ODOT contract 250023 bid tabulation
SCI-SR 139-07.65 (CULVERT REPLACEMENT). Let by Ohio DOT on January 16, 2025, SCI. 6 bids received; low bid $230,215 by Scioto Valley Paving LLC, -11% against the engineer's estimate of $260,000.
- Owner
- Ohio DOT
- Letting
- 16 JAN 2025
- Pay items
- 48
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Scioto Valley Paving LLC | $230,215 | Low | -11% |
| 2 | Fillmore Construction | $238,868 | +4.0% | -8.0% |
| 3 | CJ Hughes Construction Company | $252,133 | +10% | -3.0% |
| 4 | Axis Civil Construction LLC | $267,632 | +16% | +3.0% |
| 5 | R C Construction Company and Son Inc | $368,368 | +60% | +42% |
| 6 | D G M Inc | $385,338 | +67% | +48% |
Engineer's estimate: $260,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Scioto Valley Paving LLC | 2. Fillmore Construction | 3. CJ Hughes Construction Company | 4. Axis Civil Construction LLC | 5. R C Construction Company and Son Inc | 6. D G M Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $8,500.00 | $2,500.00 | $1,500.00 | $3,500.00 | $2,500.00 | $11,000 |
| 2 | Headwall removed (202E20010) | EACH | 1 | $2,500.00 | $1,000.00 | $710.00 | $1,500.00 | $1,500.00 | $1,000.00 |
| 3 | Pavement removed (202E23000) | SY | 227 | $38.00 | $20.00 | $18.00 | $15.00 | $10.00 | $12.00 |
| 4 | Pipe removed, 24" and under (202E35100) | FT | 10 | $75.00 | $20.00 | $100.00 | $60.00 | $50.00 | $75.00 |
| 5 | Pipe removed, over 24" diameter (202E35200) | FT | 10 | $75.00 | $100.00 | $300.00 | $125.00 | $600.00 | $200.00 |
| 6 | Catch basin removed (202E58100) | EACH | 1 | $2,000.00 | $250.00 | $600.00 | $1,250.00 | $1,000.00 | $1,000.00 |
| 7 | Special - fill and plug existing conduit (202E70000) | FT | 140 | $90.00 | $100.00 | $100.00 | $100.00 | $150.00 | $120.00 |
| 8 | Special - fill and plug existing conduit (202E70000) | FT | 29 | $100.00 | $50.00 | $55.00 | $55.00 | $100.00 | $60.00 |
| 9 | Removal misc.: timber wall (202E98200) | FT | 8 | $250.00 | $100.00 | $63.00 | $50.00 | $250.00 | $100.00 |
| 10 | Excavation (203E10000) | CY | 57 | $50.00 | $100.00 | $50.00 | $45.00 | $25.00 | $35.00 |
| 11 | Embankment (203E20000) | CY | 23 | $100.00 | $200.00 | $50.00 | $45.00 | $25.00 | $35.00 |
| 12 | Subgrade compaction (204E10000) | SY | 189 | $7.50 | $5.00 | $20.00 | $3.00 | $2.00 | $15.00 |
| 13 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $20,000 | $5,000.00 | $9,000.00 | $5,500.00 | $12,500 | $500.00 |
| 14 | Riprap, type D (601E11000) | SY | 5 | $800.00 | $200.00 | $109.00 | $450.00 | $300.00 | $350.00 |
| 15 | Rock channel protection, type B with geotextile fabric (601E32104) | CY | 14 | $400.00 | $200.00 | $290.00 | $150.00 | $150.00 | $150.00 |
| 16 | Seeding and mulching (659E10000) | SY | 421 | $3.50 | $4.25 | $6.25 | $7.25 | $10.00 | $10.00 |
| 17 | Repair seeding and mulching (659E14000) | SY | 21 | $3.50 | $2.00 | $52.00 | $7.25 | $0.20 | $0.05 |
| 18 | Commercial fertilizer (659E20000) | TON | 0.06 | $800.00 | $1,400.00 | $9,300.00 | $620.00 | $2,000.00 | $1,500.00 |
| 19 | Lime (659E31000) | ACRE | 0.09 | $800.00 | $450.00 | $14,380 | $345.00 | $1,800.00 | $300.00 |
| 20 | Water (659E35000) | MGAL | 2 | $1.00 | $100.00 | $2.00 | $1.00 | $1.00 | $1.00 |
| 21 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 22 | Concrete masonry (602E20000) | CY | 0.90 | $2,500.00 | $3,000.00 | $6,000.00 | $3,200.00 | $2,500.00 | $2,200.00 |
| 23 | 4" conduit, type F, as per plan (611E00407) | FT | 85 | $35.00 | $50.00 | $60.00 | $28.00 | $25.00 | $20.00 |
| 24 | 10" conduit, type F (611E03700) | FT | 10 | $30.00 | $100.00 | $100.00 | $110.00 | $40.00 | $40.00 |
| 25 | 42" conduit, type B (611E19400) | FT | 139 | $350.00 | $470.00 | $225.00 | $385.00 | $650.00 | $950.00 |
| 26 | Catch basin, no. 2-4 (611E98540) | EACH | 1 | $3,500.00 | $5,450.00 | $9,200.00 | $7,000.00 | $6,500.00 | $18,000 |
| 27 | Catch basin reconstructed to grade, as per plan (611E98635) | EACH | 1 | $1,500.00 | $1,000.00 | $3,200.00 | $3,100.00 | $2,000.00 | $10,000 |
| 28 | Full depth pavement sawing (252E01500) | FT | 33 | $20.00 | $10.00 | $36.00 | $15.00 | $50.00 | $20.00 |
| 29 | Pavement repair (253E02000) | CY | 50 | $50.00 | $300.00 | $300.00 | $250.00 | $50.00 | $335.00 |
| 30 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 30 | $275.00 | $280.00 | $750.00 | $400.00 | $395.00 | $415.00 |
| 31 | Aggregate base (304E20000) | CY | 31 | $150.00 | $100.00 | $90.00 | $150.00 | $150.00 | $125.00 |
| 32 | Tack coat (407E10000) | GAL | 221 | $1.00 | $5.00 | $5.00 | $4.00 | $10.00 | $2.50 |
| 33 | Stabilized crushed aggregate (411E10000) | CY | 8 | $220.00 | $200.00 | $65.00 | $140.00 | $150.00 | $200.00 |
| 34 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 115 | $39.00 | $300.00 | $450.00 | $450.00 | $475.00 | $210.00 |
| 35 | 8" non-reinforced concrete pavement, class QC 1P, as per plan (452E12011) | SY | 54 | $200.00 | $100.00 | $160.00 | $185.00 | $175.00 | $150.00 |
| 36 | Compacted aggregate (617E10100) | CY | 50 | $25.00 | $100.00 | $65.00 | $200.00 | $150.00 | $75.00 |
| 37 | RPM (621E00100) | EACH | 1 | $2,000.00 | $842.00 | $2,050.00 | $2,500.00 | $2,500.00 | $2,000.00 |
| 38 | Raised pavement marker removed (621E54000) | EACH | 1 | $100.00 | $25.00 | $1.00 | $50.00 | $50.00 | $10.00 |
| 39 | Edge line, 6", type 1 (642E00104) | MI | 0.02 | $75,000 | $75,000 | $2,300.00 | $45,500 | $45,500 | $50,000 |
| 40 | Center line, type 1 (642E00300) | MI | 0.01 | $100,000 | $100,000 | $1,800.00 | $90,500 | $90,500 | $100,000 |
| 41 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 8 | $25.00 | $150.00 | $80.00 | $65.00 | $25.00 | $60.00 |
| 42 | Detour signing (614E12420) | LS | 1 | $6,500.00 | $5,995.00 | $8,000.00 | $4,790.00 | $28,000 | $5,000.00 |
| 43 | Water (616E10000) | MGAL | 1 | $1.00 | $100.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 44 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $7,500.00 | $4,500.00 | $2,500.00 | $3,500.00 | $16,000 | $26,000 |
| 45 | Maintaining traffic (614E11000) | LS | 1 | $6,500.00 | $4,500.00 | $4,500.00 | $3,500.00 | $20,000 | $30,000 |
| 46 | Field office, type A (619E16000) | MNTH | 2 | $100.00 | $500.00 | $3,000.00 | $1,400.00 | $250.00 | $850.00 |
| 47 | Construction layout stakes and surveying (623E10000) | LS | 1 | $7,500.00 | $2,500.00 | $2,500.00 | $5,000.00 | $12,396 | $5,000.00 |
| 48 | Mobilization (624E10000) | LS | 1 | $20,000 | $8,600.00 | $5,000.00 | $20,000 | $20,000 | $20,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 16, 2025. Compiled by Mirage Metrics.