| 1 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $2,000.00 | $30,000 |
| 2 | Pavement removed (202E23000) | SY | 11 | $85.00 | $200.00 |
| 3 | Walk removed (202E30000) | SF | 148 | $5.00 | $12.00 |
| 4 | Curb removed (202E32000) | FT | 13 | $12.00 | $25.00 |
| 5 | Pipe removed, 24" and under (202E35100) | FT | 32 | $30.00 | $40.00 |
| 6 | Guardrail removed (202E38000) | FT | 119 | $10.00 | $2.40 |
| 7 | Special - pipe cleanout, 24" and under (202E70110) | FT | 706 | $100.00 | $28.00 |
| 8 | Subgrade compaction (204E10000) | SY | 11 | $5.00 | $25.00 |
| 9 | Guardrail, type MGS (606E15050) | FT | 62.50 | $36.00 | $43.60 |
| 10 | Anchor assembly, MGS type T (606E26550) | EACH | 2 | $1,400.00 | $1,980.00 |
| 11 | MGS bridge terminal assembly, type 1, as per plan (606E35003) | EACH | 1 | $2,675.00 | $7,275.00 |
| 12 | MGS bridge terminal assembly, type 2, as per plan (606E35103) | EACH | 1 | $575.00 | $3,670.00 |
| 13 | 4" concrete walk (608E10000) | SF | 148 | $25.00 | $40.00 |
| 14 | Seeding and mulching (659E10000) | SY | 100 | $23.50 | $35.89 |
| 15 | Commercial fertilizer (659E20000) | TON | 0.02 | $850.00 | $1,298.50 |
| 16 | Lime (659E31000) | ACRE | 0.02 | $100.00 | $152.50 |
| 17 | Water (659E35000) | MGAL | 1 | $1.00 | $1.53 |
| 18 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 |
| 19 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $10,000 | $3,500.00 |
| 20 | 12" conduit, type B (611E04400) | FT | 32 | $125.00 | $210.00 |
| 21 | Catch basin grate, as per plan (611E98645) | EACH | 5 | $2,000.00 | $1,000.00 |
| 22 | Pavement repair (253E02000) | CY | 1 | $1,000.00 | $6,000.00 |
| 23 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 2 | $2,000.00 | $2,500.00 |
| 24 | Aggregate base (304E20000) | CY | 2 | $200.00 | $250.00 |
| 25 | Non-tracking tack coat (407E20000) | GAL | 1 | $5.00 | $150.00 |
| 26 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 1 | $2,000.00 | $5,000.00 |
| 27 | Curb, type 6 (609E26000) | FT | 13 | $40.00 | $175.00 |
| 28 | Barrier reflector, type 2 (bidirectional) (626E00110) | EACH | 4 | $13.60 | $14.00 |
| 29 | Edge line, 4" (646E10000) | MI | 1.20 | $2,100.00 | $2,100.00 |
| 30 | Center line (646E10200) | MI | 0.30 | $5,255.00 | $5,255.00 |
| 31 | Transverse/diagonal line (646E10600) | FT | 400 | $9.50 | $9.50 |
| 32 | Bike lane symbol marking (646E20600) | EACH | 10 | $250.00 | $250.00 |
| 33 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 200 | $50.00 | $93.00 |
| 34 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 6 | $2,134.47 | $2,200.00 |
| 35 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 6 | $2,234.47 | $2,300.00 |
| 36 | Barrier reflector, type 1, bidirectional (614E13310) | EACH | 93 | $13.39 | $13.39 |
| 37 | Object marker, two way (614E13360) | EACH | 93 | $20.74 | $20.74 |
| 38 | Portable changeable message sign, as per plan (614E18601) | SNMT | 15 | $989.10 | $990.00 |
| 39 | Work zone center line, class I, 642 paint (614E21100) | MI | 0.50 | $4,995.00 | $4,995.00 |
| 40 | Work zone edge line, class I, 4", 642 paint (614E22100) | MI | 1.58 | $2,635.00 | $2,635.00 |
| 41 | Work zone edge line, class I, 6", 642 paint (614E22110) | MI | 0.19 | $6,655.00 | $6,655.00 |
| 42 | Work zone dotted line, class I (614E24000) | FT | 337 | $2.15 | $2.15 |
| 43 | Portable barrier, unanchored (622E41100) | FT | 4,240 | $22.91 | $28.00 |
| 44 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $24,505 | $260,000 |
| 45 | Pipe removed (202E34900) | FT | 318 | $74.62 | $85.00 |
| 46 | Concrete reinforcement, replacement of existing concrete reinforcement, as per plan (509E20001) | LB | 524 | $10.00 | $4.00 |
| 47 | Uncoated steel reinforcement (509E25000) | LB | 3,589 | $2.00 | $3.50 |
| 48 | Class QC2 concrete, superstructure (511E34410) | CY | 20 | $2,000.00 | $4,900.00 |
| 49 | Class QC1 concrete, abutment not including footing (511E44110) | CY | 9 | $2,000.00 | $3,400.00 |
| 50 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 3,240 | $19.75 | $27.00 |
| 51 | Treating of concrete bridge deck with SRS (512E10400) | SY | 1,231 | $12.15 | $9.25 |
| 52 | Concrete repair by epoxy injection (512E10600) | FT | 422 | $153.00 | $90.00 |
| 53 | Treating concrete bridge decks with gravity fed resin (512E73500) | SY | 3,950 | $17.25 | $14.25 |
| 54 | Removal of existing coatings from concrete surfaces, as per plan (512E74001) | SY | 29 | $100.00 | $36.00 |
| 55 | Structural steel members, level UF, as per plan (513E10201) | LB | 2,361 | $8.00 | $9.00 |
| 56 | Surface preparation of existing structural steel (514E00050) | SF | 76,912 | $16.00 | $9.00 |
| 57 | Field painting of existing structural steel, prime coat (514E00056) | SF | 76,912 | $3.00 | $5.00 |
| 58 | Field painting structural steel, intermediate coat (514E00060) | SF | 76,912 | $3.00 | $3.00 |
| 59 | Field painting structural steel, finish coat (514E00066) | SF | 76,912 | $3.00 | $1.75 |
| 60 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 89 | $200.00 | $150.00 |
| 61 | Final inspection repair (514E10000) | EACH | 23 | $200.00 | $200.00 |
| 62 | Structural expansion joint including elastomeric strip seal, as per plan (516E11211) | FT | 174.50 | $900.00 | $1,100.00 |
| 63 | Elastomeric bearing with internal laminates and load plate (516E44200) | EACH | 6 | $2,000.00 | $4,500.00 |
| 64 | Elastomeric bearing with internal laminates and load plate (516E44200) | EACH | 6 | $1,600.00 | $2,500.00 |
| 65 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $2,190.00 | $90,000 |
| 66 | 6" pipe downspout, including specials, as per plan (518E43301) | FT | 318 | $218.00 | $325.00 |
| 67 | Patching concrete structure, as per plan (519E11101) | SF | 2,787 | $185.00 | $185.50 |
| 68 | Patching concrete structures with trowelable mortar (843E50000) | SF | 4 | $400.00 | $600.00 |
| 69 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $100,000 | $22,000 |
| 70 | CPM progress schedule (108E10000) | LS | 1 | $10,000 | $5,000.00 |
| 71 | Maintaining traffic (614E11000) | LS | 1 | $50,638 | $375,000 |
| 72 | Construction layout stakes and surveying (623E10000) | LS | 1 | $5,000.00 | $8,000.00 |
| 73 | Mobilization (624E10000) | LS | 1 | $350,000 | $200,000 |
| 74 | Special - consultant for concrete quality control (690E98400) | LS | 1 | $5,000.00 | $7,500.00 |