ODOT contract 250417 bid tabulation
SEN-SR 19/SR 228/SR 590-06.07/00.00/00.00 (TWO LANE RESURFACING). Let by Ohio DOT on September 11, 2025, SEN. 4 bids received; low bid $2,296,034 by M & B Asphalt Co Inc, -8.6% against the engineer's estimate of $2,511,000.
- Owner
- Ohio DOT
- Letting
- 11 SEP 2025
- Pay items
- 58
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | M & B Asphalt Co Inc | $2,296,034 | Low | -9.0% |
| 2 | Kokosing Construction Company Inc | $2,484,725 | +8.0% | -1.0% |
| 3 | Gerken Paving Inc | $2,494,741 | +9.0% | -1.0% |
| 4 | Erie Blacktop Inc | $2,640,223 | +15% | +5.0% |
Engineer's estimate: $2,511,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. M & B Asphalt Co Inc | 2. Kokosing Construction Company Inc | 3. Gerken Paving Inc | 4. Erie Blacktop Inc |
|---|---|---|---|---|---|---|---|
| 1 | Guardrail removed (202E38000) | FT | 397 | $2.00 | $2.00 | $2.00 | $2.10 |
| 2 | Anchor assembly removed, type A (202E42000) | EACH | 4 | $295.00 | $295.00 | $295.00 | $305.00 |
| 3 | Embankment (203E20000) | CY | 40 | $73.50 | $73.50 | $73.50 | $77.00 |
| 4 | Reshaping under guardrail (209E15000) | STA | 5 | $50.00 | $50.00 | $50.00 | $52.50 |
| 5 | Linear grading (209E60500) | MI | 9.10 | $1,200.00 | $2,500.00 | $3,400.00 | $1,900.00 |
| 6 | Preparing subgrade for shoulder paving (209E72050) | MI | 8.60 | $700.00 | $300.00 | $350.00 | $1,900.00 |
| 7 | Guardrail, type MGS (606E15050) | FT | 275 | $22.80 | $22.80 | $22.80 | $23.90 |
| 8 | Guardrail, type MGS with long posts (606E15100) | FT | 12.50 | $35.60 | $35.60 | $35.69 | $37.30 |
| 9 | Guardrail, type MGS, long-span (606E17360) | FT | 50 | $29.20 | $29.20 | $29.20 | $30.50 |
| 10 | Anchor assembly, MGS type E, MASH 2016 (606E26150) | EACH | 3 | $2,920.00 | $2,920.00 | $2,920.00 | $3,066.00 |
| 11 | Anchor assembly, MGS type T (606E26550) | EACH | 2 | $1,465.00 | $1,465.00 | $1,465.00 | $1,540.00 |
| 12 | Detectable warning (608E53020) | SF | 16 | $65.00 | $62.50 | $225.00 | $65.50 |
| 13 | Monument assembly adjusted to grade (623E39500) | EACH | 1 | $900.00 | $2,500.00 | $800.00 | $645.00 |
| 14 | Crushed aggregate slope protection (601E20010) | CY | 15 | $110.00 | $220.00 | $220.00 | $105.00 |
| 15 | Seeding and mulching (659E10000) | SY | 289.70 | $7.00 | $7.00 | $7.00 | $7.35 |
| 16 | Commercial fertilizer (659E20000) | TON | 0.04 | $520.00 | $520.00 | $520.00 | $546.00 |
| 17 | Water (659E35000) | MGAL | 2 | $0.65 | $0.65 | $0.65 | $0.70 |
| 18 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 19 | Catch basin adjusted to grade (611E98630) | EACH | 4 | $1,000.00 | $949.95 | $1,050.00 | $997.00 |
| 20 | Manhole adjusted to grade (611E99654) | EACH | 4 | $1,000.00 | $744.95 | $1,050.00 | $782.00 |
| 21 | Valve box adjusted to grade (638E10800) | EACH | 1 | $650.00 | $629.95 | $500.00 | $660.00 |
| 22 | Pavement repair (253E02000) | CY | 2,709 | $196.00 | $235.00 | $202.00 | $202.00 |
| 23 | Pavement planing, asphalt concrete, 3" (254E01000) | SY | 72,784 | $2.50 | $1.75 | $3.55 | $3.15 |
| 24 | Tack coat (407E10000) | GAL | 10,334 | $2.50 | $2.90 | $2.50 | $2.50 |
| 25 | Fine graded polymer asphalt concrete, type B, (448), as per plan (424E14001) | CY | 2,122 | $250.00 | $245.00 | $236.00 | $295.00 |
| 26 | Asphalt concrete intermediate course, type 2, (448) (441E50300) | CY | 4,044 | $165.00 | $175.00 | $174.00 | $177.00 |
| 27 | Compacted aggregate (617E10100) | CY | 928 | $70.00 | $30.00 | $72.00 | $81.00 |
| 28 | Rumble stripes, center line (asphalt concrete) (618E43000) | MI | 2.30 | $3,000.00 | $3,000.00 | $3,000.00 | $4,575.00 |
| 29 | Longitudinal joint preparation (874E20000) | FT | 11,953 | $1.20 | $0.80 | $1.95 | $2.10 |
| 30 | Longitudinal joint adhesive (875E10000) | LB | 2,277 | $0.50 | $0.61 | $3.00 | $1.95 |
| 31 | RPM (621E00100) | EACH | 327 | $50.00 | $37.00 | $49.50 | $51.75 |
| 32 | Raised pavement marker removed (621E54000) | EACH | 147 | $5.00 | $2.00 | $6.00 | $13.00 |
| 33 | Barrier reflector, type 5, bidiriectional (626E00116) | EACH | 10 | $14.60 | $14.60 | $14.60 | $15.25 |
| 34 | Ground mounted support, no. 3 post (630E03100) | FT | 68 | $20.00 | $20.00 | $20.00 | $21.00 |
| 35 | Sign, flat sheet (630E80100) | SF | 13 | $25.00 | $25.00 | $25.00 | $26.25 |
| 36 | Removal of ground mounted sign and disposal (630E84900) | EACH | 5 | $10.00 | $10.00 | $10.00 | $10.50 |
| 37 | Removal of ground mounted post support and disposal (630E86002) | EACH | 5 | $15.00 | $15.00 | $15.00 | $15.75 |
| 38 | Edge line, 6", type 1 (642E00104) | MI | 9.50 | $900.00 | $830.00 | $900.00 | $997.00 |
| 39 | Center line, type 1 (642E00300) | MI | 5 | $1,200.00 | $1,152.00 | $1,200.00 | $1,415.00 |
| 40 | Stop line (644E00500) | FT | 88 | $20.00 | $12.00 | $20.00 | $10.50 |
| 41 | Crosswalk line, 24" (644E00630) | FT | 42 | $20.00 | $18.00 | $20.00 | $10.50 |
| 42 | Work zone marking sign (614E12460) | EACH | 19 | $130.00 | $70.00 | $125.00 | $78.75 |
| 43 | Replacement sign (614E12500) | EACH | 5 | $80.00 | $200.00 | $125.00 | $200.00 |
| 44 | Replacement drum (614E12600) | EACH | 5 | $50.00 | $60.00 | $55.00 | $59.00 |
| 45 | Work zone center line, class I (614E21000) | MI | 10 | $900.00 | $1,175.00 | $1,200.00 | $1,415.00 |
| 46 | Work zone center line, class III, 642 paint (614E21550) | MI | 5 | $900.00 | $1,175.00 | $1,200.00 | $1,415.00 |
| 47 | Work zone stop line, class I (614E26000) | FT | 176 | $4.00 | $2.00 | $4.00 | $3.15 |
| 48 | Work zone stop line, class III, 642 paint (614E26610) | FT | 88 | $4.00 | $2.00 | $4.00 | $3.15 |
| 49 | Pavement planing, asphalt concrete, 1" (254E01000) | SY | 522 | $1.60 | $1.75 | $1.90 | $13.00 |
| 50 | Special - sawing and sealing bituminous concrete joints (516E31200) | FT | 204 | $26.00 | $25.86 | $25.86 | $27.15 |
| 51 | Pavement planing, asphalt concrete, 1" (254E01000) | SY | 386 | $2.60 | $1.75 | $2.50 | $13.00 |
| 52 | Special - sawing and sealing bituminous concrete joints (516E31200) | FT | 136 | $26.00 | $25.86 | $25.86 | $27.15 |
| 53 | Pavement planing, asphalt concrete, 1" (254E01000) | SY | 776 | $2.00 | $1.75 | $1.50 | $13.00 |
| 54 | Special - sawing and sealing bituminous concrete joints (516E31200) | FT | 166 | $26.00 | $25.86 | $25.86 | $27.15 |
| 55 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $11,500 | $11,000 | $11,000 | $10,000 |
| 56 | Maintaining traffic (614E11000) | LS | 1 | $25,000 | $146,248 | $106,500 | $65,000 |
| 57 | Construction layout stakes and surveying (623E10000) | LS | 1 | $4,000.00 | $2,000.00 | $5,160.00 | $3,550.00 |
| 58 | Mobilization (624E10000) | LS | 1 | $100,000 | $120,000 | $75,000 | $125,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of September 11, 2025. Compiled by Mirage Metrics.