ODOT contract 250063 bid tabulation
ROS-CR 222-04.02 (BRIDGE REPLACEMENT (1 BRIDGE)). Let by Ohio DOT on January 30, 2025, ROS. 3 bids received; low bid $6,565,973 by Beaver Excavating Company, -13% against the engineer's estimate of $7,520,000.
- Owner
- Ohio DOT
- Letting
- 30 JAN 2025
- Pay items
- 122
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Beaver Excavating Company | $6,565,973 | Low | -13% |
| 2 | Shelly & Sands Inc | $6,659,186 | +1.0% | -11% |
| 3 | Complete General Construction Company | $7,203,169 | +10% | -4.0% |
Engineer's estimate: $7,520,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Beaver Excavating Company | 2. Shelly & Sands Inc | 3. Complete General Construction Company |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $235,000 | $172,400 | $125,000 |
| 2 | Headwall removed (202E20010) | EACH | 3 | $600.00 | $800.00 | $800.00 |
| 3 | Pavement removed (202E23000) | SY | 8,920 | $8.00 | $6.00 | $15.00 |
| 4 | Pipe removed, 24" and under (202E35100) | FT | 53 | $30.00 | $25.00 | $22.00 |
| 5 | Pipe removed, over 24" diameter (202E35200) | FT | 99 | $40.00 | $23.00 | $40.00 |
| 6 | Guardrail removed (202E38000) | FT | 2,243 | $2.00 | $2.00 | $2.00 |
| 7 | Fence removed (202E75000) | FT | 2,247 | $4.00 | $2.00 | $2.00 |
| 8 | Gate removed (202E75250) | EACH | 2 | $200.00 | $200.00 | $185.00 |
| 9 | Excavation (203E10000) | CY | 51,919 | $14.80 | $12.00 | $18.00 |
| 10 | Excavation, as per plan (203E10001) | CY | 4,208 | $17.00 | $17.50 | $24.00 |
| 11 | Embankment (203E20000) | CY | 34,031 | $2.25 | $5.50 | $6.50 |
| 12 | Subgrade compaction (204E10000) | SY | 11,659 | $2.50 | $3.00 | $3.50 |
| 13 | Excavation of subgrade (204E13000) | CY | 1,571 | $23.50 | $18.00 | $25.00 |
| 14 | Granular material, type C (204E30020) | CY | 1,571 | $70.00 | $68.00 | $60.00 |
| 15 | Geotextile fabric (204E50000) | SY | 2,292 | $2.00 | $0.50 | $3.30 |
| 16 | Guardrail, type MGS (606E15050) | FT | 2,350 | $18.00 | $17.80 | $17.80 |
| 17 | Guardrail, type MGS with long posts (606E15100) | FT | 287.50 | $22.00 | $19.60 | $19.60 |
| 18 | Anchor assembly, MGS type E (MASH 2016) (606E26150) | EACH | 9 | $2,100.00 | $2,450.00 | $2,450.00 |
| 19 | Anchor assembly, MGS type T (606E26550) | EACH | 1 | $975.00 | $1,385.00 | $1,385.00 |
| 20 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 4 | $2,300.00 | $2,545.00 | $2,545.00 |
| 21 | Fence, type 47, as per plan (607E15001) | FT | 2,047 | $18.00 | $12.00 | $12.00 |
| 22 | Gate, type 47, as per plan (607E40501) | EACH | 2 | $1,250.00 | $1,480.00 | $1,480.00 |
| 23 | Monument assembly, type C (623E38500) | EACH | 15 | $1,372.97 | $2,000.00 | $1,500.00 |
| 24 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $4,500.00 | $2,500.00 | $3,500.00 |
| 25 | Post construction survey monument verification and report (623E51000) | LS | 1 | $5,000.00 | $2,500.00 | $3,500.00 |
| 26 | Inspection and compaction testing of unbound materials (878E25000) | LS | 1 | $95,000 | $58,380 | $84,750 |
| 27 | Riprap (601E10000) | SY | 8 | $450.00 | $675.00 | $350.00 |
| 28 | Crushed aggregate slope protection (601E20000) | SY | 821 | $40.00 | $53.00 | $47.00 |
| 29 | Tied concrete block mat with type 2 underlayment (601E21060) | SY | 45 | $90.00 | $75.00 | $120.00 |
| 30 | Rock channel protection, type B with geotextile fabric (601E32104) | CY | 20 | $198.00 | $300.00 | $116.00 |
| 31 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 24 | $200.00 | $250.00 | $118.00 |
| 32 | Detention basin filter (601E45030) | SY | 258 | $60.00 | $26.00 | $27.00 |
| 33 | Soil analysis test (659E00100) | EACH | 2 | $50.00 | $80.00 | $150.00 |
| 34 | Topsoil (659E00300) | CY | 5,056 | $9.00 | $19.00 | $9.75 |
| 35 | Seeding and mulching (659E10000) | SY | 45,548 | $0.64 | $0.65 | $0.70 |
| 36 | Repair seeding and mulching (659E14000) | SY | 2,278 | $2.00 | $2.00 | $0.70 |
| 37 | Inter-seeding (659E15000) | SY | 2,278 | $1.50 | $1.50 | $0.70 |
| 38 | Commercial fertilizer (659E20000) | TON | 6.36 | $750.00 | $750.00 | $1,250.00 |
| 39 | Lime (659E31000) | ACRE | 9.41 | $10.00 | $10.00 | $150.00 |
| 40 | Water (659E35000) | MGAL | 252 | $1.00 | $1.00 | $1.00 |
| 41 | Slope erosion protection (670E00500) | SY | 900 | $2.75 | $2.75 | $2.50 |
| 42 | Ditch erosion protection (670E00700) | SY | 3,999 | $1.90 | $2.00 | $2.50 |
| 43 | Storm water pollution prevention plan (832E15000) | LS | 1 | $5,500.00 | $3,900.00 | $3,000.00 |
| 44 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $8,000.00 | $18,360 | $15,050 |
| 45 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $17,000 | $15,500 | $15,700 |
| 46 | Erosion control (832E30000) | EACH | 90,000 | $1.00 | $1.00 | $1.00 |
| 47 | Seeding and erosion control with turf reinforcing mat, type 1 (836E10000) | SY | 353 | $6.25 | $6.25 | $6.25 |
| 48 | Concrete masonry (602E20000) | CY | 10 | $1,750.00 | $1,950.00 | $2,100.00 |
| 49 | Aggregate drains (605E31100) | FT | 1,620 | $14.00 | $9.00 | $10.00 |
| 50 | 15" conduit, type D (611E06400) | FT | 314 | $70.00 | $64.00 | $84.00 |
| 51 | 24" conduit, type A (611E10200) | FT | 190 | $135.00 | $250.00 | $158.00 |
| 52 | 36" conduit, type A (611E16200) | FT | 75 | $160.00 | $300.00 | $193.00 |
| 53 | 36" conduit, type B (611E16400) | FT | 88 | $160.00 | $225.00 | $186.00 |
| 54 | 36" conduit, type C (611E16600) | FT | 27 | $265.00 | $205.00 | $155.00 |
| 55 | 42" conduit, type A, 706.02, 707.01 (0.064) alumin (611E19200) | FT | 60 | $190.00 | $490.00 | $292.00 |
| 56 | Catch basin, no. 8A (611E98434) | EACH | 1 | $6,000.00 | $5,750.00 | $7,000.00 |
| 57 | Water quality basin, detention (611E99854) | EACH | 1 | $7,500.00 | $6,500.00 | $15,000 |
| 58 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 974 | $183.00 | $185.00 | $183.00 |
| 59 | Aggregate base (304E20000) | CY | 1,559 | $78.00 | $85.00 | $95.00 |
| 60 | Tack coat (407E10000) | GAL | 949 | $2.50 | $3.50 | $2.50 |
| 61 | Stabilized crushed aggregate (411E10000) | CY | 1,001 | $70.00 | $90.00 | $120.00 |
| 62 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 294 | $216.00 | $232.50 | $216.00 |
| 63 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 414 | $189.00 | $217.50 | $189.00 |
| 64 | Curb, type 4-C (609E24510) | FT | 104 | $45.00 | $55.00 | $86.00 |
| 65 | Barrier reflector, type 1, bidirectional (626E00102) | EACH | 8 | $11.00 | $12.00 | $11.00 |
| 66 | Barrier reflector, type 2, bidirectional (626E00110) | EACH | 57 | $11.00 | $14.00 | $13.00 |
| 67 | Ground mounted support, no. 3 post (630E03100) | FT | 26 | $44.80 | $24.00 | $22.50 |
| 68 | Sign post reflector (630E08600) | EACH | 1 | $159.45 | $49.00 | $45.00 |
| 69 | Sign, flat sheet (630E80100) | SF | 15 | $52.27 | $27.00 | $25.00 |
| 70 | Removal of ground mounted sign and disposal (630E84900) | EACH | 11 | $16.56 | $16.00 | $15.00 |
| 71 | Removal of ground mounted post support and disposal (630E86002) | EACH | 10 | $22.08 | $16.00 | $20.00 |
| 72 | Edge line, 4" (644E00100) | MI | 1.18 | $2,600.00 | $4,400.00 | $2,600.00 |
| 73 | Center line (644E00300) | MI | 0.59 | $4,800.00 | $8,100.00 | $4,800.00 |
| 74 | Edge line, 4" (646E10000) | MI | 0.14 | $14,200 | $18,700 | $14,200 |
| 75 | Center line (646E10200) | MI | 0.07 | $14,200 | $36,000 | $14,200 |
| 76 | Traffic compacted surface, type A or B (410E12000) | CY | 100 | $65.00 | $80.00 | $85.00 |
| 77 | Traffic compacted surface, type C (410E13000) | CY | 100 | $66.00 | $85.00 | $88.00 |
| 78 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 40 | $75.00 | $100.00 | $95.00 |
| 79 | Detour signing (614E12420) | LS | 1 | $18,000 | $6,000.00 | $7,400.00 |
| 80 | Asphalt concrete for maintaining traffic (614E13000) | CY | 10 | $400.00 | $400.00 | $325.00 |
| 81 | Water (616E10000) | MGAL | 176 | $40.00 | $65.00 | $85.00 |
| 82 | Structure removed, over 20 foot span, as per plan (202E11003) | LS | 1 | $223,000 | $255,000 | $440,000 |
| 83 | Wearing course removed (202E23500) | SY | 429 | $20.00 | $16.00 | $13.00 |
| 84 | Unclassified excavation (503E21300) | LS | 1 | $90,000 | $87,000 | $75,000 |
| 85 | Pile driving equipment mobilization (505E11100) | LS | 1 | $55,000 | $18,000 | $35,000 |
| 86 | 12" cast-in-place reinforced concrete piles, driven (507E00500) | FT | 2,680 | $24.50 | $35.00 | $12.00 |
| 87 | 12" cast-in-place reinforced concrete piles, furnished (507E00550) | FT | 2,950 | $55.00 | $40.00 | $64.00 |
| 88 | 14" cast-in-place reinforced concrete piles, driven (507E00600) | FT | 1,800 | $27.50 | $35.00 | $14.00 |
| 89 | 14" cast-in-place reinforced concrete piles, furnished (507E00650) | FT | 1,980 | $58.00 | $50.00 | $76.00 |
| 90 | Epoxy coated steel reinforcement (509E10000) | LB | 172,877 | $1.30 | $1.25 | $1.41 |
| 91 | No. 4 deformed GFRP reinforcement (509E30020) | FT | 9,458 | $1.25 | $1.50 | $1.39 |
| 92 | Semi-integral diaphragm guide (511E33500) | EACH | 2 | $6,000.00 | $3,000.00 | $3,300.00 |
| 93 | Class QC2 concrete with QC/QA, bridge deck (511E34446) | CY | 381 | $1,090.00 | $1,100.00 | $1,100.00 |
| 94 | Class QC2 concrete with QC/QA, bridge deck (parapet) (511E34450) | CY | 86 | $880.00 | $850.00 | $900.00 |
| 95 | Class QC1 concrete with QC/QA, pier above footings (511E41012) | CY | 143 | $1,150.00 | $1,400.00 | $1,200.00 |
| 96 | Class QC1 concrete with QC/QA, abutment including footing (511E43512) | CY | 235 | $580.00 | $900.00 | $800.00 |
| 97 | Class QC1 concrete with QC/QA, footing (511E46512) | CY | 128 | $400.00 | $600.00 | $425.00 |
| 98 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 1,128 | $26.00 | $28.00 | $26.00 |
| 99 | Structural steel members, level 4 (513E10280) | LB | 440,500 | $2.59 | $2.69 | $2.61 |
| 100 | Welded stud shear connectors (513E20000) | EACH | 3,495 | $4.75 | $7.00 | $7.50 |
| 101 | Armorless preformed joint seal (516E10010) | FT | 110 | $50.00 | $58.00 | $75.00 |
| 102 | 1" preformed expansion joint filler (516E13600) | SF | 11 | $8.00 | $10.00 | $14.00 |
| 103 | 2" preformed expansion joint filler (516E13900) | SF | 132 | $10.00 | $10.00 | $15.00 |
| 104 | Semi-integral abutment expansion joint seal (516E14020) | FT | 133 | $35.00 | $32.00 | $50.00 |
| 105 | Elastomeric bearing with internal laminates and load plate (516E44200) | EACH | 10 | $2,100.00 | $1,900.00 | $2,700.00 |
| 106 | Elastomeric bearing with internal laminates and load plate (516E44200) | EACH | 10 | $2,100.00 | $1,900.00 | $1,275.00 |
| 107 | Porous backfill with geotextile fabric (518E21200) | CY | 111 | $120.00 | $135.00 | $125.00 |
| 108 | 6" perforated corrugated plastic pipe (518E40000) | FT | 202 | $17.00 | $3.00 | $12.00 |
| 109 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 30 | $25.00 | $25.00 | $28.00 |
| 110 | Dynamic load testing (523E20000) | EACH | 1 | $5,500.00 | $5,500.00 | $5,500.00 |
| 111 | Dynamic load testing, as per plan (523E20001) | EACH | 1 | $5,500.00 | $5,500.00 | $5,500.00 |
| 112 | Restrike, as per plan (523E20501) | EACH | 1 | $5,800.00 | $800.00 | $3,200.00 |
| 113 | Reinforced concrete approach slabs with QC/QA (T=1 (526E30010) | SY | 220 | $410.00 | $350.00 | $400.00 |
| 114 | Type C installation (526E90030) | FT | 103 | $285.00 | $325.00 | $290.00 |
| 115 | Vandal protection fence, 6' straight, coated fabric, as per plan (607E39901) | FT | 560 | $125.00 | $100.00 | $108.00 |
| 116 | Structure grounding system (625E33000) | EACH | 1 | $17,500 | $19,000 | $15,000 |
| 117 | Premium on railroads' protective public liability and property damage liability insurance (100E00300) | LS | 1 | $15,000 | $7,500.00 | $4,000.00 |
| 118 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $65,000 | $45,000 | $39,000 |
| 119 | Maintaining traffic (614E11000) | LS | 1 | $20,000 | $7,500.00 | $30,000 |
| 120 | Field office, type C (619E16020) | MNTH | 14 | $3,200.00 | $4,000.00 | $3,800.00 |
| 121 | Construction layout stakes and surveying (623E10000) | LS | 1 | $85,000 | $75,000 | $80,000 |
| 122 | Mobilization (624E10000) | LS | 1 | $320,000 | $336,400 | $330,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 30, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.