ODOT contract 250171 bid tabulation
D02-TSG FY2025 (SIGNALIZATION). Let by Ohio DOT on March 27, 2025, District 2. 5 bids received; low bid $404,014 by Perram Electric Inc, -20% against the engineer's estimate of $502,000.
- Owner
- Ohio DOT
- Letting
- 27 MAR 2025
- Pay items
- 47
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Perram Electric Inc | $404,014 | Low | -20% |
| 2 | Miller Cable Company | $445,500 | +10% | -11% |
| 3 | Complete General Construction Company | $469,247 | +16% | -7.0% |
| 4 | U S Utility Contractor Company | $474,667 | +17% | -5.0% |
| 5 | Asplundh Construction LLC | $487,453 | +21% | -3.0% |
Engineer's estimate: $502,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Perram Electric Inc | 2. Miller Cable Company | 3. Complete General Construction Company | 4. U S Utility Contractor Company | 5. Asplundh Construction LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Topsoil (659E00300) | CY | 3 | $237.00 | $14.00 | $200.00 | $37.00 | $627.20 |
| 2 | Seeding and mulching (659E10000) | SY | 25 | $3.00 | $65.00 | $75.00 | $79.75 | $73.47 |
| 3 | Repair seeding and mulching (659E14000) | SY | 2 | $3.00 | $11.00 | $75.00 | $116.75 | $515.20 |
| 4 | Inter-seeding (659E15000) | SY | 2 | $3.00 | $0.25 | $75.00 | $122.50 | $515.20 |
| 5 | Commercial fertilizer (659E20000) | TON | 0.10 | $500.00 | $440.00 | $2,000.00 | $1,154.40 | $1,836.80 |
| 6 | Water (659E35000) | MGAL | 1 | $10.00 | $1.00 | $5.00 | $15.45 | $162.40 |
| 7 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 8 | Conduit, 3", 725.051 (625E25504) | FT | 61 | $16.70 | $16.00 | $12.00 | $14.53 | $31.87 |
| 9 | Conduit, 4", 725.051 (625E25604) | FT | 38 | $22.50 | $20.00 | $16.00 | $13.53 | $35.18 |
| 10 | Conduit, jacked or drilled, 725.051, 4" (625E25906) | FT | 264 | $47.15 | $44.00 | $65.00 | $41.03 | $95.90 |
| 11 | Trench (625E29000) | FT | 90 | $14.25 | $68.00 | $22.00 | $11.21 | $14.57 |
| 12 | Pull box, 725.08, 24" (625E30706) | EACH | 4 | $1,995.00 | $1,250.00 | $1,600.00 | $1,218.75 | $2,221.52 |
| 13 | Pull box removed (625E31510) | EACH | 12 | $99.00 | $220.00 | $250.00 | $586.25 | $382.85 |
| 14 | Ground rod (625E32000) | EACH | 4 | $315.00 | $315.00 | $400.00 | $263.00 | $337.48 |
| 15 | Underground warning marking tape (625E36010) | FT | 90 | $1.25 | $4.00 | $2.50 | $2.07 | $1.43 |
| 16 | Arc flash calculations and label, signal power ser (625E76000) | EACH | 2 | $1,500.00 | $4,400.00 | $4,025.00 | $3,125.00 | $273.28 |
| 17 | Sign, flat sheet (630E80100) | SF | 8 | $28.30 | $55.00 | $185.00 | $134.00 | $26.88 |
| 18 | Sign erected, flat sheet (630E81100) | SF | 8 | $28.30 | $25.00 | $165.00 | $79.75 | $26.88 |
| 19 | Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate (632E05006) | EACH | 10 | $898.00 | $1,100.00 | $1,000.00 | $1,175.05 | $822.64 |
| 20 | Vehicular signal head, (LED), 4-section, 12" lens, 1-way, polycarbonate (632E05064) | EACH | 2 | $1,100.00 | $1,280.00 | $1,400.00 | $1,346.40 | $963.76 |
| 21 | Vehicular signal head, (LED), 5-section, 12" lens, 1-way, polycarbonate (632E05086) | EACH | 6 | $1,665.00 | $1,750.00 | $2,200.00 | $2,032.60 | $1,572.29 |
| 22 | Covering of vehicular signal head (632E25000) | EACH | 18 | $20.00 | $90.00 | $40.00 | $36.00 | $48.16 |
| 23 | Signal cable, 5 conductor, no. 14 AWG (632E40500) | FT | 2,435 | $2.90 | $2.20 | $3.25 | $4.76 | $2.76 |
| 24 | Signal cable, 7 conductor, no. 14 AWG (632E40700) | FT | 1,210 | $3.35 | $2.35 | $3.80 | $5.22 | $3.26 |
| 26 | Power cable, 3 conductor, no. 6 AWG (632E68300) | FT | 400 | $6.05 | $6.00 | $5.25 | $9.81 | $4.76 |
| 27 | Service cable, 3 conductor, no. 4 AWG (632E69900) | FT | 600 | $7.55 | $10.00 | $9.00 | $10.13 | $6.09 |
| 28 | Power service (632E70000) | EACH | 2 | $2,290.00 | $2,000.00 | $2,000.00 | $3,716.25 | $6,194.50 |
| 29 | Signal support, type TC-12.31 design 10 pole, with mast arms TC-81.22 design 13 and design 12 (632E71368) | EACH | 2 | $28,180 | $34,000 | $36,000 | $36,000 | $32,323 |
| 30 | Combination signal support, type TC-12.31 design 1 (632E78368) | EACH | 1 | $29,825 | $35,000 | $37,000 | $36,250 | $34,076 |
| 31 | Signal support, type TC-81.22, design 13 (632E72140) | EACH | 1 | $16,720 | $19,000 | $20,500 | $22,180 | $19,904 |
| 32 | Removal of traffic signal installation, as per plan (632E90101) | EACH | 2 | $4,825.00 | $3,300.00 | $7,000.00 | $8,362.50 | $3,113.60 |
| 33 | Cabinet, type TS-2, as per plan (633E65511) | EACH | 2 | $17,415 | $17,500 | $19,500 | $20,945 | $19,760 |
| 34 | Cabinet foundation, as per plan (633E67101) | EACH | 2 | $3,865.00 | $3,300.00 | $4,500.00 | $1,488.75 | $4,034.24 |
| 35 | Controller work pad, as per plan (633E67201) | EACH | 2 | $990.00 | $400.00 | $1,365.00 | $1,066.25 | $2,469.60 |
| 36 | Uninterruptible power supply (UPS), 1000 watt, as per plan (633E75001) | EACH | 2 | $6,350.00 | $5,800.00 | $6,000.00 | $7,690.45 | $6,573.84 |
| 37 | Advance radar detection, as per plan (809E69001) | EACH | 4 | $9,265.00 | $9,000.00 | $8,500.00 | $10,240 | $9,254.00 |
| 38 | Stop line radar detection, as per plan (809E69101) | EACH | 5 | $8,500.00 | $8,800.00 | $8,000.00 | $10,470 | $8,907.36 |
| 39 | Atc controller, as per plan (809E69123) | EACH | 2 | $545.00 | $500.00 | $500.00 | $544.75 | $1,167.60 |
| 40 | Law enforcement officer with patrol car for assistance, as per plan (614E11111) | HR | 24 | $75.00 | $85.00 | $100.00 | $103.50 | $89.60 |
| 41 | Portable changeable message sign, as per plan (614E18601) | SNMT | 4 | $1,245.00 | $1,050.00 | $2,600.00 | $2,070.00 | $3,920.00 |
| 42 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $6,846.90 | $4,348.00 | $2,400.00 | $6,700.00 | $6,496.00 |
| 43 | Maintaining traffic (614E11000) | LS | 1 | $6,575.00 | $17,500 | $5,000.00 | $15,763 | $7,571.20 |
| 44 | Construction layout stakes and surveying (623E10000) | LS | 1 | $1,000.00 | $3,900.00 | $1,500.00 | $5,137.50 | $4,009.50 |
| 45 | Mobilization (624E10000) | LS | 1 | $10,000 | $10,000 | $20,000 | $11,725 | $23,386 |
| 100 | Drilled shafts, 36" diameter, above bedrock, as per plan (524E94703) | FT | 15 | $585.00 | $725.00 | $650.00 | $270.00 | $787.79 |
| 101 | Drilled shafts, 42" diameter, above bedrock, as per plan (524E94803) | FT | 38 | $869.00 | $825.00 | $850.00 | $300.00 | $645.83 |
| 102 | Drilled shafts, 42" diameter, into bedrock, as per plan (524E94805) | FT | 5 | $988.00 | $2,100.00 | $1,400.00 | $900.00 | $3,069.77 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of March 27, 2025. Compiled by Mirage Metrics.