ODOT contract 250190 bid tabulation
CUY-Villaview Road (MINOR RECONSTRUCTION). Let by Ohio DOT on April 10, 2025, CUY. 3 bids received; low bid $2,898,675 by Ronyak Paving Inc, -24% against the engineer's estimate of $3,815,000.
- Owner
- Ohio DOT
- Letting
- 10 APR 2025
- Pay items
- 110
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ronyak Paving Inc | $2,898,675 | Low | -24% |
| 2 | Perk Company Inc | $3,194,153 | +10% | -16% |
| 3 | C A Agresta Construction Co | $3,947,764 | +36% | +3.0% |
Engineer's estimate: $3,815,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ronyak Paving Inc | 2. Perk Company Inc | 3. C A Agresta Construction Co |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $2,500.00 | $5,000.00 | $10,000 |
| 2 | Pavement removed (202E23000) | SY | 36 | $20.00 | $100.00 | $25.00 |
| 3 | Pavement removed, as per plan (202E23001) | SY | 836 | $30.00 | $30.00 | $25.00 |
| 4 | Wearing course removed, as per plan (202E23501) | SY | 25,182 | $4.00 | $4.50 | $6.00 |
| 5 | Walk removed, as per plan (202E30001) | SF | 9,592 | $3.25 | $2.50 | $3.00 |
| 6 | Curb removed, as per plan (202E32001) | FT | 1,909 | $10.00 | $1.00 | $10.00 |
| 7 | Subgrade compaction (204E10000) | SY | 1,049 | $1.00 | $2.50 | $2.00 |
| 8 | Excavation of subgrade (204E13000) | CY | 938 | $15.00 | $5.00 | $25.00 |
| 9 | Granular material, type B (204E30010) | CY | 938 | $20.00 | $15.00 | $60.00 |
| 10 | Geotextile fabric (204E50000) | SY | 1,875 | $1.00 | $1.00 | $1.00 |
| 11 | Geogrid (204E51000) | SY | 1,875 | $1.00 | $1.00 | $2.00 |
| 12 | Linear grading (209E60200) | STA | 63 | $15.00 | $1.00 | $160.00 |
| 13 | Preparing subgrade for shoulder paving (209E72000) | STA | 63 | $15.00 | $400.00 | $160.00 |
| 14 | 6" concrete walk, as per plan (608E13001) | SF | 5,993 | $5.00 | $13.00 | $15.00 |
| 15 | Curb ramp, as per plan (608E52001) | SF | 3,985 | $21.00 | $35.00 | $25.00 |
| 16 | Monument assembly, as per plan (623E38501) | EACH | 14 | $1,100.00 | $500.00 | $1,400.00 |
| 17 | Monument assembly adjusted to grade, as per plan (623E39501) | EACH | 12 | $950.00 | $1,500.00 | $1,200.00 |
| 18 | Special - vertical clearance (690E98000) | EACH | 2 | $1,500.00 | $500.00 | $3,000.00 |
| 19 | Special - pre-construction video (690E98400) | LS | 1 | $2,500.00 | $1,500.00 | $3,000.00 |
| 20 | Topsoil furnished and placed (653E10000) | CY | 31 | $200.00 | $210.00 | $70.00 |
| 21 | Seeding and mulching, class 1 (659E00500) | SY | 2,240 | $4.00 | $15.00 | $4.00 |
| 22 | Commercial fertilizer (659E20000) | TON | 0.30 | $850.00 | $850.00 | $600.00 |
| 23 | Lime (659E31000) | ACRE | 0.39 | $250.00 | $750.00 | $100.00 |
| 24 | Water (659E35000) | MGAL | 6.05 | $10.00 | $100.00 | $20.00 |
| 25 | Erosion control (832E30000) | EACH | 30,000 | $1.00 | $1.00 | $1.00 |
| 26 | 4" unclassified pipe underdrains, as per plan (605E05201) | FT | 324 | $8.00 | $4.00 | $20.00 |
| 27 | 6" unclassified pipe underdrains, as per plan (605E13301) | FT | 1,767 | $9.00 | $4.00 | $20.00 |
| 28 | 4" conduit, type F for underdrain outlet, as per plan (611E00411) | FT | 37 | $8.00 | $4.00 | $20.00 |
| 29 | 6" conduit, type F for underdrain outlets, as per plan (611E00511) | FT | 37 | $9.00 | $4.00 | $20.00 |
| 30 | Catch basin adjusted to grade, as per plan (611E98631) | EACH | 12 | $1,100.00 | $1,500.00 | $1,700.00 |
| 31 | Catch basin reconstructed to grade, as per plan (611E98635) | EACH | 13 | $2,000.00 | $1,600.00 | $1,900.00 |
| 32 | Manhole adjusted to grade, as per plan (611E99655) | EACH | 1 | $975.00 | $2,500.00 | $1,600.00 |
| 33 | Manhole reconstructed to grade, as per plan (611E99661) | EACH | 1 | $1,500.00 | $2,600.00 | $2,000.00 |
| 34 | Special - miscellaneous metal (611E99820) | LB | 19,250 | $2.00 | $2.00 | $2.50 |
| 35 | Low strength mortar backfill (type 1) (613E41250) | CY | 165 | $75.00 | $40.00 | $100.00 |
| 36 | Partial depth pavement repair (441), as per plan (251E01001) | SY | 1,268 | $80.00 | $15.00 | $50.00 |
| 37 | Pavement planing, asphalt concrete (T=3") (254E01000) | SY | 224 | $10.00 | $10.00 | $12.00 |
| 38 | Full depth pavement removal and rigid replacement, type 1, class QC1, as per plan (255E11001) | SY | 7,000 | $140.00 | $178.00 | $195.00 |
| 39 | Full depth pavement removal and rigid replacement, type 2, class QC1, as per plan (255E12001) | SY | 465 | $200.00 | $178.00 | $210.00 |
| 40 | Aggregate base, as per plan (304E20001) | CY | 175 | $36.00 | $100.00 | $85.00 |
| 41 | Tack coat, 702.13 (407E13900) | GAL | 1,920 | $5.00 | $3.00 | $3.00 |
| 42 | Non-tracking tack coat (407E20000) | GAL | 1,446 | $3.00 | $3.00 | $3.00 |
| 43 | Prime coat (408E10000) | GAL | 574 | $5.00 | $5.00 | $6.00 |
| 44 | Asphalt concrete surface course, type 1, (448), as per plan (441E50101) | CY | 9 | $425.00 | $450.00 | $500.00 |
| 45 | Asphalt concrete surface course, type 1, (448), as per plan (441E50101) | CY | 936 | $235.00 | $240.00 | $250.00 |
| 46 | Asphalt concrete intermediate course, type 2, (449), as per plan (441E70301) | CY | 1,261 | $195.00 | $205.00 | $215.00 |
| 47 | 9" reinforced concrete pavement, class QC 1P (451E14010) | SY | 801 | $120.00 | $155.00 | $175.00 |
| 48 | 6" non-reinforced concrete pavement, class QC MS, as per plan (452E10051) | SY | 85 | $100.00 | $144.00 | $140.00 |
| 49 | 8" non-reinforced concrete pavement, class QC MS, as per plan (452E12051) | SY | 12 | $150.00 | $200.00 | $200.00 |
| 50 | Curb, type 2-A, as per plan (609E14001) | FT | 1,221 | $18.00 | $5.00 | $45.00 |
| 51 | Curb, type 2-B, as per plan (609E16001) | FT | 461 | $20.00 | $10.00 | $45.00 |
| 52 | Curb, type 6, as per plan (609E26001) | FT | 365 | $30.00 | $65.00 | $60.00 |
| 53 | Compacted aggregate (617E10100) | CY | 125 | $120.00 | $135.00 | $145.00 |
| 54 | Longitudinal joint adhesive (875E10000) | LB | 1,488 | $5.00 | $1.50 | $1.50 |
| 55 | Valve box adjusted to grade, as per plan (638E10801) | EACH | 9 | $800.00 | $1,350.00 | $1,000.00 |
| 56 | Manhole adjusted to grade, as per plan (611E99655) | EACH | 7 | $1,000.00 | $1,500.00 | $2,000.00 |
| 57 | Manhole reconstructed to grade, as per plan (611E99661) | EACH | 3 | $1,450.00 | $1,550.00 | $2,100.00 |
| 58 | Ground mounted support, no. 3 post (630E03100) | FT | 55.20 | $12.50 | $14.00 | $15.00 |
| 59 | Sign post reflector (630E08600) | EACH | 3 | $35.00 | $65.00 | $35.00 |
| 60 | Sign hanger assembly, span wire (630E79000) | EACH | 3 | $225.00 | $385.00 | $225.00 |
| 61 | Sign support assembly, pole mounted (630E79500) | EACH | 4 | $65.00 | $75.00 | $65.00 |
| 62 | Sign, flat sheet (630E80100) | SF | 60 | $20.00 | $16.00 | $20.00 |
| 63 | Removal of ground mounted sign and reerection (630E85100) | EACH | 5 | $30.00 | $85.00 | $30.00 |
| 64 | Removal of ground mounted post support and disposal (630E86002) | EACH | 4 | $30.00 | $40.00 | $30.00 |
| 65 | Removal of overhead mounted sign and disposal (630E87400) | EACH | 3 | $65.00 | $75.00 | $65.00 |
| 66 | Removal of pole mounted sign and disposal (630E87500) | EACH | 1 | $30.00 | $25.00 | $30.00 |
| 67 | Detector loop, as per plan (632E26501) | EACH | 2 | $1,400.00 | $1,550.00 | $3,000.00 |
| 68 | Edge line, 4" (644E00100) | MI | 1.18 | $4,200.00 | $4,200.00 | $5,200.00 |
| 69 | Lane line, 4" (644E00200) | MI | 0.27 | $2,000.00 | $2,800.00 | $3,000.00 |
| 70 | Center line (644E00300) | MI | 1.01 | $5,000.00 | $5,800.00 | $6,000.00 |
| 71 | Channelizing line, 8" (644E00400) | FT | 789 | $1.45 | $1.50 | $2.00 |
| 72 | Stop line (644E00500) | FT | 144 | $6.50 | $8.00 | $7.00 |
| 73 | Crosswalk line, 12" (644E00620) | FT | 455 | $3.75 | $4.00 | $4.00 |
| 74 | Crosswalk line, 12", as per plan (644E00621) | FT | 53 | $3.75 | $4.00 | $4.00 |
| 75 | Crosswalk line, 24", as per plan (644E00631) | FT | 35 | $6.50 | $8.00 | $7.00 |
| 76 | Chevron marking (644E00720) | FT | 124 | $6.50 | $10.00 | $7.00 |
| 77 | Lane arrow (644E01300) | EACH | 16 | $150.00 | $105.00 | $170.00 |
| 78 | Pavement marking, misc.:channel line, dotted (644E50300) | FT | 772 | $1.75 | $3.50 | $2.00 |
| 79 | Lane line, 4" (646E10100) | MI | 0.06 | $7,000.00 | $4,500.00 | $7,000.00 |
| 80 | Center line (646E10200) | MI | 0.26 | $8,000.00 | $7,500.00 | $8,000.00 |
| 81 | Channelizing line, 8" (646E10300) | FT | 567 | $1.85 | $2.05 | $2.00 |
| 82 | Stop line (646E10400) | FT | 73 | $12.50 | $12.00 | $14.00 |
| 83 | Crosswalk line, 12" (646E10510) | FT | 512 | $6.95 | $6.00 | $7.00 |
| 84 | Island marking (646E10800) | SF | 48 | $8.00 | $4.00 | $8.00 |
| 85 | Lane arrow (646E20300) | EACH | 22 | $200.00 | $175.00 | $200.00 |
| 86 | Removal of pavement marking (646E50000) | EACH | 17 | $50.00 | $200.00 | $50.00 |
| 87 | Removal of pavement marking (646E50100) | FT | 891 | $1.50 | $4.00 | $2.00 |
| 88 | Removal of pavement marking (646E50300) | MI | 0.47 | $2,500.00 | $3,500.00 | $2,500.00 |
| 89 | Pavement marking, misc.:channel line, dotted (646E90000) | FT | 388 | $1.85 | $5.00 | $2.00 |
| 90 | Traffic compacted surface, type A or B (410E12000) | CY | 75 | $10.00 | $25.00 | $100.00 |
| 91 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 80 | $125.00 | $110.00 | $100.00 |
| 92 | Asphalt concrete for maintaining traffic (614E13000) | CY | 150 | $110.00 | $50.00 | $100.00 |
| 93 | Portable changeable message sign, as per plan (614E18601) | SNMT | 10 | $825.00 | $900.00 | $825.00 |
| 94 | Work zone lane line, class III, 4", 642 paint (614E20550) | MI | 0.42 | $1,500.00 | $1,200.00 | $1,500.00 |
| 95 | Work zone center line, class I, 642 paint (614E21100) | MI | 1.94 | $1,500.00 | $2,500.00 | $1,500.00 |
| 96 | Work zone center line, class III, 642 paint (614E21550) | MI | 0.99 | $1,500.00 | $2,500.00 | $1,500.00 |
| 97 | Work zone edge line, class I, 4", 642 paint (614E22100) | MI | 4.78 | $800.00 | $950.00 | $800.00 |
| 98 | Work zone edge line, class III, 4", 642 paint (614E22350) | MI | 1.21 | $800.00 | $950.00 | $800.00 |
| 99 | Work zone channelizing line, class III, 8", 642 paint (614E23680) | FT | 762 | $0.50 | $0.95 | $1.00 |
| 100 | Work zone stop line, class I (614E26000) | FT | 305 | $3.50 | $4.50 | $4.00 |
| 101 | Work zone stop line, class III, 642 paint (614E26610) | FT | 113 | $3.50 | $4.50 | $4.00 |
| 102 | Work zone arrow, class III, 642 paint (614E30650) | EACH | 13 | $55.00 | $75.00 | $55.00 |
| 103 | Business entrance sign, as per plan (614E40051) | EACH | 4 | $225.00 | $450.00 | $225.00 |
| 104 | Water (616E10000) | MGAL | 50 | $5.00 | $1.00 | $20.00 |
| 105 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $19,351 | $30,725 | $40,799 |
| 106 | CPM progress schedule short duration projects (108E30000) | LS | 1 | $2,500.00 | $5,500.00 | $6,000.00 |
| 107 | Maintaining traffic, as per plan (614E11001) | LS | 1 | $195,000 | $58,300 | $366,000 |
| 108 | Field office, type B, as per plan (619E16011) | MNTH | 6 | $1,850.00 | $3,000.00 | $3,200.00 |
| 109 | Construction layout stakes and surveying (623E10000) | LS | 1 | $35,440 | $10,000 | $20,000 |
| 110 | Mobilization (624E10000) | LS | 1 | $162,800 | $250,000 | $254,500 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 10, 2025. Compiled by Mirage Metrics.