ODOT contract 250240 bid tabulation
BEL-CR 4-27.05 (BRIDGE REPLACEMENT (1 BRIDGE)). Let by Ohio DOT on May 8, 2025, BEL. 3 bids received; low bid $1,415,154 by Shelly & Sands Inc, -20% against the engineer's estimate of $1,760,000.
- Owner
- Ohio DOT
- Letting
- 08 MAY 2025
- Pay items
- 80
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly & Sands Inc | $1,415,154 | Low | -20% |
| 2 | Ohio-West Virginia Excavating Co | $1,428,208 | +1.0% | -19% |
| 3 | S E T Inc | $1,659,454 | +17% | -6.0% |
Engineer's estimate: $1,760,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly & Sands Inc | 2. Ohio-West Virginia Excavating Co | 3. S E T Inc |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $4,349.90 | $10,000 | $30,000 |
| 2 | Pavement removed (202E23000) | SY | 969 | $7.00 | $17.00 | $11.00 |
| 3 | Guardrail removed (202E38000) | FT | 49 | $5.00 | $25.00 | $11.00 |
| 4 | Mailbox removed (202E53100) | EACH | 2 | $123.00 | $90.00 | $38.00 |
| 5 | Excavation (203E10000) | CY | 634 | $26.00 | $23.00 | $38.00 |
| 6 | Embankment (203E20000) | CY | 535 | $22.00 | $60.00 | $38.00 |
| 7 | Subgrade compaction (204E10000) | SY | 1,119 | $6.00 | $6.50 | $1.60 |
| 8 | Guardrail, type MGS (606E15050) | FT | 37.50 | $23.00 | $95.00 | $91.00 |
| 9 | Anchor assembly, MGS type E (MASH 2016) (606E26150) | EACH | 1 | $2,700.00 | $2,500.00 | $2,500.00 |
| 10 | Anchor assembly, MGS type T (606E26550) | EACH | 2 | $1,250.00 | $1,200.00 | $1,150.00 |
| 11 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 3 | $2,500.00 | $2,300.00 | $2,205.00 |
| 12 | MGS bridge terminal assembly, type 1, as per plan (606E35003) | EACH | 1 | $2,800.00 | $2,500.00 | $2,500.00 |
| 13 | Monument assembly, type C (623E38500) | EACH | 5 | $1,460.00 | $350.00 | $1,000.00 |
| 14 | Special - mailbox support (690E50000) | EACH | 2 | $160.00 | $125.00 | $135.00 |
| 15 | Special - misc.: work involving asbestos containin (690E98400) | LS | 1 | $225.00 | $1,200.00 | $250.00 |
| 16 | Rock channel protection, type A with geotextile fabric (601E32004) | CY | 451 | $118.00 | $85.00 | $96.00 |
| 17 | Soil analysis test (659E00100) | EACH | 2 | $125.00 | $100.00 | $160.00 |
| 18 | Topsoil (659E00300) | CY | 198 | $45.00 | $53.00 | $76.00 |
| 19 | Seeding and mulching (659E10000) | SY | 1,783 | $3.00 | $4.00 | $2.60 |
| 20 | Repair seeding and mulching (659E14000) | SY | 90 | $1.00 | $4.00 | $2.00 |
| 21 | Commercial fertilizer (659E20000) | TON | 0.24 | $901.00 | $350.00 | $1,300.00 |
| 22 | Lime (659E31000) | ACRE | 0.37 | $156.00 | $350.00 | $160.00 |
| 23 | Water (659E35000) | MGAL | 10 | $1.00 | $10.00 | $10.00 |
| 24 | Ditch erosion protection (670E00700) | SY | 107 | $1.50 | $6.00 | $2.65 |
| 25 | Erosion control (832E30000) | EACH | 2,000 | $1.00 | $1.00 | $1.00 |
| 26 | Concrete masonry (602E20000) | CY | 1 | $1,000.00 | $1,400.00 | $1,500.00 |
| 27 | Aggregate drains (605E31100) | FT | 74 | $25.00 | $25.00 | $28.00 |
| 28 | 12" conduit, type B (611E04400) | FT | 62 | $145.00 | $125.00 | $120.00 |
| 29 | 12" conduit, type D (611E04900) | FT | 75 | $65.00 | $125.00 | $45.00 |
| 30 | Catch basin, no. 2-2B (611E98470) | EACH | 1 | $4,500.00 | $3,500.00 | $1,600.00 |
| 31 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 141 | $250.00 | $275.00 | $265.00 |
| 32 | Aggregate base (304E20000) | CY | 320 | $100.00 | $110.00 | $100.00 |
| 33 | Non-tracking tack coat (407E20000) | GAL | 90 | $3.50 | $9.00 | $3.75 |
| 34 | Prime coat (408E10000) | GAL | 107 | $9.00 | $10.00 | $10.00 |
| 35 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 69 | $360.00 | $275.00 | $380.00 |
| 36 | 6" non-reinforced concrete pavement, class QC 1P (452E10010) | SY | 104 | $120.00 | $125.00 | $126.00 |
| 37 | Water work, misc.: 2" water main (638E98600) | FT | 80 | $70.00 | $100.00 | $99.00 |
| 38 | Barrier reflector, type 2, bidirectional (626E00110) | EACH | 10 | $12.00 | $12.00 | $13.00 |
| 39 | Ground mounted support, no. 3 post (630E03100) | FT | 28 | $22.00 | $40.00 | $38.00 |
| 40 | Removal of ground mounted sign and disposal (630E84900) | EACH | 6 | $25.00 | $105.00 | $25.00 |
| 41 | Removal of ground mounted sign and reerection (630E85100) | EACH | 1 | $100.00 | $550.00 | $100.00 |
| 42 | Removal of ground mounted post support and disposal (630E86002) | EACH | 10 | $25.00 | $65.00 | $25.00 |
| 43 | Edge line, 4", type 1 (642E00100) | MI | 0.18 | $950.00 | $4,500.00 | $4,450.00 |
| 44 | Center line, type 1 (642E00300) | MI | 0.09 | $1,500.00 | $9,000.00 | $9,000.00 |
| 45 | Traffic compacted surface, type A or B (410E12000) | CY | 10 | $130.00 | $125.00 | $75.00 |
| 46 | Detour signing (614E12420) | LS | 1 | $4,800.00 | $5,000.00 | $10,000 |
| 47 | Asphalt concrete for maintaining traffic (614E13000) | CY | 10 | $350.00 | $350.00 | $250.00 |
| 48 | Work zone center line, class III, 642 paint (614E21550) | MI | 0.09 | $10,000 | $7,500.00 | $6,000.00 |
| 49 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 0.18 | $6,000.00 | $3,500.00 | $3,000.00 |
| 50 | Water (616E10000) | MGAL | 10 | $108.00 | $10.00 | $50.00 |
| 51 | Structure removed, over 20 foot span (202E11002) | LS | 1 | $75,000 | $40,000 | $160,000 |
| 52 | Wearing course removed (202E23500) | SY | 182 | $5.00 | $15.00 | $50.00 |
| 53 | Unclassified excavation (503E21300) | LS | 1 | $44,500 | $45,000 | $65,000 |
| 54 | Epoxy coated steel reinforcement (509E10000) | LB | 33,172 | $1.50 | $1.75 | $1.46 |
| 55 | Semi-integral diaphragm guide (511E33500) | EACH | 2 | $4,900.00 | $3,800.00 | $2,850.00 |
| 56 | Class QC2 concrete with QC/QA, bridge deck (511E34446) | CY | 116 | $1,500.00 | $1,250.00 | $1,350.00 |
| 57 | Class QC1 concrete with QC/QA, abutment including footing (511E43512) | CY | 104 | $850.00 | $900.00 | $700.00 |
| 58 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 149 | $38.00 | $30.00 | $44.00 |
| 59 | Type 2 waterproofing (512E33000) | SY | 15 | $45.00 | $32.00 | $20.00 |
| 60 | Structural steel members, level 1, as per plan (513E10221) | LB | 94,000 | $3.00 | $3.50 | $2.80 |
| 61 | Welded stud shear connectors (513E20000) | EACH | 1,728 | $6.00 | $9.00 | $6.85 |
| 62 | 2" preformed expansion joint filler (516E13900) | SF | 59 | $6.00 | $10.00 | $4.60 |
| 63 | Semi-integral abutment expansion joint seal (516E14020) | FT | 110 | $42.00 | $28.00 | $29.00 |
| 64 | Elastomeric bearing with internal laminates and load plate (516E44100) | EACH | 8 | $1,690.00 | $2,600.00 | $1,700.00 |
| 65 | Railing (twin steel tube) (517E70000) | FT | 178 | $258.00 | $275.00 | $275.00 |
| 66 | Porous backfill with geotextile fabric (518E21200) | CY | 72 | $131.00 | $175.00 | $175.00 |
| 67 | Special - steel drip strip (518E22300) | FT | 200.12 | $15.00 | $18.00 | $16.50 |
| 68 | 6" perforated corrugated plastic pipe (518E40000) | FT | 117 | $5.00 | $10.00 | $10.00 |
| 69 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 71 | $5.00 | $10.00 | $10.00 |
| 70 | Drilled shafts, 36" diameter, above bedrock (524E94702) | FT | 27 | $400.00 | $575.00 | $450.00 |
| 71 | Drilled shafts, 36" diameter, into bedrock (524E94704) | FT | 120 | $500.00 | $400.00 | $580.00 |
| 72 | Reinforced concrete approach slabs with QC/QA (T=1 (526E25010) | SY | 167 | $450.00 | $475.00 | $460.00 |
| 73 | Type A installation (526E90010) | FT | 74 | $160.00 | $250.00 | $340.00 |
| 74 | Structure grounding system (625E33000) | EACH | 1 | $15,750 | $17,500 | $10,000 |
| 75 | Polymer modified asphalt expansion joint system (846E00110) | CF | 31 | $650.00 | $650.00 | $700.00 |
| 76 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $7,900.00 | $20,000 | $30,000 |
| 77 | Maintaining traffic (614E11000) | LS | 1 | $3,000.00 | $5,000.00 | $15,000 |
| 78 | Field office, type B (619E16010) | MNTH | 4 | $4,500.00 | $2,000.00 | $3,000.00 |
| 79 | Construction layout stakes and surveying (623E10000) | LS | 1 | $15,000 | $5,300.00 | $30,000 |
| 80 | Mobilization (624E10000) | LS | 1 | $70,773 | $40,000 | $145,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of May 8, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way