ODOT contract 250560 bid tabulation
LAK-E 305th St. Resurface (FOUR LANE RESURFACING). Let by Ohio DOT on December 4, 2025, LAK. 5 bids received; low bid $2,655,150 by Great Lakes Crushing LTD, -3.6% against the engineer's estimate of $2,753,000.
- Owner
- Ohio DOT
- Letting
- 04 DEC 2025
- Pay items
- 66
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Great Lakes Crushing LTD | $2,655,150 | Low | -4.0% |
| 2 | C A Agresta Construction Co | $2,740,440 | +3.0% | 0.0% |
| 3 | Perk Company Inc | $2,742,151 | +3.0% | 0.0% |
| 4 | Geauga Highway Co | $2,923,408 | +10% | +6.0% |
| 5 | Ronyak Paving Inc | $3,213,926 | +21% | +17% |
Engineer's estimate: $2,753,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Great Lakes Crushing LTD | 2. C A Agresta Construction Co | 3. Perk Company Inc | 4. Geauga Highway Co | 5. Ronyak Paving Inc |
|---|---|---|---|---|---|---|---|---|
| 1 | Pavement removed, as per plan (202E23001) | SY | 1,624 | $20.00 | $15.00 | $21.00 | $22.50 | $25.00 |
| 2 | Walk removed, as per plan (202E30001) | SF | 6,643 | $3.00 | $3.00 | $2.50 | $2.35 | $8.00 |
| 3 | Curb removed, as per plan (202E32001) | FT | 3,582 | $5.00 | $18.00 | $2.50 | $14.00 | $12.00 |
| 4 | Excavation (203E10000) | CY | 501 | $35.00 | $35.00 | $1.00 | $60.00 | $45.00 |
| 5 | Subgrade compaction (204E10000) | SY | 1,783 | $2.00 | $2.00 | $2.00 | $2.50 | $2.00 |
| 6 | 4" concrete walk, as per plan (608E10001) | SF | 2,696 | $14.00 | $12.00 | $17.00 | $7.00 | $14.00 |
| 7 | Curb ramp, as per plan (608E52001) | SF | 4,648 | $18.00 | $26.00 | $38.75 | $22.50 | $40.00 |
| 8 | Topsoil (659E00300) | CY | 200 | $40.00 | $50.00 | $70.00 | $65.00 | $85.00 |
| 9 | Seeding and mulching, class 1 (659E00500) | SY | 1,810 | $5.00 | $10.00 | $8.50 | $4.50 | $10.00 |
| 10 | Water (659E35000) | MGAL | 10 | $100.00 | $20.00 | $100.00 | $1.00 | $10.00 |
| 11 | Erosion control (832E30000) | EACH | 25,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 12 | Catch basin adjusted to grade, as per plan (611E98631) | EACH | 80 | $1,200.00 | $1,600.00 | $1,500.00 | $1,200.00 | $1,525.00 |
| 13 | Catch basin reconstructed to grade, as per plan (611E98635) | EACH | 5 | $1,500.00 | $2,000.00 | $1,750.00 | $1,800.00 | $1,775.00 |
| 14 | Manhole adjusted to grade, as per plan (611E99655) | EACH | 42 | $1,200.00 | $1,000.00 | $1,500.00 | $1,200.00 | $1,000.00 |
| 15 | Special - miscellaneous metal (611E99820) | LB | 16,000 | $2.00 | $2.00 | $5.00 | $2.50 | $4.00 |
| 16 | Pavement planing, asphalt concrete, T=3" (254E01000) | SY | 1,626 | $8.00 | $6.00 | $7.45 | $7.00 | $8.00 |
| 17 | Pavement planing, portland cement concrete, T=3" (254E01010) | SY | 3,426 | $10.00 | $8.00 | $4.25 | $9.00 | $15.00 |
| 18 | Patching planed surface (254E01600) | SY | 70 | $50.00 | $30.00 | $1.00 | $1.00 | $30.00 |
| 19 | Full depth pavement removal and rigid replacement, type 2, class QC MS, as per plan (255E16001) | SY | 750 | $150.00 | $180.00 | $255.00 | $140.00 | $225.00 |
| 20 | Full depth pavement removal and rigid replacement, type 2, class QC MS, as per plan (255E16001) | SY | 750 | $150.00 | $165.00 | $165.00 | $130.00 | $200.00 |
| 21 | Full depth pavement sawing (255E20000) | FT | 800 | $7.50 | $3.00 | $10.00 | $4.00 | $4.00 |
| 22 | Aggregate base (304E20000) | CY | 575 | $85.00 | $75.00 | $25.00 | $85.00 | $65.00 |
| 23 | Tack coat, 702.13 (407E13900) | GAL | 2,096 | $5.00 | $3.40 | $3.89 | $3.00 | $2.00 |
| 24 | Non-tracking tack coat (407E20000) | GAL | 3,134 | $5.00 | $3.40 | $3.89 | $3.00 | $2.00 |
| 25 | Asphalt concrete surface course, type 1, (448), as per plan (441E50101) | CY | 1,220 | $250.00 | $220.00 | $221.00 | $245.00 | $270.00 |
| 26 | Asphalt concrete intermediate course, type 2, (448) (441E50300) | CY | 1,705 | $225.00 | $200.00 | $201.60 | $225.00 | $225.00 |
| 27 | 6" non-reinforced concrete pavement, class QC MS, as per plan (452E10051) | SY | 1,621 | $135.00 | $120.00 | $130.00 | $110.00 | $123.00 |
| 28 | 8" non-reinforced concrete pavement, class QC MS, as per plan (452E12051) | SY | 163 | $150.00 | $135.00 | $145.00 | $125.00 | $160.00 |
| 29 | Combination curb and gutter, type 2, as per plan (609E12001) | FT | 3,172 | $35.00 | $65.00 | $76.00 | $40.00 | $85.00 |
| 30 | Special - pavement reinforcing fabric (690E12030) | SY | 34,648 | $6.00 | $5.55 | $5.55 | $6.25 | $5.55 |
| 31 | Void reducing asphalt membrane (vram) (872E10000) | FT | 8,135 | $3.50 | $2.50 | $2.50 | $3.00 | $3.30 |
| 32 | Valve box adjusted to grade, as per plan (638E10801) | EACH | 42 | $800.00 | $800.00 | $1,100.00 | $850.00 | $1,000.00 |
| 33 | Service box adjusted to grade, as per plan (638E10901) | EACH | 5 | $1,000.00 | $300.00 | $10.00 | $850.00 | $850.00 |
| 34 | Manhole adjusted to grade, as per plan (611E99655) | EACH | 40 | $1,200.00 | $1,200.00 | $1,500.00 | $1,200.00 | $1,100.00 |
| 35 | Manhole reconstructed to grade, as per plan (611E99661) | EACH | 5 | $1,500.00 | $1,500.00 | $1,750.00 | $1,800.00 | $1,875.00 |
| 36 | Lane line, 4" (644E00200) | MI | 0.66 | $3,500.00 | $3,500.00 | $3,500.00 | $3,500.00 | $2,750.00 |
| 37 | Center line (644E00300) | MI | 2.33 | $6,600.00 | $7,500.00 | $7,500.00 | $7,500.00 | $5,500.00 |
| 38 | Channelizing line, 8" (644E00400) | FT | 607 | $2.50 | $1.25 | $1.25 | $1.25 | $2.25 |
| 39 | Stop line (644E00500) | FT | 576 | $9.00 | $10.00 | $10.00 | $10.00 | $7.50 |
| 40 | Crosswalk line, 12" (644E00620) | FT | 1,800 | $7.00 | $5.00 | $5.00 | $5.00 | $5.50 |
| 41 | Transverse/diagonal line (644E00700) | FT | 72 | $9.00 | $9.00 | $9.00 | $9.00 | $7.50 |
| 42 | School symbol marking, 72" (644E01100) | EACH | 2 | $800.00 | $850.00 | $850.00 | $850.00 | $650.00 |
| 43 | Lane arrow (644E01300) | EACH | 26 | $125.00 | $105.00 | $105.00 | $105.00 | $100.00 |
| 44 | Two way left turn arrow (644E01370) | EACH | 18 | $240.00 | $210.00 | $210.00 | $210.00 | $200.00 |
| 45 | Crosswalk line, 12", type A125 (647E20026) | FT | 1,047 | $15.00 | $13.00 | $13.00 | $13.00 | $12.50 |
| 46 | Crosswalk line, 24", type A125 (647E20076) | FT | 686 | $21.00 | $25.00 | $25.00 | $25.00 | $17.50 |
| 47 | Pull box, misc.:pull box removed and replaced to G (625E31600) | EACH | 2 | $500.00 | $1,100.00 | $1,100.00 | $1,100.00 | $1,800.00 |
| 48 | Detector loop, as per plan (632E26501) | EACH | 13 | $4,500.00 | $1,550.00 | $1,550.00 | $1,550.00 | $1,550.00 |
| 49 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 40 | $125.00 | $90.00 | $115.00 | $95.00 | $125.00 |
| 50 | Detour signing, as per plan (614E12421) | LS | 1 | $30,000 | $31,450 | $22,300 | $31,450 | $25,000 |
| 51 | Replacement sign (614E12500) | EACH | 5 | $200.00 | $200.00 | $200.00 | $200.00 | $150.00 |
| 52 | Asphalt concrete for maintaining traffic, as per plan (614E13001) | CY | 200 | $200.00 | $200.00 | $50.00 | $110.00 | $100.00 |
| 53 | Portable changeable message sign, as per plan (614E18601) | SNMT | 12 | $1,100.00 | $900.00 | $950.00 | $900.00 | $900.00 |
| 54 | Work zone lane line, class I, 4", 642 paint (614E20100) | MI | 0.66 | $800.00 | $900.00 | $900.00 | $900.00 | $650.00 |
| 55 | Work zone lane line, class III, 4", 642 paint (614E20550) | MI | 0.66 | $800.00 | $900.00 | $900.00 | $900.00 | $650.00 |
| 56 | Work zone center line, class I, 642 paint (614E21100) | MI | 2.33 | $1,800.00 | $1,800.00 | $1,800.00 | $1,800.00 | $1,500.00 |
| 57 | Work zone center line, class III, 642 paint (614E21550) | MI | 2.33 | $1,800.00 | $1,500.00 | $1,500.00 | $1,500.00 | $1,500.00 |
| 58 | Work zone channelizing line, class I, 8", 642 paint (614E23200) | FT | 607 | $1.00 | $1.00 | $0.95 | $0.95 | $0.75 |
| 59 | Work zone channelizing line, class III, 8", 642 paint (614E23680) | FT | 607 | $1.00 | $1.00 | $0.95 | $0.95 | $0.75 |
| 60 | Work zone stop line, class I, 642 paint (614E26200) | FT | 576 | $6.00 | $5.00 | $5.00 | $5.00 | $4.50 |
| 61 | Work zone stop line, class III, 642 paint (614E26610) | FT | 576 | $6.00 | $5.00 | $5.00 | $5.00 | $4.50 |
| 62 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $60,000 | $30,000 | $27,370 | $25,000 | $21,499 |
| 63 | Maintaining traffic, as per plan (614E11001) | LS | 1 | $50,000 | $162,000 | $60,825 | $518,325 | $179,100 |
| 64 | Field office, type B, as per plan (619E16011) | MNTH | 8 | $2,500.00 | $3,000.00 | $2,550.00 | $1,200.00 | $2,000.00 |
| 65 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $10,000 | $25,000 | $20,000 | $3,000.00 | $13,000 |
| 66 | Mobilization (624E10000) | LS | 1 | $100,000 | $54,440 | $33,500 | $25,000 | $175,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of December 4, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way