25.85 | $25.00 |
| 0067 | Generic fencing item (LF) - bicycle/pedestrian safety rail (3575000000-E) | LF | 320 | $175.00 | $183.75 | $175.00 | $286.00 | $196.50 | $187.00 |
| 0068 | Generic fencing item (EA) - bollards (3578000000-N) | EACH | 6 | $2,000.00 | $2,100.00 | $2,000.00 | $1,382.00 | $2,246.00 | $2,140.00 |
| 0069 | Rip rap, class I (3628000000-E) | TON | 55 | $82.50 | $96.00 | $105.00 | $84.50 | $117.25 | $58.00 |
| 0070 | Rip rap, class II (3635000000-E) | TON | 135 | $111.00 | $105.00 | $100.00 | $97.00 | $165.00 | $67.00 |
| 0071 | Rip rap, class B (3649000000-E) | TON | 105 | $54.50 | $85.00 | $90.00 | $87.00 | $106.00 | $56.00 |
| 0072 | Geotextile for drainage (3656000000-E) | SY | 1,255 | $5.90 | $2.60 | $3.00 | $4.55 | $3.05 | $2.00 |
| 0073 | Supports, 3-LB steel U-channel (4072000000-E) | LF | 440 | $8.00 | $9.45 | $7.65 | $10.80 | $10.45 | $9.00 |
| 0074 | Sign erection, type E (4102000000-N) | EACH | 54 | $225.00 | $78.75 | $225.00 | $70.00 | $87.00 | $241.00 |
| 0075 | Disposal of sign system, U-channel (4155000000-N) | EACH | 32 | $10.00 | $2.10 | $15.00 | $27.00 | $2.30 | $11.00 |
| 0076 | Work zone signs (stationary) (4400000000-E) | SF | 694 | $9.35 | $10.50 | $8.00 | $6.75 | $12.00 | $9.00 |
| 0077 | Work zone signs (portable) (4405000000-E) | SF | 258 | $10.00 | $19.15 | $25.00 | $19.00 | $18.10 | $9.00 |
| 0078 | Work zone signs (barricade mounted) (4410000000-E) | SF | 274 | $9.60 | $8.40 | $11.50 | $7.00 | $10.25 | $9.00 |
| 0079 | Flashing arrow board (4415000000-N) | EACH | 2 | $2,645.00 | $619.48 | $3,000.00 | $2,106.00 | $3,425.00 | $2,354.00 |
| 0080 | Portable changeable message sign (short term) (4422000000-N) | DAY | 56 | $76.00 | $96.36 | $150.00 | $540.00 | $39.00 | $54.00 |
| 0081 | Drums (4430000000-N) | EACH | 115 | $53.00 | $57.00 | $65.00 | $71.00 | $50.00 | $47.00 |
| 0082 | Cones (4435000000-N) | EACH | 81 | $24.00 | $25.00 | $20.00 | $49.00 | $37.10 | $21.00 |
| 0083 | Barricades (type III) (4445000000-E) | LF | 152 | $27.50 | $23.10 | $30.00 | $20.50 | $56.00 | $25.00 |
| 0084 | Pedestrian channelizing devices (4447000000-E) | LF | 1,332 | $28.00 | $21.00 | $38.00 | $36.00 | $50.50 | $21.00 |
| 0085 | Flagger (4455000000-N) | DAY | 80 | $500.00 | $525.00 | $780.00 | $850.00 | $449.00 | $746.00 |
| 0086 | TMA (4480000000-N) | EACH | 2 | $17,360 | $9,000.00 | $2,500.00 | $15,981 | $16,840 | $48,151 |
| 0087 | Tubular markers (fixed) (4520000000-N) | EACH | 39 | $130.00 | $111.30 | $130.00 | $140.00 | $119.00 | $113.00 |
| 0088 | Thermoplastic pavement marking lines (4", 90 mils) (4685000000-E) | LF | 19,279 | $1.25 | $0.89 | $1.25 | $1.35 | $0.95 | $1.00 |
| 0089 | Thermoplastic pavement marking lines (8", 90 mils) (4695000000-E) | LF | 1,638 | $2.50 | $2.36 | $2.50 | $2.70 | $2.55 | $2.00 |
| 0090 | Thermoplastic pavement marking lines (12", 90 mils) (4700000000-E) | LF | 2,243 | $3.00 | $2.89 | $3.00 | $3.24 | $3.10 | $3.00 |
| 0091 | Thermoplastic pavement marking lines (24", 90 mils) (4709000000-E) | LF | 2,819 | $11.00 | $13.39 | $11.00 | $11.88 | $14.30 | $14.00 |
| 0092 | Thermoplastic pavement marking character (90 mils) (4720000000-E) | EACH | 40 | $100.00 | $105.00 | $100.00 | $108.00 | $112.25 | $107.00 |
| 0093 | Thermoplastic pavement marking symbol (90 mils) (4725000000-E) | EACH | 70 | $110.00 | $141.75 | $110.00 | $119.00 | $151.50 | $145.00 |
| 0094 | Heated-in-place thermoplastic pavement marking symbol (90 mils) (4726110000-E) | EACH | 10 | $215.00 | $309.75 | $215.00 | $232.00 | $331.25 | $316.00 |
| 0095 | Paint pavement marking lines (4") (4810000000-E) | LF | 24,035 | $0.35 | $0.11 | $0.35 | $0.38 | $0.10 | $0.15 |
| 0096 | Paint pavement marking lines (8") (4820000000-E) | LF | 2,132 | $0.95 | $0.47 | $0.95 | $1.03 | $0.50 | $0.50 |
| 0097 | Paint pavement marking lines (12") (4825000000-E) | LF | 1,500 | $2.00 | $1.31 | $2.00 | $2.16 | $1.50 | $1.50 |
| 0098 | Paint pavement marking lines (24") (4835000000-E) | LF | 1,004 | $8.00 | $1.58 | $8.00 | $8.64 | $1.70 | $2.00 |
| 0099 | Paint pavement marking character (4840000000-N) | EACH | 18 | $75.00 | $57.75 | $75.00 | $80.98 | $61.75 | $59.00 |
| 0100 | Paint pavement marking symbol (4845000000-N) | EACH | 2 | $75.00 | $57.75 | $75.00 | $80.98 | $61.75 | $59.00 |
| 0101 | Removal of pavement marking lines (4") (4850000000-E) | LF | 8,827 | $1.25 | $1.00 | $1.25 | $1.35 | $1.05 | $1.00 |
| 0102 | Removal of pavement marking lines (24") (4870000000-E) | LF | 88 | $4.00 | $5.78 | $4.00 | $4.32 | $6.20 | $6.00 |
| 0103 | Removal of pavement marking symbols & characters (4875000000-N) | EACH | 12 | $65.00 | $94.50 | $65.00 | $70.19 | $101.00 | $96.00 |
| 0104 | Generic pavement marking item (LF) - yield line paint pavement marking (12") (4890000000-E) | LF | 44 | $2.00 | $26.25 | $2.00 | $2.16 | $28.05 | $27.00 |
| 0105 | Generic pavement marking item (LF) - yield line thermoplastic pavement marking (12", 90 mils) (4890000000-E) | LF | 44 | $3.00 | $47.25 | $3.00 | $3.24 | $50.50 | $48.00 |
| 0106 | Generic pavement marking item (EA) - polycarbonate H-shaped markers (4895000000-N) | EACH | 545 | $55.00 | $57.75 | $55.00 | $59.39 | $61.75 | $59.00 |
| 0107 | Portable lighting (5255000000-N) | LS | 1 | $50,460 | $32,500 | $7,500.00 | $15,044 | $33,690 | $136,662 |
| 0108 | Generic lighting item (LF) - 2" street lighting conduit, type BD (5265000000-E) | LF | 4,560 | $25.00 | $12.34 | $12.00 | $9.23 | $13.20 | $9.00 |
| 0109 | Generic lighting item (LF) - 2" street lighting conduit, type TL (5265000000-E) | LF | 350 | $50.00 | $28.88 | $28.00 | $27.74 | $31.15 | $37.00 |
| 0110 | 12" water line (5326200000-E) | LF | 2,103 | $165.00 | $200.00 | $185.00 | $122.00 | $185.25 | $121.00 |
| 0111 | DI H2O pipe fittings (5329000000-E) | LB | 4,885 | $17.00 | $10.00 | $12.00 | $7.00 | $19.10 | $11.00 |
| 0112 | 6" valve (5540000000-E) | EACH | 4 | $3,450.00 | $3,000.00 | $3,700.00 | $2,631.00 | $3,874.00 | $2,955.00 |
| 0113 | 12" valve (5558000000-E) | EACH | 6 | $7,950.00 | $7,000.00 | $8,150.00 | $3,266.00 | $8,928.00 | $6,507.00 |
| 0114 | **" water meter - (1") (5643000000-E) | EACH | 1 | $3,500.00 | $3,750.00 | $5,550.00 | $2,337.00 | $3,930.00 | $1,825.00 |
| 0115 | **" RPZ backflow prevnt asmbly - (1") (5656000000-E) | EACH | 1 | $7,500.00 | $6,250.00 | $4,500.00 | $4,160.00 | $8,422.00 | $3,396.00 |
| 0116 | Fire hydrant (5666000000-N) | EACH | 4 | $7,450.00 | $7,250.00 | $13,000 | $6,734.00 | $8,366.00 | $6,444.00 |
| 0117 | Fire hydrant leg (5673000000-E) | LF | 106 | $205.00 | $150.00 | $90.00 | $105.00 | $230.25 | $83.00 |
| 0118 | **" water service line - (1") (5686000000-E) | LF | 85 | $90.00 | $47.00 | $80.00 | $140.00 | $101.00 | $53.00 |
| 0119 | 8" sanitary gravity sewer (5691300000-E) | LF | 20 | $605.00 | $790.00 | $600.00 | $370.00 | $679.50 | $737.00 |
| 0120 | 4' dia utility manhole (5775000000-E) | EACH | 1 | $11,395 | $10,500 | $8,500.00 | $3,888.00 | $12,800 | $8,458.00 |
| 0121 | Utility manhole wall 4' dia (5781000000-E) | LF | 8 | $850.00 | $490.00 | $350.00 | $184.00 | $954.50 | $344.00 |
| 0122 | Remove water meter (5815000000-N) | EACH | 2 | $3,495.00 | $640.00 | $1,395.00 | $893.00 | $3,925.00 | $472.00 |
| 0123 | Remove fire hydrant (5815500000-N) | EACH | 4 | $3,665.00 | $1,500.00 | $2,950.00 | $161.00 | $4,116.00 | $1,350.00 |
| 0124 | Remove utility manhole (5828000000-N) | EACH | 1 | $4,750.00 | $4,200.00 | $1,550.00 | $4,517.00 | $5,334.00 | $2,388.00 |
| 0125 | **" encasement pipe - (4") (5835000000-E) | LF | 25 | $140.00 | $150.00 | $200.00 | $290.00 | $157.25 | $43.00 |
| 0126 | 24" encasement pipe (5836000000-E) | LF | 40 | $695.00 | $327.00 | $300.00 | $319.00 | $780.50 | $424.00 |
| 0127 | Temporary silt fence (6000000000-E) | LF | 13,030 | $2.75 | $3.06 | $2.45 | $3.74 | $2.75 | $3.70 |
| 0128 | Stone for erosion control, class A (6006000000-E) | TON | 245 | $70.00 | $85.00 | $80.00 | $54.00 | $51.50 | $41.00 |
| 0129 | Stone for erosion control, class B (6009000000-E) | TON | 295 | $74.00 | $87.00 | $65.00 | $56.00 | $0.01 | $45.00 |
| 0130 | Sediment control stone (6012000000-E) | TON | 1,035 | $52.00 | $75.00 | $35.00 | $38.48 | $62.50 | $34.00 |
| 0131 | Temporary mulching (6015000000-E) | ACRE | 5.50 | $1,900.00 | $997.50 | $950.00 | $1,998.00 | $1,067.00 | $1,980.00 |
| 0132 | Seed for temporary seeding (6018000000-E) | LB | 300 | $1.00 | $4.99 | $4.75 | $2.16 | $5.35 | $2.00 |
| 0133 | Fertilizer for temporary seeding (6021000000-E) | TON | 2.50 | $275.00 | $1,050.00 | $600.00 | $1,179.00 | $1,123.00 | $1,169.00 |
| 0134 | Temporary slope drains (6024000000-E) | LF | 200 | $25.00 | $37.48 | $20.00 | $31.84 | $97.50 | $30.00 |
| 0135 | Safety fence (6029000000-E) | LF | 260 | $1.85 | $2.41 | $2.00 | $3.08 | $2.20 | $3.00 |
| 0136 | Silt excavation (6030000000-E) | CY | 1,540 | $25.50 | $30.51 | $4.00 | $8.85 | $1.00 | $2.00 |
| 0137 | Matting for erosion control (6036000000-E) | SY | 10,000 | $1.70 | $2.10 | $2.00 | $2.15 | $2.25 | $2.00 |
| 0138 | Coir fiber mat (6037000000-E) | SY | 100 | $5.00 | $3.15 | $3.00 | $4.71 | $3.35 | $6.00 |
| 0139 | 1/4" hardware cloth (6042000000-E) | LF | 4,150 | $11.00 | $5.71 | $4.00 | $3.78 | $5.75 | $4.00 |
| 0140 | Low permeability geotextile (6043000000-E) | SY | 100 | $4.20 | $5.25 | $6.00 | $3.23 | $1.40 | $4.00 |
| 0141 | Special stilling basins (6070000000-N) | EACH | 4 | $2,245.00 | $414.47 | $500.00 | $2,585.00 | $1,683.00 | $530.00 |
| 0142 | Flocculant (6071002000-E) | LB | 150 | $9.10 | $12.60 | $6.00 | $25.65 | $13.50 | $20.00 |
| 0143 | Coir fiber wattle (6071012000-E) | LF | 300 | $11.50 | $9.45 | $12.00 | $15.66 | $10.10 | $16.00 |
| 0144 | Coir fiber baffle (6071030000-E) | LF | 460 | $4.60 | $4.73 | $4.50 | $9.23 | $5.00 | $9.00 |
| 0145 | **" skimmer - (2") (6071050000-E) | EACH | 1 | $915.00 | $2,048.66 | $4,000.00 | $1,738.47 | $2,807.00 | $14,136 |
| 0146 | Seeding and mulching (6084000000-E) | ACRE | 6 | $2,750.00 | $2,257.50 | $2,150.00 | $318.54 | $2,414.00 | $5,297.00 |
| 0147 | Mowing (6087000000-E) | ACRE | 6 | $175.00 | $157.50 | $150.00 | $5,345.00 | $168.50 | $316.00 |
| 0148 | Seed for repair seeding (6090000000-E) | LB | 50 | $5.00 | $6.83 | $6.50 | $318.50 | $7.25 | $4.00 |
| 0149 | Fertilizer for repair seeding (6093000000-E) | TON | 0.25 | $400.00 | $1,050.00 | $1,000.00 | $1,179.00 | $1,123.00 | $1,169.00 |
| 0150 | Seed for supplemental seeding (6096000000-E) | LB | 100 | $5.00 | $6.83 | $6.50 | $5.38 | $7.25 | $5.00 |
| 0151 | Fertilizer topdressing (6108000000-E) | TON | 3 | $400.00 | $1,050.00 | $750.00 | $1,179.00 | $1,123.00 | $1,169.00 |
| 0152 | Impervious dike (6111000000-E) | LF | 55 | $149.89 | $157.38 | $150.00 | $118.00 | $190.00 | $81.00 |
| 0153 | Specialized hand mowing (6114500000-N) | MHR | 10 | $55.00 | $78.75 | $90.00 | $80.98 | $84.25 | $80.00 |
| 0154 | Response for erosion control (6117000000-N) | EACH | 75 | $300.00 | $157.50 | $1.00 | $140.00 | $168.50 | $107.00 |
| 0155 | Concrete washout structure (6117500000-N) | EACH | 1 | $1,730.00 | $1,620.53 | $1,250.00 | $3,330.00 | $1,957.00 | $885.00 |
| 0156 | Culvert diversion channel (6120000000-E) | CY | 298 | $48.55 | $50.98 | $95.00 | $58.62 | $61.50 | $22.00 |
| 0157 | Reforestation (6123000000-E) | ACRE | 2 | $875.00 | $1,953.00 | $1,860.00 | $2,969.50 | $2,089.00 | $2,943.00 |
| 0158 | Generic erosion control item (EA) - fabric insert inlet protection cleanout (6132000000-N) | EACH | 237 | $235.00 | $52.50 | $75.00 | $100.00 | $56.25 | $35.00 |
| 0159 | Generic erosion control item (EA) - fabric insert inlet protection, type 1 (6132000000-N) | EACH | 79 | $160.00 | $115.50 | $150.00 | $230.00 | $123.50 | $80.00 |
| 0160 | Generic erosion control item (EA) - prefabricated concrete washout (6132000000-N) | EACH | 6 | $1,875.00 | $957.49 | $1,250.00 | $270.00 | $561.50 | $744.00 |
| 0161 | Pedestrian signal head (16", 1 section W/countdown) (7048500000-E) | EACH | 8 | $898.00 | $1,550.00 | $1,460.00 | $1,295.75 | $1,640.00 | $1,562.00 |
| 0162 | Signal cable (7060000000-E) | LF | 5,200 | $4.05 | $4.93 | $4.65 | $7.00 | $5.20 | $5.00 |
| 0163 | Vehicle signal head (12", 3 section) (7120000000-E) | EACH | 15 | $1,297.00 | $1,479.00 | $1,395.00 | $1,403.75 | $1,567.00 | $1,493.00 |
| 0164 | Vehicle signal head (12", 4 section) (7132000000-E) | EACH | 6 | $1,562.00 | $1,705.00 | $1,608.00 | $1,612.00 | $1,806.00 | $1,721.00 |
| 0165 | Vehicle signal head (12", 5 section) (7144000000-E) | EACH | 4 | $1,867.00 | $1,990.00 | $1,877.00 | $1,350.00 | $2,108.00 | $2,009.00 |
| 0166 | APS detector station (7229000000-N) | EACH | 8 | $1,571.00 | $992.00 | $935.00 | $1,134.00 | $1,050.00 | $1,001.00 |
| 0167 | Central control unit APS detector station (7230000000-N) | EACH | 3 | $5,233.00 | $5,138.00 | $4,845.00 | $4,508.00 | $5,441.00 | $5,185.00 |
| 0168 | Messenger cable (3/8") (7264000000-E) | LF | 675 | $3.00 | $6.90 | $6.50 | $7.56 | $7.25 | $7.00 |
| 0169 | Tracer wire (7279000000-E) | LF | 5,475 | $1.40 | $1.33 | $0.84 | $1.89 | $1.40 | $1.00 |
| 0170 | Paved trench (***********) - (1, 2") (7288000000-E) | LF | 25 | $31.00 | $53.55 | $50.50 | $48.59 | $56.75 | $54.00 |
| 0171 | Unpaved trench (***********) - (1, 2") (7300000000-E) | LF | 1,325 | $12.00 | $12.45 | $11.75 | $18.36 | $13.20 | $13.00 |
| 0172 | Unpaved trench (***********) - (2, 2") (7300000000-E) | LF | 4,450 | $19.00 | $18.19 | $17.15 | $21.60 | $19.25 | $18.00 |
| 0173 | Direct drill (***********) - (1, 2") (7301000000-E) | LF | 255 | $31.00 | $29.15 | $27.50 | $34.55 | $30.90 | $29.00 |
| 0174 | Direct drill (***********) - (2, 2") (7301000000-E) | LF | 1,300 | $44.00 | $39.24 | $37.00 | $37.79 | $41.50 | $40.00 |
| 0175 | Junction box (***************) - (special oversized) (7312000000-N) | EACH | 3 | $1,100.00 | $1,604.70 | $1,513.00 | $3,239.00 | $1,699.00 | $1,619.00 |
| 0176 | Junction box (standard size) (7324000000-N) | EACH | 15 | $409.00 | $812.42 | $766.00 | $918.00 | $860.25 | $820.00 |
| 0177 | Junction box (over-sized, heavy duty) (7348000000-N) | EACH | 12 | $706.00 | $1,612.12 | $1,520.00 | $1,512.00 | $1,707.00 | $1,627.00 |
| 0178 | Inductive loop sawcut (7444000000-E) | LF | 2,400 | $8.70 | $19.46 | $18.35 | $16.20 | $20.60 | $20.00 |
| 0179 | Lead-in cable (14-2) (7456100000-E) | LF | 5,000 | $3.20 | $3.61 | $3.40 | $3.13 | $3.80 | $4.00 |
| 0180 | Communications cable (** fiber) - (24) (7516000000-E) | LF | 5,825 | $5.20 | $4.51 | $4.25 | $5.13 | $4.75 | $5.00 |
| 0181 | Drop cable (7528000000-E) | LF | 555 | $5.20 | $4.51 | $4.25 | $5.34 | $4.75 | $5.00 |
| 0182 | Splice enclosure (7540000000-N) | EACH | 3 | $3,032.00 | $2,651.52 | $2,500.00 | $3,240.00 | $2,807.00 | $2,675.00 |
| 0183 | Modify splice enclosure (7541000000-N) | EACH | 1 | $1,790.00 | $1,569.70 | $2,960.00 | $1,836.00 | $1,662.00 | $1,584.00 |
| 0184 | Interconnect center (7552000000-N) | EACH | 3 | $2,727.00 | $2,386.36 | $2,250.00 | $2,699.48 | $2,527.00 | $2,408.00 |
| 0185 | Delineator marker (7566000000-N) | EACH | 10 | $173.00 | $152.73 | $144.00 | $270.00 | $161.75 | $154.00 |
| 0186 | Metal strain signal pole (7576000000-N) | EACH | 6 | $13,988 | $14,462 | $13,636 | $23,216 | $15,310 | $14,592 |
| 0187 | Metal pole with single mast arm (7588000000-N) | EACH | 4 | $30,277 | $31,437 | $29,641 | $41,032 | $33,290 | $31,720 |
| 0188 | Soil test (7613000000-N) | EACH | 10 | $4,163.00 | $2,428.79 | $2,290.00 | $1,943.00 | $2,572.00 | $2,451.00 |
| 0189 | Drilled pier foundation (7614100000-E) | CY | 60 | $1,589.00 | $2,156.21 | $2,033.00 | $2,375.50 | $2,210.00 | $2,176.00 |
| 0190 | Mast arm with metal pole design (7631000000-N) | EACH | 4 | $347.00 | $847.42 | $799.00 | $216.00 | $895.00 | $855.00 |
| 0191 | Sign for signals (7636000000-N) | EACH | 9 | $561.00 | $807.12 | $761.00 | $918.00 | $855.00 | $814.00 |
| 0192 | Type II pedestal with foundation (7642200000-N) | EACH | 6 | $3,103.00 | $3,960.30 | $3,734.00 | $5,399.00 | $4,193.00 | $3,996.00 |
| 0193 | Signal cabinet foundation (7684000000-N) | EACH | 3 | $1,002.00 | $3,845.76 | $3,626.00 | $2,699.48 | $4,072.00 | $3,880.00 |
| 0194 | Contlrs with CBNT (**************) - (2070LXN2, NEMA TS-2, base mounted) (7696000000-N) | EACH | 3 | $26,945 | $29,546 | $27,858 | $35,093 | $31,280 | $29,812 |
| 0195 | Detector card (NEMA TS-2) (7852000000-N) | EACH | 11 | $456.00 | $540.91 | $510.00 | $783.00 | $572.75 | $546.00 |
| 0196 | Cabinet base extender (7901000000-N) | EACH | 3 | $492.00 | $513.33 | $484.00 | $267.00 | $543.50 | $518.00 |
| 0197 | Generic signal item (EA) - ethernet edge switch (7980000000-N) | EACH | 3 | $17,725 | $1,310.91 | $1,236.00 | $16,197 | $1,388.00 | $1,323.00 |
| 0198 | Generic signal item (EA) - relocate rectangular rapid flashing beacon assembly (7980000000-N) | EACH | 1 | $3,683.00 | $5,445.15 | $5,134.00 | $8,098.50 | $5,765.00 | $5,494.00 |
| 0199 | Box culv excav @ ******** - (18+78.00 -L-) (8130000000-N) | LS | 1 | $16,222 | $17,033 | $80,000 | $33,640 | $22,000 | $89,626 |
| 0200 | Foundation conditioning material, box culvert (8133000000-E) | TON | 117.50 | $64.00 | $66.77 | $75.00 | $64.00 | $80.75 | $54.00 |
| 0201 | Class A concrete (culvert) (8196000000-E) | CY | 125.70 | $897.00 | $900.00 | $800.00 | $1,763.61 | $1,137.00 | $1,497.00 |
| 0202 | Reinforcing steel (culvert) (8245000000-E) | LB | 19,723 | $2.40 | $2.50 | $2.50 | $1.53 | $3.00 | $3.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NCDOT's tabulation for this contract. NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
Every contract let that day: NCDOT letting of February 17, 2026. Compiled by Mirage Metrics.