ODOT contract 250269 bid tabulation
JEF-SR 150-03.544 (INTERSECTION). Let by Ohio DOT on May 8, 2025, JEF. 5 bids received; low bid $498,957 by LMS Construction Inc, -4.0% against the engineer's estimate of $520,000.
- Owner
- Ohio DOT
- Letting
- 08 MAY 2025
- Pay items
- 70
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | LMS Construction Inc | $498,957 | Low | -4.0% |
| 2 | Ohio-West Virginia Excavating Co | $619,022 | +24% | +19% |
| 3 | Tucson Inc | $630,662 | +26% | +21% |
| 4 | NLS Paving, Inc | $646,155 | +30% | +24% |
| 5 | Shelly & Sands Inc | $657,944 | +32% | +27% |
Engineer's estimate: $520,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. LMS Construction Inc | 2. Ohio-West Virginia Excavating Co | 3. Tucson Inc | 4. NLS Paving, Inc | 5. Shelly & Sands Inc |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $1,000.00 | $3,600.00 | $10,120 | $1,000.00 | $900.00 |
| 2 | Pavement removed (202E23000) | SY | 1,362 | $10.00 | $27.00 | $10.00 | $40.00 | $21.00 |
| 3 | Walk removed, as per plan (202E30001) | SF | 804 | $5.00 | $5.00 | $3.50 | $9.00 | $1.50 |
| 4 | Curb removed (202E32000) | FT | 65 | $12.00 | $27.00 | $18.15 | $13.50 | $9.00 |
| 5 | Pipe removed, 24" and under (202E35100) | FT | 128 | $10.00 | $95.00 | $11.10 | $45.00 | $42.00 |
| 6 | Catch basin removed (202E58100) | EACH | 3 | $800.00 | $1,700.00 | $380.00 | $1,625.00 | $450.00 |
| 7 | Removal misc.: foundation (202E98000) | LS | 1 | $800.00 | $1,800.00 | $1,525.00 | $950.00 | $2,250.00 |
| 8 | Removal misc.: sign support on building (202E98000) | LS | 1 | $800.00 | $1,500.00 | $2,000.00 | $450.00 | $575.00 |
| 9 | Excavation (203E10000) | CY | 252 | $35.00 | $40.00 | $57.00 | $48.25 | $47.00 |
| 10 | Embankment (203E20000) | CY | 112 | $35.00 | $73.00 | $36.50 | $100.00 | $20.00 |
| 11 | Roadway, misc.: removal and reset of decorative RO (203E98100) | SY | 47 | $10.00 | $90.00 | $104.00 | $110.00 | $60.00 |
| 12 | Subgrade compaction (204E10000) | SY | 1,694 | $4.00 | $1.00 | $3.00 | $0.50 | $8.00 |
| 13 | Proof rolling (204E45000) | HR | 1 | $300.00 | $200.00 | $178.00 | $250.00 | $250.00 |
| 14 | 6" concrete walk (608E13000) | SF | 985 | $20.00 | $20.00 | $13.65 | $17.50 | $14.00 |
| 15 | Curb ramp (608E52000) | SF | 244 | $25.00 | $40.00 | $32.15 | $44.00 | $45.00 |
| 16 | Special - work involving petroleum contaminated soil (690E65016) | TON | 290 | $25.00 | $100.00 | $124.00 | $110.00 | $128.00 |
| 17 | Special - work involving regulated water (690E65024) | GAL | 50 | $10.00 | $33.00 | $68.00 | $40.00 | $58.00 |
| 18 | Seeding and mulching, class 1 (659E00500) | SY | 182 | $5.00 | $6.00 | $17.00 | $8.00 | $15.50 |
| 19 | Commercial fertilizer (659E20000) | TON | 0.02 | $20,000 | $1,475.00 | $2,430.00 | $16,500 | $850.00 |
| 20 | Lime (659E31000) | ACRE | 0.04 | $10,000 | $180.00 | $2,500.00 | $4,000.00 | $50.00 |
| 21 | Water (659E35000) | MGAL | 5 | $5.00 | $1.00 | $1.00 | $275.00 | $1.00 |
| 22 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 23 | 6" shallow pipe underdrains (605E11100) | FT | 680 | $25.00 | $26.00 | $36.00 | $35.00 | $25.00 |
| 24 | 12" conduit, type C (611E04600) | FT | 43 | $80.00 | $140.00 | $178.00 | $104.00 | $150.00 |
| 25 | 15" conduit, type B (611E05900) | FT | 8 | $200.00 | $516.00 | $178.00 | $230.00 | $200.00 |
| 26 | 18" conduit, type B (611E07400) | FT | 62 | $150.00 | $265.00 | $151.00 | $105.00 | $200.00 |
| 27 | Catch basin, no. 3 (611E98150) | EACH | 1 | $6,000.00 | $4,700.00 | $4,650.00 | $4,425.00 | $5,300.00 |
| 28 | Catch basin, no. 2-2B (611E98470) | EACH | 2 | $3,500.00 | $2,960.00 | $3,325.00 | $4,150.00 | $3,100.00 |
| 29 | Manhole adjusted to grade (611E99654) | EACH | 1 | $600.00 | $1,490.00 | $1,008.00 | $950.00 | $100.00 |
| 30 | Full depth pavement sawing (252E01500) | FT | 203 | $5.00 | $15.00 | $8.85 | $10.50 | $8.00 |
| 31 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 287 | $235.00 | $259.00 | $292.00 | $250.00 | $265.00 |
| 32 | Asphalt concrete base, PG64-22, (449), (driveways) (301E56100) | CY | 3 | $950.00 | $1,105.00 | $991.00 | $450.00 | $900.00 |
| 33 | Aggregate base (304E20000) | CY | 252 | $125.00 | $161.00 | $128.00 | $145.00 | $145.00 |
| 34 | Non-tracking tack coat (407E20000) | GAL | 247 | $3.00 | $9.00 | $4.00 | $4.00 | $3.50 |
| 35 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 7 | $950.00 | $765.00 | $1,050.00 | $575.00 | $950.00 |
| 36 | Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100) | CY | 46 | $600.00 | $337.00 | $551.00 | $350.00 | $500.00 |
| 37 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 64 | $450.00 | $305.00 | $606.00 | $390.00 | $550.00 |
| 38 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 1 | $2,000.00 | $3,772.00 | $1,000.00 | $1,500.00 | $900.00 |
| 39 | 6" non-reinforced concrete pavement, class QC 1P (452E10010) | SY | 27 | $150.00 | $360.00 | $109.00 | $300.00 | $130.00 |
| 40 | 8" non-reinforced concrete pavement, class QC 1P (452E12010) | SY | 77 | $140.00 | $221.00 | $124.00 | $170.00 | $145.00 |
| 41 | Curb, type 6 (609E26000) | FT | 168 | $50.00 | $75.00 | $42.00 | $66.00 | $63.00 |
| 42 | Valve box adjusted to grade (638E10800) | EACH | 5 | $300.00 | $675.00 | $825.00 | $585.00 | $1,045.00 |
| 43 | Ground mounted support, no. 3 post (630E03100) | FT | 26 | $48.00 | $6.00 | $52.25 | $50.00 | $48.00 |
| 44 | Sign post reflector (630E08600) | EACH | 2 | $45.00 | $14.00 | $150.00 | $50.00 | $45.00 |
| 45 | Sign, flat sheet (630E80100) | SF | 26 | $52.00 | $25.00 | $57.00 | $55.00 | $52.00 |
| 46 | Removal of ground mounted sign and disposal (630E84900) | EACH | 2 | $15.00 | $60.00 | $18.00 | $230.00 | $15.00 |
| 47 | Removal of ground mounted sign and reerection (630E85100) | EACH | 1 | $85.00 | $236.00 | $145.00 | $460.00 | $85.00 |
| 48 | Removal of ground mounted post support and disposal (630E86002) | EACH | 2 | $20.00 | $180.00 | $108.25 | $230.00 | $20.00 |
| 49 | Edge line, 6" (646E10010) | MI | 0.12 | $15,000 | $19,260 | $32,000 | $17,400 | $16,320 |
| 50 | Center line (646E10200) | MI | 0.06 | $25,000 | $34,000 | $42,650 | $30,800 | $28,965 |
| 51 | Dotted line, 6" (646E20504) | FT | 21 | $6.00 | $6.00 | $4.60 | $5.50 | $5.00 |
| 52 | Traffic compacted surface, type A (410E10000) | CY | 50 | $82.53 | $198.00 | $115.00 | $190.00 | $95.00 |
| 53 | Temporary asphalt concrete walk (608E21200) | SF | 735 | $20.00 | $13.00 | $6.00 | $10.50 | $10.50 |
| 54 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 3 | $2,925.00 | $2,450.00 | $2,755.00 | $3,100.00 | $2,925.00 |
| 55 | Detour signing (614E12420) | LS | 1 | $7,500.00 | $8,900.00 | $8,300.00 | $8,000.00 | $8,200.00 |
| 56 | Asphalt concrete for maintaining traffic (614E13000) | CY | 50 | $100.00 | $200.00 | $372.00 | $350.00 | $500.00 |
| 57 | Barrier reflector, type 1, one-way (614E13310) | EACH | 9 | $50.00 | $55.00 | $55.50 | $50.00 | $10.00 |
| 58 | Object marker, one way (614E13350) | EACH | 9 | $50.00 | $55.00 | $55.50 | $50.00 | $17.00 |
| 59 | Portable changeable message sign, as per plan (614E18601) | SNMT | 9 | $1,500.00 | $1,800.00 | $1,660.00 | $1,600.00 | $1,500.00 |
| 60 | Work zone edge line, class I, 6", 642 paint (614E22110) | MI | 0.57 | $3,325.00 | $3,900.00 | $3,660.00 | $3,600.00 | $3,325.00 |
| 61 | Work zone edge line, class I, 6", 740.06, type I (614E22210) | MI | 0.57 | $9,750.00 | $11,500 | $10,730 | $11,000 | $9,750.00 |
| 62 | Roads for maintaining traffic (615E10000) | LS | 1 | $3,000.00 | $7,000.00 | $12,300 | $6,700.00 | $13,000 |
| 63 | Pavement for maintaining traffic, class A (615E20000) | SY | 142 | $100.00 | $145.00 | $132.00 | $100.00 | $88.00 |
| 64 | Water (616E10000) | MGAL | 2 | $5.00 | $1.00 | $5.00 | $185.00 | $60.00 |
| 65 | Portable barrier, unanchored (622E41100) | FT | 482 | $40.00 | $40.00 | $54.50 | $45.00 | $38.00 |
| 66 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $20,000 | $8,500.00 | $9,800.00 | $3,000.00 | $4,725.39 |
| 67 | Maintaining traffic (614E11000) | LS | 1 | $24,000 | $17,000 | $33,500 | $20,000 | $47,550 |
| 68 | Field office, type B (619E16010) | MNTH | 3 | $1,400.00 | $3,800.00 | $2,375.00 | $3,000.00 | $7,900.00 |
| 69 | Construction layout stakes and surveying (623E10000) | LS | 1 | $2,500.00 | $4,000.00 | $16,300 | $27,000 | $18,500 |
| 70 | Mobilization (624E10000) | LS | 1 | $20,000 | $29,500 | $22,600 | $40,000 | $30,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of May 8, 2025. Compiled by Mirage Metrics.