ODOT contract 250383 bid tabulation
WAS-Beverly Sidewalk (SIDEWALK). Let by Ohio DOT on August 14, 2025, WAS. 8 bids received; low bid $325,921 by McVoyt Construction Company Inc, -12% against the engineer's estimate of $370,000.
- Owner
- Ohio DOT
- Letting
- 14 AUG 2025
- Pay items
- 28
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | McVoyt Construction Company Inc | $325,921 | Low | -12% |
| 2 | LMS Construction Inc | $335,834 | +3.0% | -9.0% |
| 3 | Shelly & Sands Inc | $353,598 | +8.0% | -4.0% |
| 4 | Alan Stone Co Inc | $373,951 | +15% | +1.0% |
| 5 | Axis Civil Construction LLC | $415,574 | +28% | +12% |
| 6 | Parker Corporation | $447,369 | +37% | +21% |
| 7 | Complete General Construction Company | $605,170 | +86% | +64% |
| 8 | Ohio-West Virginia Excavating Co | $687,186 | +111% | +86% |
Engineer's estimate: $370,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. McVoyt Construction Company Inc | 2. LMS Construction Inc | 3. Shelly & Sands Inc | 4. Alan Stone Co Inc | 5. Axis Civil Construction LLC | 6. Parker Corporation |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $1,500.00 | $400.00 | $4,088.00 | $5,000.00 | $2,500.00 | $5,000.00 |
| 2 | Pavement removed (202E23000) | SY | 961 | $13.50 | $10.00 | $21.00 | $20.00 | $15.00 | $15.00 |
| 3 | Walk removed (202E30000) | SF | 8,517 | $4.50 | $1.50 | $3.85 | $3.00 | $3.90 | $3.00 |
| 4 | Removal misc.:brick pavers (202E98400) | SF | 1,150 | $7.00 | $2.50 | $3.75 | $4.50 | $4.00 | $6.00 |
| 5 | Subgrade compaction (204E10000) | SY | 2,331 | $6.00 | $3.50 | $2.00 | $7.00 | $2.50 | $2.00 |
| 6 | Aggregate base (304E20000) | CY | 35 | $186.00 | $65.00 | $175.00 | $120.00 | $230.00 | $100.00 |
| 7 | 4" concrete walk (608E10000) | SF | 14,173 | $7.25 | $9.00 | $6.30 | $7.50 | $8.90 | $11.00 |
| 8 | Curb ramp (608E52000) | SF | 600 | $18.00 | $36.00 | $43.00 | $35.00 | $34.00 | $22.00 |
| 9 | Detectable warning (608E53020) | SF | 169 | $24.00 | $30.00 | $58.00 | $20.00 | $45.00 | $40.00 |
| 10 | Excavation (203E10000) | CY | 134 | $60.00 | $50.00 | $57.00 | $75.00 | $95.00 | $20.00 |
| 11 | Embankment (203E20000) | CY | 63 | $85.00 | $50.00 | $28.00 | $120.00 | $95.00 | $20.00 |
| 12 | Seeding and mulching, class 1 (659E00500) | SY | 1,529 | $2.36 | $1.50 | $5.00 | $2.00 | $2.25 | $3.00 |
| 13 | Repair seeding and mulching (659E14000) | SY | 77 | $2.40 | $1.00 | $1.00 | $4.00 | $2.25 | $13.00 |
| 14 | Commercial fertilizer (659E20000) | TON | 0.20 | $1,500.00 | $2,000.00 | $965.00 | $660.00 | $1,250.00 | $5,000.00 |
| 15 | Water (659E35000) | MGAL | 8 | $1.00 | $10.00 | $1.10 | $120.00 | $1.00 | $10.00 |
| 16 | Erosion control (832E30000) | EACH | 2,500 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 17 | 6" non-reinforced concrete pavement, class QC 1P (452E10010) | SY | 609 | $66.00 | $105.00 | $103.00 | $80.00 | $115.00 | $140.00 |
| 18 | 8" non-reinforced concrete pavement, class QC 1P (452E12010) | SY | 136 | $122.00 | $118.00 | $112.00 | $140.00 | $130.00 | $145.00 |
| 19 | Curb, type 6 (609E26000) | FT | 200 | $72.50 | $35.00 | $75.00 | $55.00 | $55.00 | $50.00 |
| 20 | Valve box removed (202E75610) | EACH | 1 | $1,100.00 | $400.00 | $390.00 | $250.00 | $300.00 | $500.00 |
| 21 | Valve box adjusted to grade (638E10800) | EACH | 10 | $220.00 | $400.00 | $520.00 | $250.00 | $300.00 | $700.00 |
| 22 | Removal of ground mounted sign and reerection (630E85100) | EACH | 8 | $150.00 | $150.00 | $55.00 | $100.00 | $300.00 | $100.00 |
| 23 | Crosswalk line, 12", type 1 (642E00620) | FT | 526 | $7.00 | $6.50 | $7.00 | $7.00 | $6.50 | $15.00 |
| 24 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $8,200.00 | $12,000 | $1,960.00 | $4,500.00 | $4,000.00 | $6,100.00 |
| 25 | Special - gas valve box adjusted to grade (611E99700) | EACH | 3 | $267.00 | $600.00 | $530.00 | $250.00 | $300.00 | $700.00 |
| 26 | Maintaining traffic (614E11000) | LS | 1 | $6,000.00 | $5,000.00 | $19,000 | $21,000 | $25,000 | $27,000 |
| 27 | Construction layout stakes and surveying (623E10000) | LS | 1 | $2,500.00 | $500.00 | $1,500.00 | $11,000 | $10,000 | $20,000 |
| 28 | Mobilization (624E10000) | LS | 1 | $10,000 | $15,000 | $10,000 | $20,000 | $20,000 | $12,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of August 14, 2025. Compiled by Mirage Metrics.