ODOT contract 250125 bid tabulation
LOR-US 20-24.97 (BRIDGE REPLACEMENT (1 BRIDGE)). Let by Ohio DOT on February 27, 2025, LOR. 3 bids received; low bid $2,746,645 by Perk Company Inc, +12% against the engineer's estimate of $2,460,000.
- Owner
- Ohio DOT
- Letting
- 27 FEB 2025
- Pay items
- 134
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Perk Company Inc | $2,746,645 | Low | +12% |
| 2 | Schirmer Construction LLC | $4,084,776 | +49% | +66% |
| 3 | Beaver Excavating Company | $6,018,130 | +119% | +145% |
Engineer's estimate: $2,460,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Perk Company Inc | 2. Schirmer Construction LLC | 3. Beaver Excavating Company |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $5,500.00 | $3,000.00 | $150,000 |
| 2 | Headwall removed (202E20010) | EACH | 1 | $525.00 | $2,000.00 | $200.00 |
| 3 | Pavement removed (202E23000) | SY | 1,491 | $32.50 | $15.00 | $40.00 |
| 4 | Curb removed (202E32000) | FT | 59 | $16.70 | $40.00 | $4.50 |
| 5 | Pipe removed, 24" and under (202E35100) | FT | 23 | $25.00 | $75.00 | $30.00 |
| 6 | Guardrail removed (202E38000) | FT | 463 | $6.50 | $5.00 | $5.00 |
| 7 | Anchor assembly removed, type A, as per plan (202E42001) | EACH | 4 | $595.00 | $150.00 | $150.00 |
| 8 | Special - pipe cleanout, 24" and under (202E70110) | FT | 50 | $100.00 | $50.00 | $65.00 |
| 9 | Fence removed (202E75000) | FT | 121 | $10.00 | $15.00 | $4.50 |
| 10 | Removal misc.: landscape bed removed (202E98100) | EACH | 2 | $850.00 | $1,500.00 | $400.00 |
| 11 | Removal misc.:rock removed (202E98100) | EACH | 4 | $240.00 | $150.00 | $215.00 |
| 12 | Excavation (203E10000) | CY | 44 | $40.00 | $100.00 | $246.40 |
| 13 | Embankment (203E20000) | CY | 1,464 | $19.00 | $42.00 | $54.00 |
| 14 | Subgrade compaction (204E10000) | SY | 1,899 | $1.50 | $3.00 | $2.50 |
| 15 | Proof rolling (204E45000) | HR | 9 | $250.00 | $100.00 | $350.00 |
| 16 | Guardrail, type MGS (606E15050) | FT | 50 | $21.00 | $21.00 | $21.00 |
| 17 | Anchor assembly, MGS type E, MASH 2016 (606E26150) | EACH | 4 | $2,650.00 | $2,700.00 | $2,650.00 |
| 18 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 4 | $2,475.00 | $2,500.00 | $2,475.00 |
| 19 | Fence, misc.:split rail wood fence (607E98000) | FT | 121 | $55.00 | $55.00 | $53.80 |
| 20 | Monument assembly, type C (623E38500) | EACH | 2 | $1,500.00 | $1,000.00 | $1,500.00 |
| 21 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $5,000.00 | $1,000.00 | $5,000.00 |
| 22 | Post construction survey monument verification and report (623E51000) | LS | 1 | $5,000.00 | $2,000.00 | $5,000.00 |
| 23 | Special - maintain existing lighting (625E40000) | LS | 1 | $3,500.00 | $3,500.00 | $3,500.00 |
| 24 | Special - replacement of existing lighting unit (625E40010) | EACH | 2 | $500.00 | $500.00 | $500.00 |
| 25 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 8 | $200.00 | $175.00 | $350.00 |
| 26 | Soil analysis test (659E00100) | EACH | 2 | $500.00 | $10.00 | $100.00 |
| 27 | Topsoil (659E00300) | CY | 88 | $2.00 | $135.00 | $45.00 |
| 28 | Seeding and mulching (659E10000) | SY | 788 | $5.00 | $8.00 | $3.95 |
| 29 | Repair seeding and mulching (659E14000) | SY | 41 | $2.00 | $4.00 | $1.00 |
| 30 | Inter-seeding (659E15000) | SY | 41 | $1.00 | $4.00 | $0.10 |
| 31 | Commercial fertilizer (659E20000) | TON | 0.12 | $1,000.00 | $600.00 | $665.00 |
| 32 | Lime (659E31000) | ACRE | 0.20 | $1,000.00 | $250.00 | $52.50 |
| 33 | Water (659E35000) | MGAL | 2 | $100.00 | $10.00 | $1.00 |
| 34 | Erosion control (832E30000) | EACH | 25,000 | $1.00 | $1.00 | $1.00 |
| 35 | Concrete masonry (602E20000) | CY | 0.60 | $2,500.00 | $4,000.00 | $4,000.00 |
| 36 | 6" unclassified pipe underdrains (605E13300) | FT | 100 | $24.00 | $22.00 | $32.00 |
| 37 | 6" base pipe underdrains (605E14000) | FT | 768 | $24.00 | $22.00 | $32.00 |
| 38 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 49 | $24.00 | $100.00 | $17.00 |
| 39 | 6" conduit, type F (611E01500) | FT | 50 | $24.00 | $100.00 | $17.00 |
| 40 | 12" conduit, type B (611E04400) | FT | 41 | $340.00 | $190.00 | $100.00 |
| 41 | 12" conduit, type C (611E04600) | FT | 57 | $270.00 | $170.00 | $90.00 |
| 42 | 24" conduit, type C (611E10600) | FT | 12 | $660.00 | $180.00 | $335.00 |
| 43 | Catch basin, no. 2-3 (611E98510) | EACH | 1 | $7,350.00 | $4,000.00 | $3,000.00 |
| 44 | Inlet, no. 2-8, as per plan (611E98721) | EACH | 2 | $9,900.00 | $6,500.00 | $7,300.00 |
| 45 | Precast reinforced concrete outlet (611E99710) | EACH | 4 | $885.00 | $1,000.00 | $480.00 |
| 46 | Pavement planing, asphalt concrete, 3" depth (254E01000) | SY | 2,444 | $6.90 | $7.00 | $8.00 |
| 47 | Full depth pavement sawing (255E20000) | FT | 78 | $2.50 | $40.00 | $5.00 |
| 48 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 280 | $241.00 | $245.00 | $245.00 |
| 49 | Aggregate base (304E20000) | CY | 317 | $72.50 | $110.00 | $115.00 |
| 50 | Tack coat (407E10000) | GAL | 450 | $3.25 | $4.00 | $3.25 |
| 51 | Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000) | CY | 143 | $291.00 | $300.00 | $300.00 |
| 52 | Asphalt concrete intermediate course, type 2, (448) (441E50300) | CY | 199 | $289.00 | $300.00 | $300.00 |
| 53 | 4" concrete walk (608E10000) | SF | 657 | $10.50 | $19.00 | $20.00 |
| 54 | Curb, type 4-C (609E24510) | FT | 85 | $15.80 | $35.00 | $55.00 |
| 55 | Curb, type 6 (609E26000) | FT | 227 | $32.00 | $35.00 | $60.00 |
| 56 | Removal misc.:12" water main removed (202E98200) | FT | 250 | $125.00 | $60.00 | $54.54 |
| 57 | 6" water main ductile iron pipe ansi class 52, boltless-restrained joints and fittings (638E00800) | FT | 4 | $1,966.00 | $1,800.00 | $765.00 |
| 58 | 8" water main ductile iron pipe ansi class 52, boltless-restrained joints and fittings (638E01400) | FT | 8 | $1,515.00 | $2,000.00 | $700.00 |
| 59 | 12" water main ductile iron pipe ansi class 52, boltless-restrained joints and fittings (638E02600) | FT | 291 | $335.00 | $880.00 | $850.00 |
| 60 | 6" gate valve and valve box (638E07800) | EACH | 1 | $3,805.00 | $6,000.00 | $3,500.00 |
| 61 | 12" gate valve and valve box (638E08100) | EACH | 2 | $10,125 | $10,000 | $6,500.00 |
| 62 | 12" X 8" tapping sleeve, valve and valve box (638E09710) | EACH | 1 | $12,050 | $12,000 | $6,500.00 |
| 63 | 6" fire hydrant (638E10200) | EACH | 1 | $11,507 | $12,000 | $10,000 |
| 64 | Valve box adjusted to grade (638E10800) | EACH | 2 | $840.00 | $400.00 | $425.00 |
| 65 | Special - 12" water main dip and fittings: TR flex (638E11608) | FT | 60 | $1,085.00 | $425.00 | $5,000.00 |
| 66 | Special - cut and plug existing 12" water line cit (638E20884) | EACH | 2 | $1,435.00 | $4,000.00 | $2,000.00 |
| 67 | Barrier reflector, type 2, bidirectional (626E00110) | EACH | 12 | $11.00 | $12.00 | $11.00 |
| 68 | Ground mounted support, no. 2 post (630E02100) | FT | 20 | $13.00 | $14.00 | $12.80 |
| 69 | Ground mounted support, no. 3 post (630E03100) | FT | 53 | $14.00 | $15.00 | $12.85 |
| 70 | Sign, flat sheet (630E80100) | SF | 24 | $25.00 | $26.00 | $29.55 |
| 71 | Sign, flat sheet, as per plan (630E80101) | SF | 2 | $25.00 | $26.00 | $90.00 |
| 72 | Removal of ground mounted sign and disposal (630E84900) | EACH | 2 | $30.00 | $34.00 | $72.50 |
| 73 | Removal of ground mounted post support and disposal (630E86002) | EACH | 1 | $40.00 | $41.00 | $145.00 |
| 76 | Edge line, 6" (646E10010) | MI | 0.40 | $4,600.00 | $5,000.00 | $9,350.00 |
| 77 | Center line (646E10200) | MI | 0.06 | $5,800.00 | $6,000.00 | $36,100 |
| 78 | Center line (646E10200) | MI | 0.34 | $5,800.00 | $6,000.00 | $22,600 |
| 79 | Channelizing line, 8" (646E10300) | FT | 58 | $1.90 | $2.00 | $18.00 |
| 80 | Stop line (646E10400) | FT | 23 | $12.00 | $13.00 | $16.00 |
| 81 | School symbol marking, 96" (646E20110) | EACH | 1 | $750.00 | $800.00 | $695.00 |
| 82 | Lane arrow (646E20300) | EACH | 6 | $175.00 | $200.00 | $195.00 |
| 83 | Traffic compacted surface, type A (410E10000) | CY | 10 | $177.50 | $175.00 | $75.00 |
| 84 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 80 | $100.00 | $75.00 | $70.00 |
| 85 | Increased barrier delineation (614E11630) | FT | 166 | $4.00 | $4.00 | $3.95 |
| 86 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 9 | $2,850.00 | $3,500.00 | $3,000.00 |
| 87 | Work zone marking sign (614E12460) | EACH | 2 | $200.00 | $200.00 | $200.00 |
| 88 | Replacement sign (614E12500) | EACH | 5 | $100.00 | $100.00 | $100.00 |
| 89 | Replacement drum (614E12600) | EACH | 5 | $50.00 | $225.00 | $45.00 |
| 90 | Barrier reflector, type 1, bidirectional (614E13310) | EACH | 39 | $8.00 | $10.00 | $8.00 |
| 91 | Barrier reflector, type 3, bidirectional (614E13314) | EACH | 6 | $10.00 | $12.00 | $10.00 |
| 92 | Object marker, two way (614E13360) | EACH | 45 | $18.00 | $20.00 | $25.00 |
| 93 | Work zone center line, class I (614E21000) | MI | 0.67 | $2,500.00 | $2,700.00 | $2,500.00 |
| 94 | Work zone center line, class I (614E21000) | MI | 0.07 | $2,500.00 | $2,700.00 | $2,500.00 |
| 95 | Work zone center line, class I, 642 paint (614E21100) | MI | 0.06 | $2,500.00 | $2,700.00 | $2,500.00 |
| 96 | Work zone center line, class I, 740.06, type I (614E21200) | MI | 0.01 | $15,000 | $16,000 | $15,000 |
| 97 | Work zone edge line, class I, 6" (614E22010) | MI | 2.22 | $1,400.00 | $1,500.00 | $1,400.00 |
| 98 | Work zone edge line, class I, 4", 642 paint (614E22100) | MI | 0.20 | $1,400.00 | $1,500.00 | $1,400.00 |
| 99 | Work zone edge line, class I, 4", 740.06, type I (614E22200) | MI | 0.02 | $8,500.00 | $9,000.00 | $8,500.00 |
| 100 | Work zone channelizing line, class I, 8" (614E23000) | FT | 100 | $1.00 | $1.00 | $0.95 |
| 101 | Pavement for maintaining traffic, class A (615E20000) | SY | 375 | $160.00 | $250.00 | $225.00 |
| 102 | Water (616E10000) | MGAL | 1 | $200.00 | $10.00 | $400.00 |
| 103 | Portable barrier, unanchored (622E41100) | FT | 1,120 | $26.00 | $100.00 | $30.00 |
| 104 | Portable barrier, anchored (622E41110) | FT | 240 | $36.00 | $115.00 | $30.00 |
| 105 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $68,985 | $512,000 | $775,000 |
| 106 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $55,500 | $345,000 | $175,000 |
| 107 | Unclassified excavation (503E21100) | CY | 1,760 | $37.15 | $85.00 | $150.00 |
| 108 | Steel piles HP10X42, furnished, as per plan (507E00101) | FT | 600 | $56.00 | $27.00 | $55.00 |
| 109 | Steel piles HP12X53, furnished, as per plan (507E00201) | FT | 640 | $61.00 | $33.00 | $60.00 |
| 110 | Special - pile encasement (507E71200) | FT | 195 | $600.00 | $140.00 | $225.00 |
| 111 | Prebored holes, as per plan (507E92201) | FT | 620 | $230.00 | $50.00 | $225.00 |
| 112 | Epoxy coated steel reinforcement (509E10000) | LB | 81,499 | $1.75 | $2.50 | $2.10 |
| 113 | Dowel holes with nonshrink, nonmetallic grout (510E10000) | EACH | 230 | $30.00 | $35.00 | $30.00 |
| 114 | Class QC2 concrete with QC/QA, superstructure (511E33312) | CY | 272 | $1,495.00 | $2,600.00 | $3,000.00 |
| 115 | Class QC1 concrete, abutment including footing (511E43510) | CY | 75 | $1,270.00 | $2,200.00 | $1,200.00 |
| 116 | Class QC2 concrete with QC/QA, sidewalk (511E51512) | CY | 47 | $640.00 | $1,100.00 | $600.00 |
| 117 | Sealing of concrete surfaces (non-epoxy) (512E10050) | SY | 177 | $25.00 | $25.00 | $21.00 |
| 118 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 328 | $45.00 | $45.00 | $45.00 |
| 119 | Type 2 waterproofing (512E33000) | SY | 16 | $50.00 | $150.00 | $48.00 |
| 120 | 1/2" preformed expansion joint filler (516E13200) | SF | 84 | $12.00 | $5.00 | $6.00 |
| 121 | 1" preformed expansion joint filler (516E13600) | SF | 112 | $10.00 | $6.00 | $7.00 |
| 122 | Integral abutment expansion joint seal (516E14014) | FT | 133 | $37.00 | $45.00 | $45.00 |
| 123 | Railing (concrete parapet with twin steel tube railing), as per plan (517E75121) | FT | 226 | $340.00 | $415.00 | $450.00 |
| 124 | Porous backfill with geotextile fabric (518E21200) | CY | 68 | $132.50 | $125.00 | $125.00 |
| 125 | 6" perforated corrugated plastic pipe (518E40000) | FT | 133 | $24.00 | $40.00 | $20.00 |
| 126 | 6" non-perforated corrugated plastic pipe (518E40012) | FT | 60 | $24.00 | $45.50 | $20.00 |
| 127 | Reinforced concrete approach slabs (T=12"), as per plan (526E10001) | SY | 176 | $480.00 | $565.00 | $500.00 |
| 128 | Special - structures (existing structure repair) (530E00200) | LS | 1 | $8,625.00 | $5,000.00 | $30,000 |
| 129 | Rock channel protection, type C with filter (601E32200) | CY | 361 | $140.00 | $145.00 | $260.00 |
| 130 | Structure grounding system (625E33000) | EACH | 1 | $8,500.00 | $9,000.00 | $15,000 |
| 131 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $27,000 | $85,000 | $80,000 |
| 132 | Maintaining traffic (614E11000) | LS | 1 | $97,250 | $92,000 | $340,000 |
| 133 | Field office, type B (619E16010) | MNTH | 8 | $2,075.00 | $1,300.00 | $3,400.00 |
| 134 | Construction layout stakes and surveying (623E10000) | LS | 1 | $31,830 | $60,000 | $100,000 |
| 135 | Mobilization (624E10000) | LS | 1 | $180,000 | $100,000 | $1,000,000 |
| 200 | CPM progress schedule short duration projects (108E30000) | LS | 1 | $5,000.00 | $3,000.00 | $5,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of February 27, 2025. Compiled by Mirage Metrics.