MAR-US 23/SR 529-07.86 & 10.06/02.80 (BRIDGE REPAIR). Let by Ohio DOT on August 14, 2025, MAR. 3 bids received; low bid $7,286,057 by Shelly & Sands Inc, +5.4% against the engineer's estimate of $6,911,000.
- Owner
- Ohio DOT
- Letting
- 14 AUG 2025
- Pay items
- 201
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly & Sands Inc | $7,286,057 | Low | +5.0% |
| 2 | Ruhlin Company | $7,623,518 | +5.0% | +10% |
| 3 | Complete General Construction Company | $7,818,106 | +7.0% | +13% |
Engineer's estimate: $6,911,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly & Sands Inc | 2. Ruhlin Company | 3. Complete General Construction Company |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $11,000 | $15,000 | $15,000 |
| 2 | Pavement removed (202E23000) | SY | 11,411 | $18.00 | $26.25 | $20.00 |
| 3 | Guardrail removed (202E38000) | FT | 300 | $3.00 | $2.00 | $2.00 |
| 4 | Bridge terminal assembly removed (202E47000) | EACH | 12 | $123.00 | $95.00 | $250.00 |
| 5 | Subgrade compaction (204E10000) | SY | 12,714 | $3.45 | $3.50 | $3.50 |
| 6 | Guardrail, type MGS (606E15050) | FT | 100 | $25.00 | $26.40 | $26.40 |
| 7 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 8 | $2,700.00 | $2,980.00 | $2,980.00 |
| 8 | MGS bridge terminal assembly, type 2 (606E35102) | EACH | 4 | $590.00 | $720.00 | $720.00 |
| 9 | Concrete barrier end section, type D (622E25000) | EACH | 4 | $8,000.00 | $5,100.00 | $5,000.00 |
| 10 | Concrete barrier end section, type D, as per plan (622E25001) | EACH | 2 | $8,000.00 | $5,250.00 | $6,000.00 |
| 11 | Special - asbestos abatement(see proposal note) (690E71000) | LS | 1 | $6,000.00 | $15,200 | $35,000 |
| 12 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 1 | $250.00 | $600.00 | $350.00 |
| 13 | Tied concrete block mat with type 2 underlayment (601E21060) | SY | 318 | $60.00 | $130.00 | $98.00 |
| 14 | Water (616E10000) | MGAL | 1 | $1.00 | $39.71 | $200.00 |
| 15 | Soil analysis test (659E00100) | EACH | 1 | $200.00 | $25.00 | $125.00 |
| 16 | Topsoil (659E00300) | CY | 1,129 | $40.00 | $45.00 | $40.00 |
| 17 | Seeding and mulching (659E10000) | SY | 10,164 | $1.55 | $0.92 | $0.92 |
| 18 | Repair seeding and mulching (659E14000) | SY | 508 | $1.00 | $0.60 | $0.80 |
| 19 | Inter-seeding (659E15000) | SY | 508 | $1.29 | $0.30 | $0.80 |
| 20 | Commercial fertilizer (659E20000) | TON | 0.25 | $1,600.00 | $800.00 | $892.00 |
| 21 | Lime (659E31000) | ACRE | 2.10 | $215.00 | $5.00 | $156.00 |
| 22 | Water (659E35000) | MGAL | 82 | $1.00 | $5.00 | $1.00 |
| 23 | Mowing (659E40000) | MSF | 1 | $1.00 | $80.00 | $800.00 |
| 24 | Erosion control (832E30000) | EACH | 50,000 | $1.00 | $1.00 | $1.00 |
| 25 | Concrete masonry (602E20000) | CY | 0.40 | $6,500.00 | $6,500.00 | $4,500.00 |
| 26 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 12 | $50.00 | $90.00 | $90.00 |
| 27 | 12" conduit, type F (611E05200) | FT | 97 | $120.00 | $120.00 | $165.00 |
| 28 | Precast reinforced concrete outlet (611E99710) | EACH | 2 | $580.00 | $650.00 | $350.00 |
| 29 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 3,494 | $230.00 | $237.00 | $230.00 |
| 30 | Aggregate base (304E20000) | CY | 516 | $102.00 | $115.00 | $100.00 |
| 31 | Aggregate base, as per plan (304E20001) | CY | 2,096 | $65.00 | $120.00 | $105.00 |
| 32 | Tack coat (407E10000) | GAL | 1,197 | $2.25 | $2.00 | $2.25 |
| 33 | Non-tracking tack coat (407E20000) | GAL | 165 | $3.25 | $2.00 | $3.25 |
| 34 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 120 | $290.00 | $350.00 | $290.00 |
| 35 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 122 | $275.00 | $325.00 | $275.00 |
| 36 | Asphalt concrete surface course, 12.5 MM, type A (448) (442E20000) | CY | 448 | $315.00 | $335.00 | $315.00 |
| 37 | Asphalt concrete intermediate course, 12.5 MM, type A (448) (442E20170) | CY | 448 | $300.00 | $325.00 | $300.00 |
| 38 | Curb, type 4-C (609E24510) | FT | 345 | $60.00 | $23.00 | $65.00 |
| 39 | Compacted aggregate (617E10100) | CY | 457 | $55.00 | $75.00 | $55.00 |
| 40 | Water (617E25000) | MGAL | 1 | $115.00 | $100.00 | $78.04 |
| 41 | Rumble stripes, edge line (asphalt concrete) (618E40800) | FT | 14,450 | $0.50 | $0.45 | $1.90 |
| 42 | Edge line, 4", type 1 (642E00100) | MI | 3.90 | $740.00 | $1,000.00 | $1,000.00 |
| 43 | Center line, type 1 (642E00300) | MI | 1.95 | $1,100.00 | $1,980.00 | $1,980.00 |
| 44 | Edge line, 6" (644E00104) | MI | 1.44 | $8,000.00 | $8,025.00 | $8,025.00 |
| 45 | Lane line, 6" (644E00204) | MI | 0.03 | $8,000.00 | $3,795.00 | $3,795.00 |
| 46 | Traffic compacted surface, type A or B (410E12000) | CY | 359 | $85.00 | $100.76 | $90.00 |
| 47 | Maintaining traffic (614E11000) | LS | 1 | $150,000 | $168,500 | $115,000 |
| 48 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 400 | $120.00 | $90.00 | $95.00 |
| 49 | Increased barrier delineation (614E11630) | FT | 11,590 | $0.50 | $1.29 | $1.40 |
| 50 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 14 | $2,300.00 | $1,918.66 | $2,000.00 |
| 51 | Work zone impact attenuator, over 24" and less than 36" wide hazards, (unidirectional) (614E12390) | EACH | 2 | $2,300.00 | $3,970.42 | $4,000.00 |
| 52 | Detour signing (614E12420) | LS | 1 | $15,000 | $9,924.39 | $18,000 |
| 53 | Work zone marking sign (614E12460) | EACH | 23 | $305.00 | $99.99 | $270.00 |
| 54 | Asphalt concrete for maintaining traffic (614E13000) | CY | 359 | $220.00 | $228.00 | $300.00 |
| 55 | Barrier reflector, type 1, one-way (614E13310) | EACH | 280 | $10.00 | $11.91 | $15.00 |
| 56 | Object marker, one way (614E13350) | EACH | 331 | $17.00 | $20.11 | $18.00 |
| 57 | Portable changeable message sign, as per plan (614E18601) | SNMT | 8 | $800.00 | $977.40 | $1,100.00 |
| 58 | Work zone edge line, class I, 4", 740.06, type I (614E22200) | MI | 11.45 | $11,770 | $7,649.35 | $7,650.00 |
| 59 | Work zone dotted line, class I, 4", 740.06, type I (614E24400) | FT | 2,647 | $1.00 | $1.03 | $1.03 |
| 60 | Work zone pavement marking, misc.: "black-out" tem (614E98000) | MI | 10.52 | $15,450 | $15,060 | $15,060 |
| 61 | Portable barrier, unanchored (622E41100) | FT | 13,330 | $20.00 | $17.90 | $30.00 |
| 62 | Barrier reflector, type 4, one-way (626E00114) | EACH | 51 | $16.00 | $15.00 | $19.00 |
| 63 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $150,000 | $190,000 | $240,000 |
| 64 | Epoxy coated steel reinforcement (509E10000) | LB | 38,609 | $2.40 | $2.79 | $2.50 |
| 65 | Concrete reinforcement, replacement of existing concrete reinforcement, as per plan (509E20001) | LB | 1,409 | $0.80 | $2.67 | $2.50 |
| 66 | No. 4 deformed GFRP reinforcement (509E30020) | FT | 6,335 | $2.00 | $1.72 | $1.83 |
| 67 | Dowel holes with nonshrink, nonmetallic grout (510E10000) | EACH | 48 | $85.00 | $35.00 | $18.00 |
| 68 | Class QC2 concrete with QC/QA, superstructure (511E32212) | CY | 94 | $1,750.00 | $2,000.00 | $1,650.00 |
| 69 | Class QC2 concrete with QC/QA, bridge deck (parapet) (511E34450) | CY | 63 | $1,100.00 | $700.00 | $885.00 |
| 70 | Class QC1 concrete, abutment (511E45710) | CY | 5 | $2,270.00 | $1,550.00 | $700.00 |
| 71 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 495 | $30.00 | $40.00 | $28.50 |
| 72 | Structural expansion joint including elastomeric compression seal, as per plan (516E10501) | FT | 90 | $840.00 | $800.00 | $800.00 |
| 73 | Special - composite fiber wrap system (519E00100) | SF | 341 | $35.00 | $45.00 | $45.00 |
| 74 | Patching concrete structure, as per plan (519E11101) | SF | 89 | $200.00 | $170.00 | $185.00 |
| 75 | Pull box, 725.08, 32" (625E30710) | EACH | 2 | $2,150.00 | $3,606.99 | $4,350.00 |
| 76 | Conduit, 4", multicell, HDPE with 4 - 1" innerducts (809E24500) | FT | 166 | $27.00 | $39.82 | $58.50 |
| 77 | Superplasticized dense concrete overlay using hydrodemolition (848E10200) | SY | 799 | $125.00 | $115.97 | $95.00 |
| 78 | Surface preparation using hydrodemolition (848E20000) | SY | 799 | $89.00 | $73.99 | $105.00 |
| 79 | Superplasticized dense concrete overlay (variable thickness), material only (848E30200) | CY | 16 | $275.00 | $426.88 | $257.00 |
| 80 | Hand chipping (848E50000) | SY | 100 | $75.00 | $140.13 | $75.00 |
| 81 | Test slab (848E50100) | LS | 1 | $2,400.00 | $3,059.51 | $1,200.00 |
| 82 | Full-depth repair (848E50200) | CY | 1 | $2,000.00 | $692.84 | $1,700.00 |
| 83 | Existing concrete overlay removed (1.75" thick) (848E50320) | SY | 809 | $12.50 | $14.61 | $12.75 |
| 84 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $125,000 | $190,000 | $240,000 |
| 85 | Epoxy coated steel reinforcement (509E10000) | LB | 38,609 | $2.40 | $2.79 | $2.50 |
| 86 | Concrete reinforcement, replacement of existing concrete reinforcement, as per plan (509E20001) | LB | 1,409 | $0.82 | $2.67 | $2.50 |
| 87 | No. 4 deformed GFRP reinforcement (509E30020) | FT | 6,335 | $2.00 | $1.72 | $1.83 |
| 88 | Dowel holes with nonshrink, nonmetallic grout (510E10000) | EACH | 48 | $84.00 | $35.00 | $18.22 |
| 89 | Class QC2 concrete with QC/QA, superstructure (511E32212) | CY | 94 | $1,750.00 | $2,000.00 | $1,650.00 |
| 90 | Class QC2 concrete with QC/QA, bridge deck (parapet) (511E34450) | CY | 63 | $900.00 | $700.00 | $885.00 |
| 91 | Class QC1 concrete, abutment (511E45710) | CY | 5 | $2,200.00 | $1,600.00 | $700.00 |
| 92 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 495 | $30.00 | $40.00 | $28.50 |
| 93 | Structural expansion joint including elastomeric compression seal, as per plan (516E10501) | FT | 90 | $845.00 | $800.00 | $800.00 |
| 94 | Special - composite fiber wrap system (519E00100) | SF | 1,327 | $35.00 | $27.00 | $42.00 |
| 95 | Patching concrete structure, as per plan (519E11101) | SF | 451 | $180.00 | $170.00 | $170.00 |
| 96 | Superplasticized dense concrete overlay using hydrodemolition (848E10200) | SY | 799 | $110.00 | $115.97 | $95.00 |
| 97 | Surface preparation using hydrodemolition (848E20000) | SY | 799 | $90.00 | $73.99 | $105.00 |
| 98 | Superplasticized dense concrete overlay (variable thickness), material only (848E30200) | CY | 18 | $275.00 | $418.29 | $257.00 |
| 99 | Hand chipping (848E50000) | SY | 110 | $75.00 | $127.39 | $75.00 |
| 100 | Test slab (848E50100) | LS | 1 | $2,400.00 | $3,059.51 | $1,200.00 |
| 101 | Existing concrete overlay removed (1.75" thick) (848E50320) | SY | 809 | $12.00 | $14.61 | $12.75 |
| 102 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $125,000 | $135,000 | $230,000 |
| 103 | Approach slab removed (202E22900) | SY | 134 | $40.00 | $60.00 | $70.00 |
| 104 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $15,000 | $25,000 | $25,000 |
| 105 | Unclassified excavation (503E21100) | CY | 28 | $320.00 | $500.00 | $300.00 |
| 106 | Epoxy coated steel reinforcement (509E10000) | LB | 25,861 | $2.75 | $3.29 | $2.90 |
| 107 | Concrete reinforcement, replacement of existing concrete reinforcement, as per plan (509E20001) | LB | 850 | $2.00 | $2.68 | $2.90 |
| 108 | No. 4 deformed GFRP reinforcement (509E30020) | FT | 4,270 | $2.00 | $1.72 | $1.83 |
| 109 | Dowel holes with nonshrink, nonmetallic grout (510E10000) | EACH | 72 | $70.00 | $35.00 | $18.00 |
| 110 | Class QC2 concrete, superstructure (511E32210) | CY | 89 | $1,700.00 | $2,000.00 | $1,400.00 |
| 111 | Class QC2 concrete, bridge deck (parapet) (511E34448) | CY | 43 | $1,550.00 | $800.00 | $1,100.00 |
| 112 | Class QC1 concrete, abutment including footing (511E43510) | CY | 10 | $4,000.00 | $2,250.00 | $1,900.00 |
| 113 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 357 | $30.00 | $40.00 | $28.50 |
| 114 | 1" preformed expansion joint filler (516E13600) | SF | 308 | $7.50 | $8.60 | $13.00 |
| 115 | Semi-integral abutment expansion joint seal (516E14020) | FT | 102 | $57.99 | $50.00 | $54.00 |
| 116 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $45,000 | $41,000 | $75,000 |
| 117 | Porous backfill with geotextile fabric (518E21200) | CY | 49 | $150.00 | $125.00 | $100.00 |
| 118 | 6" perforated corrugated plastic pipe (518E40000) | FT | 100 | $10.00 | $17.00 | $12.00 |
| 119 | 6" non-perforated corrugated plastic pipe (518E40012) | FT | 40 | $10.00 | $19.00 | $20.00 |
| 120 | Special - composite fiber wrap system (519E00100) | SF | 383 | $35.00 | $38.00 | $42.00 |
| 121 | Patching concrete structure, as per plan (519E11101) | SF | 71 | $200.00 | $170.00 | $185.00 |
| 122 | Reinforced concrete approach slabs (T=15") (526E25000) | SY | 225 | $420.00 | $425.00 | $380.00 |
| 123 | Type A installation (526E90010) | FT | 77 | $235.00 | $170.00 | $300.00 |
| 124 | Crushed aggregate slope protection (601E20010) | CY | 32 | $200.00 | $100.00 | $200.00 |
| 125 | Superplasticized dense concrete overlay using hydrodemolition (848E10200) | SY | 495 | $150.00 | $153.21 | $120.00 |
| 126 | Surface preparation using hydrodemolition (848E20000) | SY | 495 | $90.00 | $84.37 | $125.00 |
| 127 | Superplasticized dense concrete overlay (variable thickness), material only (848E30200) | CY | 9 | $275.00 | $418.29 | $257.00 |
| 128 | Hand chipping (848E50000) | SY | 56 | $75.00 | $125.12 | $85.00 |
| 129 | Test slab (848E50100) | LS | 1 | $2,400.00 | $3,059.51 | $1,200.00 |
| 130 | Full-depth repair (848E50200) | CY | 1 | $2,500.00 | $702.43 | $1,800.00 |
| 131 | Existing concrete overlay removed (1.75") (848E50320) | SY | 448 | $15.00 | $23.93 | $18.00 |
| 132 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $122,000 | $135,000 | $230,000 |
| 133 | Approach slab removed (202E22900) | SY | 134 | $43.00 | $60.00 | $70.00 |
| 134 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $18,000 | $25,000 | $25,000 |
| 135 | Unclassified excavation (503E21100) | CY | 28 | $330.00 | $500.00 | $300.00 |
| 136 | Epoxy coated steel reinforcement (509E10000) | LB | 25,861 | $3.00 | $3.29 | $2.90 |
| 137 | Concrete reinforcement, replacement of existing concrete reinforcement, as per plan (509E20001) | LB | 850 | $2.00 | $2.68 | $2.90 |
| 138 | No. 4 deformed GFRP reinforcement (509E30020) | FT | 4,270 | $2.00 | $1.72 | $1.83 |
| 139 | Dowel holes with nonshrink, nonmetallic grout (510E10000) | EACH | 72 | $55.00 | $35.00 | $18.00 |
| 140 | Class QC2 concrete, superstructure (511E32210) | CY | 89 | $1,750.00 | $2,000.00 | $1,400.00 |
| 141 | Class QC2 concrete, bridge deck (parapet) (511E34448) | CY | 43 | $1,450.00 | $800.00 | $1,100.00 |
| 142 | Class QC1 concrete, abutment including footing (511E43510) | CY | 10 | $4,800.00 | $2,250.00 | $1,900.00 |
| 143 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 357 | $30.00 | $40.00 | $28.50 |
| 144 | 1" preformed expansion joint filler (516E13600) | SF | 308 | $5.00 | $8.60 | $13.00 |
| 145 | Semi-integral abutment expansion joint seal (516E14020) | FT | 102 | $54.00 | $50.00 | $54.00 |
| 146 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $42,000 | $41,000 | $75,000 |
| 147 | Porous backfill with geotextile fabric (518E21200) | CY | 49 | $157.00 | $125.00 | $100.00 |
| 148 | 6" perforated corrugated plastic pipe (518E40000) | FT | 100 | $10.00 | $17.00 | $12.00 |
| 149 | 6" non-perforated corrugated plastic pipe (518E40012) | FT | 40 | $10.00 | $19.00 | $20.00 |
| 150 | Special - composite fiber wrap system (519E00100) | SF | 524 | $35.00 | $35.00 | $42.00 |
| 151 | Patching concrete structure, as per plan (519E11101) | SF | 115 | $195.00 | $170.00 | $185.00 |
| 152 | Reinforced concrete approach slabs (T=15") (526E25000) | SY | 225 | $425.00 | $425.00 | $380.00 |
| 153 | Type A installation (526E90010) | FT | 77 | $210.00 | $170.00 | $300.00 |
| 154 | Crushed aggregate slope protection (601E20010) | CY | 32 | $205.00 | $100.00 | $200.00 |
| 155 | Pull box, 725.08, 32" (625E30710) | EACH | 2 | $5,700.00 | $3,606.99 | $4,350.00 |
| 156 | Conduit, 4", multicell, HDPE with 4 - 1" innerducts (809E24500) | FT | 166 | $45.00 | $39.82 | $58.50 |
| 157 | Superplasticized dense concrete overlay using hydrodemolition (848E10200) | SY | 495 | $140.00 | $157.45 | $120.00 |
| 158 | Surface preparation using hydrodemolition (848E20000) | SY | 495 | $92.00 | $84.37 | $125.00 |
| 159 | Superplasticized dense concrete overlay (variable thickness), material only (848E30200) | CY | 9 | $275.00 | $418.29 | $257.00 |
| 160 | Hand chipping (848E50000) | SY | 57 | $75.00 | $122.92 | $85.00 |
| 161 | Test slab (848E50100) | LS | 1 | $2,400.00 | $3,059.51 | $1,200.00 |
| 162 | Full-depth repair (848E50200) | CY | 6 | $1,600.00 | $702.40 | $1,400.00 |
| 163 | Existing concrete overlay removed (2.25") (848E50320) | SY | 448 | $16.00 | $25.14 | $18.00 |
| 164 | Portions of structure removed, as per plan (202E11201) | LS | 1 | $72,000 | $78,000 | $70,000 |
| 165 | Approach slab removed (202E22900) | SY | 85 | $50.00 | $60.00 | $70.00 |
| 166 | Unclassified excavation, as per plan (503E21301) | LS | 1 | $18,000 | $7,100.00 | $12,000 |
| 167 | Epoxy coated steel reinforcement (509E10000) | LB | 5,237 | $2.00 | $1.75 | $1.75 |
| 168 | Concrete reinforcement, replacement of existing concrete reinforcement, as per plan (509E20001) | LB | 100 | $2.26 | $2.68 | $2.75 |
| 169 | Dowel holes with nonshrink, nonmetallic grout (510E10000) | EACH | 122 | $45.00 | $35.00 | $16.00 |
| 170 | Semi-integral diaphragm guide, as per plan (511E33501) | EACH | 2 | $4,000.00 | $4,150.00 | $3,600.00 |
| 171 | Class QC2 concrete, bridge deck (511E34444) | CY | 28 | $2,775.00 | $1,350.00 | $1,400.00 |
| 172 | Class QC1 concrete, abutment (511E45710) | CY | 11 | $2,800.00 | $1,500.00 | $1,800.00 |
| 173 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 71 | $58.01 | $50.00 | $58.50 |
| 174 | Structural steel, misc.: (drilled holes) (513E95030) | EACH | 20 | $80.00 | $65.13 | $75.00 |
| 175 | Field painting, misc.: (coating of beam ends) (514E27700) | SF | 184 | $200.00 | $250.00 | $195.00 |
| 176 | 2" preformed expansion joint filler (516E13900) | SF | 23 | $13.00 | $13.00 | $18.00 |
| 177 | Semi-integral abutment expansion joint seal (516E14020) | FT | 80 | $58.01 | $55.00 | $54.00 |
| 178 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44001) | EACH | 10 | $1,600.00 | $1,350.00 | $1,435.00 |
| 179 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $50,000 | $41,000 | $76,000 |
| 180 | Railing, misc.: (railing posts to BE RE-used) (517E76302) | EACH | 4 | $295.00 | $400.00 | $865.00 |
| 181 | Porous backfill with geotextile fabric (518E21200) | CY | 21 | $260.00 | $125.00 | $100.00 |
| 182 | Special - steel drip strip (518E22300) | FT | 204 | $16.00 | $26.00 | $18.00 |
| 183 | 6" perforated corrugated plastic pipe (518E40000) | FT | 75 | $10.00 | $23.00 | $12.00 |
| 184 | 6" non-perforated corrugated plastic pipe (518E40012) | FT | 40 | $10.00 | $22.00 | $18.00 |
| 185 | Patching concrete structure, as per plan (519E11101) | SF | 16 | $200.00 | $500.00 | $200.00 |
| 186 | Reinforced concrete approach slabs (T=13") (526E15000) | SY | 125 | $400.00 | $350.00 | $350.00 |
| 187 | Type A installation (526E90010) | FT | 60 | $275.00 | $170.00 | $275.00 |
| 188 | Superplasticized dense concrete overlay using hydrodemolition (848E10200) | SY | 275 | $165.00 | $146.04 | $115.00 |
| 189 | Surface preparation using hydrodemolition (848E20000) | SY | 275 | $125.00 | $116.12 | $120.00 |
| 190 | Superplasticized dense concrete overlay (variable thickness), material only (848E30200) | CY | 4 | $270.00 | $470.58 | $257.00 |
| 191 | Hand chipping (848E50000) | SY | 27 | $90.00 | $129.75 | $90.00 |
| 192 | Test slab (848E50100) | LS | 1 | $2,400.00 | $3,059.51 | $1,200.00 |
| 193 | Full-depth repair (848E50200) | CY | 1 | $1,600.00 | $1,072.45 | $1,800.00 |
| 194 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $38,000 | $90,206 | $40,000 |
| 195 | Field office, type B (619E16010) | MNTH | 3 | $6,000.00 | $5,335.32 | $7,500.00 |
| 196 | Construction layout stakes and surveying (623E10000) | LS | 1 | $24,973 | $16,000 | $90,000 |
| 197 | Mobilization (624E10000) | LS | 1 | $366,000 | $385,000 | $340,000 |
| 200 | Center line (644E00300) | MI | 0.01 | $8,000.00 | $2,140.00 | $2,140.00 |
| 201 | Edge line, 6" (646E10010) | MI | 0.35 | $35,000 | $23,665 | $23,665 |
| 202 | Lane line, 6" (646E10110) | MI | 0.15 | $23,000 | $8,270.00 | $8,270.00 |
| 203 | Center line (646E10200) | MI | 0.02 | $23,000 | $11,420 | $11,420 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of August 14, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.