CLE-US 50/SR 28-00.83/00.00 (MISCELLANEOUS). Let by Ohio DOT on May 15, 2025, CLE. 4 bids received; low bid $1,324,845 by Prus Construction Company, +13% against the engineer's estimate of $1,174,000.
- Owner
- Ohio DOT
- Letting
- 15 MAY 2025
- Pay items
- 44
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Prus Construction Company | $1,324,845 | Low | +13% |
| 2 | Ford Development Corp | $1,394,667 | +5.0% | +19% |
| 3 | Sunesis Construction Co | $1,454,754 | +10% | +24% |
| 4 | Axis Civil Construction LLC | $1,551,314 | +17% | +32% |
Engineer's estimate: $1,174,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Prus Construction Company | 2. Ford Development Corp | 3. Sunesis Construction Co | 4. Axis Civil Construction LLC |
|---|---|---|---|---|---|---|---|
| 1 | Pavement removed (202E23000) | SY | 1,625 | $46.00 | $18.00 | $39.27 | $45.00 |
| 2 | Walk removed (202E30000) | SF | 25,304 | $3.00 | $2.00 | $5.23 | $4.00 |
| 3 | Curb removed (202E32000) | FT | 1,907 | $20.50 | $8.00 | $1.43 | $26.00 |
| 4 | 5" concrete walk, as per plan (608E12001) | SF | 25,294 | $9.75 | $13.00 | $10.39 | $13.00 |
| 5 | 7" concrete walk (608E13020) | SF | 6,399 | $16.00 | $14.00 | $12.41 | $18.50 |
| 6 | Curb ramp (608E52000) | SF | 2,756 | $25.00 | $47.00 | $25.31 | $32.50 |
| 7 | Walkway, misc.:5" concrete walk (608E98000) | SF | 1,000 | $17.00 | $12.00 | $12.65 | $25.00 |
| 8 | Valve box adjusted to grade (638E10800) | EACH | 19 | $350.00 | $50.00 | $142.56 | $500.00 |
| 9 | Soil analysis test (659E00100) | EACH | 2 | $265.00 | $175.00 | $100.00 | $150.00 |
| 10 | Repair seeding and mulching (659E14000) | SY | 62 | $2.40 | $1.00 | $14.89 | $18.00 |
| 11 | Commercial fertilizer (659E20000) | TON | 0.17 | $1,575.00 | $100.00 | $2,291.65 | $250.00 |
| 12 | Lime (659E31000) | ACRE | 0.26 | $1,050.00 | $100.00 | $2,298.58 | $160.00 |
| 13 | Water (659E35000) | MGAL | 7 | $10.00 | $3.00 | $195.52 | $1.00 |
| 14 | Erosion control (832E30000) | EACH | 10,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 15 | Pavement repair, as per plan (253E01001) | SY | 440 | $113.00 | $90.00 | $248.90 | $200.00 |
| 16 | 6" non-reinforced concrete pavement, class QC 1P (452E10010) | SY | 482 | $130.00 | $160.00 | $116.89 | $125.00 |
| 17 | 6" non-reinforced concrete pavement, class QC 1P, as per plan (452E10011) | SY | 60 | $175.00 | $160.00 | $159.13 | $320.00 |
| 18 | 8" non-reinforced concrete pavement, class QC 1P, as per plan (452E12011) | SY | 40 | $950.00 | $1,325.00 | $316.45 | $950.00 |
| 19 | Curb, type 6 (609E26000) | FT | 1,526 | $42.00 | $60.00 | $44.46 | $48.00 |
| 20 | Conduit, 2", 725.051, as per plan (625E25409) | FT | 1,883 | $8.00 | $8.25 | $7.50 | $14.00 |
| 21 | Conduit, jacked or drilled, 725.052, as per plan (625E25909) | FT | 91 | $84.00 | $88.00 | $80.00 | $40.00 |
| 22 | Trench, 30" deep (625E29010) | FT | 1,883 | $25.20 | $26.40 | $24.00 | $17.00 |
| 23 | Pull box, misc.:duke pull box, installation only (625E31600) | EACH | 8 | $1,440.00 | $1,508.00 | $1,371.00 | $650.00 |
| 24 | Underground warning marking tape (625E36010) | FT | 1,883 | $1.80 | $1.90 | $1.70 | $3.00 |
| 25 | Lighting, misc.:duke energy lighting (625E98000) | EACH | 208,077 | $1.00 | $1.00 | $1.00 | $1.00 |
| 26 | Ground rod (625E32000) | EACH | 4 | $725.00 | $759.00 | $690.00 | $272.00 |
| 27 | Ground mounted support, no. 3 post (630E03100) | FT | 244 | $16.50 | $22.00 | $19.91 | $19.91 |
| 28 | Sign post reflector (630E08600) | EACH | 1 | $57.75 | $84.00 | $76.53 | $77.00 |
| 29 | Sign, flat sheet (630E80100) | SF | 86 | $16.80 | $26.25 | $23.89 | $24.00 |
| 30 | Removal of ground mounted sign and disposal (630E84900) | EACH | 5 | $21.00 | $20.00 | $16.56 | $17.00 |
| 31 | Removal of ground mounted sign and reerection (630E85100) | EACH | 6 | $47.25 | $85.00 | $76.54 | $77.00 |
| 32 | Removal of ground mounted post support and disposal (630E86002) | EACH | 7 | $26.25 | $25.00 | $22.08 | $22.00 |
| 33 | Removal of pole mounted sign and reerection (630E87520) | EACH | 1 | $47.25 | $200.00 | $183.65 | $185.00 |
| 34 | Signing, misc.:solar powered RRFB sign assembly (630E97700) | EACH | 4 | $7,000.00 | $7,315.00 | $6,650.00 | $8,600.00 |
| 35 | Pedestal foundation (632E64020) | EACH | 4 | $2,373.00 | $2,485.00 | $2,260.00 | $1,500.00 |
| 36 | Stop line (644E00500) | FT | 12 | $21.00 | $16.05 | $14.60 | $15.00 |
| 37 | Crosswalk line, 12" (644E00620) | FT | 56 | $11.25 | $15.25 | $13.85 | $14.00 |
| 38 | Yield line (644E20800) | FT | 80 | $21.00 | $18.00 | $16.35 | $16.50 |
| 39 | Removal of pavement marking (644E30000) | FT | 78 | $25.50 | $23.30 | $21.20 | $22.00 |
| 40 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $12,000 | $13,900 | $8,411.97 | $11,000 |
| 41 | Maintaining traffic (614E11000) | LS | 1 | $50,000 | $40,000 | $50,771 | $65,000 |
| 42 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 8 | $130.00 | $150.00 | $82.00 | $75.00 |
| 43 | Construction layout stakes and surveying (623E10000) | LS | 1 | $10,000 | $10,000 | $20,100 | $15,000 |
| 44 | Mobilization (624E10000) | LS | 1 | $40,000 | $40,000 | $140,195 | $40,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of May 15, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.