ODOT contract 250560 bid tabulation

LAK-E 305th St. Resurface (FOUR LANE RESURFACING). Let by Ohio DOT on December 4, 2025, LAK. 5 bids received; low bid $2,655,150 by Great Lakes Crushing LTD, -3.6% against the engineer's estimate of $2,753,000.

Owner
Ohio DOT
Letting
04 DEC 2025
Pay items
66
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Great Lakes Crushing LTD$2,655,150Low-4.0%
2C A Agresta Construction Co$2,740,440+3.0%0.0%
3Perk Company Inc$2,742,151+3.0%0.0%
4Geauga Highway Co$2,923,408+10%+6.0%
5Ronyak Paving Inc$3,213,926+21%+17%
ODOT contract 250560: bids by rank

Engineer's estimate: $2,753,000.

Bid tabulation

LinePay itemUnitQuantity1. Great Lakes Crushing LTD2. C A Agresta Construction Co3. Perk Company Inc4. Geauga Highway Co5. Ronyak Paving Inc
1Pavement removed, as per plan (202E23001)SY1,624$20.00$15.00$21.00$22.50$25.00
2Walk removed, as per plan (202E30001)SF6,643$3.00$3.00$2.50$2.35$8.00
3Curb removed, as per plan (202E32001)FT3,582$5.00$18.00$2.50$14.00$12.00
4Excavation (203E10000)CY501$35.00$35.00$1.00$60.00$45.00
5Subgrade compaction (204E10000)SY1,783$2.00$2.00$2.00$2.50$2.00
64" concrete walk, as per plan (608E10001)SF2,696$14.00$12.00$17.00$7.00$14.00
7Curb ramp, as per plan (608E52001)SF4,648$18.00$26.00$38.75$22.50$40.00
8Topsoil (659E00300)CY200$40.00$50.00$70.00$65.00$85.00
9Seeding and mulching, class 1 (659E00500)SY1,810$5.00$10.00$8.50$4.50$10.00
10Water (659E35000)MGAL10$100.00$20.00$100.00$1.00$10.00
11Erosion control (832E30000)EACH25,000$1.00$1.00$1.00$1.00$1.00
12Catch basin adjusted to grade, as per plan (611E98631)EACH80$1,200.00$1,600.00$1,500.00$1,200.00$1,525.00
13Catch basin reconstructed to grade, as per plan (611E98635)EACH5$1,500.00$2,000.00$1,750.00$1,800.00$1,775.00
14Manhole adjusted to grade, as per plan (611E99655)EACH42$1,200.00$1,000.00$1,500.00$1,200.00$1,000.00
15Special - miscellaneous metal (611E99820)LB16,000$2.00$2.00$5.00$2.50$4.00
16Pavement planing, asphalt concrete, T=3" (254E01000)SY1,626$8.00$6.00$7.45$7.00$8.00
17Pavement planing, portland cement concrete, T=3" (254E01010)SY3,426$10.00$8.00$4.25$9.00$15.00
18Patching planed surface (254E01600)SY70$50.00$30.00$1.00$1.00$30.00
19Full depth pavement removal and rigid replacement, type 2, class QC MS, as per plan (255E16001)SY750$150.00$180.00$255.00$140.00$225.00
20Full depth pavement removal and rigid replacement, type 2, class QC MS, as per plan (255E16001)SY750$150.00$165.00$165.00$130.00$200.00
21Full depth pavement sawing (255E20000)FT800$7.50$3.00$10.00$4.00$4.00
22Aggregate base (304E20000)CY575$85.00$75.00$25.00$85.00$65.00
23Tack coat, 702.13 (407E13900)GAL2,096$5.00$3.40$3.89$3.00$2.00
24Non-tracking tack coat (407E20000)GAL3,134$5.00$3.40$3.89$3.00$2.00
25Asphalt concrete surface course, type 1, (448), as per plan (441E50101)CY1,220$250.00$220.00$221.00$245.00$270.00
26Asphalt concrete intermediate course, type 2, (448) (441E50300)CY1,705$225.00$200.00$201.60$225.00$225.00
276" non-reinforced concrete pavement, class QC MS, as per plan (452E10051)SY1,621$135.00$120.00$130.00$110.00$123.00
288" non-reinforced concrete pavement, class QC MS, as per plan (452E12051)SY163$150.00$135.00$145.00$125.00$160.00
29Combination curb and gutter, type 2, as per plan (609E12001)FT3,172$35.00$65.00$76.00$40.00$85.00
30Special - pavement reinforcing fabric (690E12030)SY34,648$6.00$5.55$5.55$6.25$5.55
31Void reducing asphalt membrane (vram) (872E10000)FT8,135$3.50$2.50$2.50$3.00$3.30
32Valve box adjusted to grade, as per plan (638E10801)EACH42$800.00$800.00$1,100.00$850.00$1,000.00
33Service box adjusted to grade, as per plan (638E10901)EACH5$1,000.00$300.00$10.00$850.00$850.00
34Manhole adjusted to grade, as per plan (611E99655)EACH40$1,200.00$1,200.00$1,500.00$1,200.00$1,100.00
35Manhole reconstructed to grade, as per plan (611E99661)EACH5$1,500.00$1,500.00$1,750.00$1,800.00$1,875.00
36Lane line, 4" (644E00200)MI0.66$3,500.00$3,500.00$3,500.00$3,500.00$2,750.00
37Center line (644E00300)MI2.33$6,600.00$7,500.00$7,500.00$7,500.00$5,500.00
38Channelizing line, 8" (644E00400)FT607$2.50$1.25$1.25$1.25$2.25
39Stop line (644E00500)FT576$9.00$10.00$10.00$10.00$7.50
40Crosswalk line, 12" (644E00620)FT1,800$7.00$5.00$5.00$5.00$5.50
41Transverse/diagonal line (644E00700)FT72$9.00$9.00$9.00$9.00$7.50
42School symbol marking, 72" (644E01100)EACH2$800.00$850.00$850.00$850.00$650.00
43Lane arrow (644E01300)EACH26$125.00$105.00$105.00$105.00$100.00
44Two way left turn arrow (644E01370)EACH18$240.00$210.00$210.00$210.00$200.00
45Crosswalk line, 12", type A125 (647E20026)FT1,047$15.00$13.00$13.00$13.00$12.50
46Crosswalk line, 24", type A125 (647E20076)FT686$21.00$25.00$25.00$25.00$17.50
47Pull box, misc.:pull box removed and replaced to G (625E31600)EACH2$500.00$1,100.00$1,100.00$1,100.00$1,800.00
48Detector loop, as per plan (632E26501)EACH13$4,500.00$1,550.00$1,550.00$1,550.00$1,550.00
49Law enforcement officer with patrol car for assistance (614E11110)HR40$125.00$90.00$115.00$95.00$125.00
50Detour signing, as per plan (614E12421)LS1$30,000$31,450$22,300$31,450$25,000
51Replacement sign (614E12500)EACH5$200.00$200.00$200.00$200.00$150.00
52Asphalt concrete for maintaining traffic, as per plan (614E13001)CY200$200.00$200.00$50.00$110.00$100.00
53Portable changeable message sign, as per plan (614E18601)SNMT12$1,100.00$900.00$950.00$900.00$900.00
54Work zone lane line, class I, 4", 642 paint (614E20100)MI0.66$800.00$900.00$900.00$900.00$650.00
55Work zone lane line, class III, 4", 642 paint (614E20550)MI0.66$800.00$900.00$900.00$900.00$650.00
56Work zone center line, class I, 642 paint (614E21100)MI2.33$1,800.00$1,800.00$1,800.00$1,800.00$1,500.00
57Work zone center line, class III, 642 paint (614E21550)MI2.33$1,800.00$1,500.00$1,500.00$1,500.00$1,500.00
58Work zone channelizing line, class I, 8", 642 paint (614E23200)FT607$1.00$1.00$0.95$0.95$0.75
59Work zone channelizing line, class III, 8", 642 paint (614E23680)FT607$1.00$1.00$0.95$0.95$0.75
60Work zone stop line, class I, 642 paint (614E26200)FT576$6.00$5.00$5.00$5.00$4.50
61Work zone stop line, class III, 642 paint (614E26610)FT576$6.00$5.00$5.00$5.00$4.50
62Premium for contract performance bond and for payment bond (103E05000)LS1$60,000$30,000$27,370$25,000$21,499
63Maintaining traffic, as per plan (614E11001)LS1$50,000$162,000$60,825$518,325$179,100
64Field office, type B, as per plan (619E16011)MNTH8$2,500.00$3,000.00$2,550.00$1,200.00$2,000.00
65Construction layout stakes and surveying, as per plan (623E10001)LS1$10,000$25,000$20,000$3,000.00$13,000
66Mobilization (624E10000)LS1$100,000$54,440$33,500$25,000$175,000
ODOT contract 250560: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of December 4, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy