ODOT contract 250539 bid tabulation
D02-SIGN FY2026 (SIGNING). Let by Ohio DOT on November 13, 2025, District 2. 1 bid received; low bid $2,353,525 by Lake Erie Construction Company, -14% against the engineer's estimate of $2,724,000.
- Owner
- Ohio DOT
- Letting
- 13 NOV 2025
- Pay items
- 75
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Lake Erie Construction Company | $2,353,525 | Low | -14% |
Engineer's estimate: $2,724,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Lake Erie Construction Company |
|---|---|---|---|---|
| 1 | Guardrail removed (202E38000) | FT | 112.50 | $3.60 |
| 2 | Anchor assembly removed, type A (202E42000) | EACH | 1 | $345.00 |
| 3 | Anchor assembly removed, type E (202E42010) | EACH | 4 | $150.00 |
| 4 | Anchor assembly removed, type T (202E42040) | EACH | 3 | $95.00 |
| 5 | Impact attenuator removed (202E47800) | EACH | 1 | $320.00 |
| 6 | Reshaping under guardrail (209E15050) | MI | 0.52 | $3,600.00 |
| 7 | Guardrail, type MGS (606E15050) | FT | 1,937.50 | $20.40 |
| 8 | Guardrail, barrier design, type MGS (606E15550) | FT | 37.50 | $39.60 |
| 9 | Anchor assembly, MGS type E, MASH 2016 (606E26150) | EACH | 8 | $2,840.00 |
| 10 | Anchor assembly, MGS type T (606E26550) | EACH | 16 | $1,380.00 |
| 11 | Impact attenuator, type 1 (bidirectional) (606E60012) | EACH | 1 | $9,320.00 |
| 12 | Law enforcement officer with patrol car for assistance, as per plan (614E11111) | HR | 200 | $85.00 |
| 13 | Portable changeable message sign, as per plan (614E18601) | SNMT | 9 | $850.00 |
| 14 | Barrier reflector, type 5, bidirectional (626E00116) | EACH | 54 | $15.00 |
| 15 | Topsoil (659E00300) | CY | 134 | $50.00 |
| 16 | Seeding and mulching (659E10000) | SY | 1,211 | $2.40 |
| 17 | Repair seeding and mulching (659E14000) | SY | 61 | $0.85 |
| 18 | Inter-seeding (659E15000) | SY | 61 | $0.15 |
| 19 | Commercial fertilizer (659E20000) | TON | 0.16 | $500.00 |
| 20 | Water (659E35000) | MGAL | 7 | $1.00 |
| 21 | Ground rod (625E32000) | EACH | 29 | $345.00 |
| 22 | Ground mounted support, no. 3 post, as per plan (630E03101) | FT | 485.10 | $15.00 |
| 23 | Ground mounted structural beam support, W8X18 (630E07000) | FT | 296.60 | $50.00 |
| 24 | Ground mounted structural beam support, W10X22 (630E07500) | FT | 191.30 | $60.00 |
| 25 | Ground mounted structural beam support, W10X12 (630E07600) | FT | 129 | $40.00 |
| 26 | Ground mounted structural beam support, W12X30 (630E08000) | FT | 980.10 | $75.00 |
| 27 | Sign post reflector, as per plan (630E08601) | EACH | 20 | $45.00 |
| 28 | Sign post reflector, as per plan (630E08601) | EACH | 6 | $45.00 |
| 29 | Breakaway structural beam connection (630E09000) | EACH | 61 | $945.00 |
| 30 | Overhead sign support, type TC-12.31, design 6 (630E72320) | EACH | 13 | $26,250 |
| 31 | Overhead sign support, type TC-12.31, design 10 (630E72330) | EACH | 1 | $37,850 |
| 32 | Overhead sign support, type TC-12.31, design 12 (630E72340) | EACH | 1 | $44,250 |
| 33 | Overhead sign support, type TC-15.116, design 1 (630E72410) | EACH | 5 | $62,600 |
| 34 | Overhead sign support, type TC-15.116, design 2 (630E72420) | EACH | 1 | $83,400 |
| 35 | Overhead sign support, type TC-15.116, design 3 (630E72430) | EACH | 1 | $141,500 |
| 36 | Sign attachment assembly (630E75000) | EACH | 25 | $725.00 |
| 37 | Sign, flat sheet (630E80100) | SF | 726.30 | $15.00 |
| 38 | Sign, ground mounted extrusheet (630E80200) | SF | 5,934 | $22.00 |
| 39 | Sign, overhead extrusheet (630E80224) | SF | 6,122.50 | $23.00 |
| 40 | Sign, temporary overlay (630E80300) | SF | 70 | $21.00 |
| 41 | Sign erected, flat sheet (630E81100) | SF | 656.30 | $5.00 |
| 42 | Sign erected, extrusheet (630E81200) | SF | 12,056.50 | $6.00 |
| 43 | Ground mounted structural beam support foundation (630E84500) | EACH | 61 | $750.00 |
| 44 | Ground mounted structural beam support foundation, as per plan (630E84501) | EACH | 109 | $475.00 |
| 45 | Rigid overhead sign support foundation (630E84510) | EACH | 20 | $8,350.00 |
| 46 | Rigid overhead sign support foundation, as per plan (630E84511) | EACH | 1 | $28,400 |
| 47 | Rigid overhead sign support foundation, as per plan (630E84511) | EACH | 1 | $6,850.00 |
| 48 | Rigid overhead sign support foundation, as per plan (630E84511) | EACH | 1 | $6,850.00 |
| 49 | Rigid overhead sign support foundation, as per plan (630E84511) | EACH | 1 | $14,750 |
| 50 | Rigid overhead sign support foundation, as per plan (630E84511) | EACH | 1 | $11,800 |
| 51 | Rigid overhead sign support foundation, as per plan (630E84511) | EACH | 1 | $11,800 |
| 52 | Rigid overhead sign support foundation, as per plan (630E84511) | EACH | 1 | $14,750 |
| 53 | Rigid overhead sign support foundation, as per plan (630E84511) | EACH | 1 | $13,650 |
| 54 | Rigid overhead sign support foundation, as per plan (630E84511) | EACH | 1 | $13,650 |
| 55 | Removal of ground mounted sign and disposal (630E84900) | EACH | 174 | $8.00 |
| 56 | Removal of ground mounted sign and reerection (630E85100) | EACH | 6 | $65.00 |
| 57 | Removal of ground mounted sign and delivery, as per plan (630E85201) | EACH | 2 | $85.00 |
| 58 | Removal of ground mounted major sign and disposal (630E85400) | EACH | 51 | $165.00 |
| 59 | Removal of ground mounted major sign and reerection (630E85600) | EACH | 3 | $340.00 |
| 60 | Removal of ground mounted post support and disposal, as per plan (630E86003) | EACH | 82 | $15.00 |
| 61 | Removal of ground mounted structural beam support (630E86102) | EACH | 144 | $235.00 |
| 62 | Removal of structure mounted sign and disposal (630E86310) | EACH | 2 | $750.00 |
| 63 | Removal of overhead mounted sign and reerection (630E87100) | EACH | 3 | $430.00 |
| 64 | Removal of overhead mounted sign and disposal (630E87400) | EACH | 49 | $65.00 |
| 65 | Removal of overhead sign support and disposal (630E89702) | EACH | 13 | $1,350.00 |
| 66 | Signing, misc.:sign support assembly, pole mounted (630E97700) | EACH | 17 | $225.00 |
| 67 | Signing, misc.:4"X6" wood post, as per plan (630E97900) | FT | 194 | $30.00 |
| 68 | Signing, misc.:6"X8" wood post, as per plan (630E97900) | FT | 1,887.30 | $45.00 |
| 69 | Removal of luminaire (631E94250) | EACH | 6 | $100.00 |
| 70 | Removal of signs wired (631E94406) | EACH | 3 | $395.00 |
| 71 | Sign lighting misc.: removal of sign service and D (631E97700) | EACH | 1 | $1,480.00 |
| 72 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $12,500 |
| 73 | Maintaining traffic (614E11000) | LS | 1 | $68,975 |
| 74 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $8,250.00 |
| 75 | Mobilization (624E10000) | LS | 1 | $55,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of November 13, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.