ODOT contract 254030 bid tabulation
GEA-US 322-05.76 Slope (SLIDE REPAIR). Let by Ohio DOT on December 4, 2025, GEA. 3 bids received; low bid $997,318 by Madex Construction Co, +41% against the engineer's estimate of $707,000.
- Owner
- Ohio DOT
- Letting
- 04 DEC 2025
- Pay items
- 54
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Madex Construction Co | $997,318 | Low | +41% |
| 2 | Shook Company LLC | $1,000,000 | 0.0% | +41% |
| 3 | Cook Paving & Construction Co Inc | $1,121,248 | +12% | +59% |
Engineer's estimate: $707,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Madex Construction Co | 2. Shook Company LLC | 3. Cook Paving & Construction Co Inc |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $40,675 | $47,829 | $50,000 |
| 2 | Pavement removed (202E23000) | SY | 445 | $41.68 | $15.00 | $55.00 |
| 3 | Curb removed (202E32000) | FT | 98 | $20.72 | $20.00 | $12.00 |
| 4 | Guardrail removed (202E38000) | FT | 598 | $9.79 | $3.00 | $2.00 |
| 5 | Excavation (203E10000) | CY | 1,478 | $33.25 | $35.00 | $55.00 |
| 6 | Embankment (203E20000) | CY | 2,907 | $37.53 | $50.00 | $40.00 |
| 7 | Subgrade compaction (204E10000) | SY | 767 | $4.63 | $2.00 | $5.00 |
| 8 | Ditch cleanout (209E10000) | FT | 20 | $80.07 | $25.00 | $30.00 |
| 9 | Guardrail, type MGS (606E15050) | FT | 625 | $28.32 | $30.00 | $22.00 |
| 10 | Anchor assembly, MGS type E, (MASH 2016) (606E26150) | EACH | 2 | $3,473.68 | $3,000.00 | $3,000.00 |
| 11 | Reference monument, type A (623E40500) | EACH | 1 | $1,736.84 | $1,500.00 | $800.00 |
| 12 | Right-of-way monument, type B (623E40520) | EACH | 7 | $868.42 | $1,500.00 | $1,000.00 |
| 13 | Ground rod (625E32000) | EACH | 1 | $70.53 | $150.00 | $400.00 |
| 14 | Rock channel protection, type C with filter (601E32200) | CY | 1.11 | $1,157.89 | $200.00 | $450.00 |
| 15 | Soil analysis test (659E00100) | EACH | 2 | $289.47 | $50.00 | $400.00 |
| 16 | Topsoil (659E00300) | CY | 371 | $75.63 | $45.00 | $48.00 |
| 17 | Seeding and mulching (659E10000) | SY | 3,338 | $4.63 | $3.00 | $1.15 |
| 18 | Repair seeding and mulching (659E14000) | SY | 167 | $2.32 | $1.00 | $2.00 |
| 19 | Inter-seeding (659E15000) | SY | 167 | $2.32 | $0.10 | $1.00 |
| 20 | Commercial fertilizer (659E20000) | TON | 0.46 | $1,157.89 | $1,000.00 | $1,200.00 |
| 21 | Lime (659E31000) | ACRE | 0.69 | $578.96 | $1,000.00 | $300.00 |
| 22 | Water (659E35000) | MGAL | 28 | $28.95 | $1.00 | $10.00 |
| 23 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 |
| 24 | Concrete masonry (602E20000) | CY | 0.20 | $4,795.25 | $5,000.00 | $3,000.00 |
| 25 | 6" shallow pipe underdrains (605E11100) | FT | 773 | $27.54 | $15.00 | $30.00 |
| 26 | 15" conduit, type B (611E05900) | FT | 76 | $127.33 | $125.00 | $95.00 |
| 27 | 15" conduit, type C (611E06100) | FT | 20 | $173.68 | $125.00 | $95.00 |
| 28 | Catch basin, no. 3A (611E98180) | EACH | 2 | $4,138.58 | $3,500.00 | $6,000.00 |
| 29 | Manhole, no. 3 (611E99574) | EACH | 1 | $6,947.37 | $7,000.00 | $5,000.00 |
| 30 | Aggregate base (304E20000) | CY | 320 | $97.66 | $100.00 | $115.00 |
| 31 | Crack sealing, type IV (423E00150) | LB | 1,300 | $11.58 | $7.50 | $6.00 |
| 32 | 9" non-reinforced concrete pavement, class QC 1P (452E13010) | SY | 637 | $133.68 | $135.00 | $120.00 |
| 33 | Curb, type 6 (609E26000) | FT | 780 | $66.84 | $50.00 | $50.00 |
| 34 | RPM (621E00100) | EACH | 16 | $202.63 | $135.00 | $200.00 |
| 35 | RPM (621E00100) | EACH | 11 | $202.63 | $135.00 | $200.00 |
| 36 | Removal of ground mounted sign and reerection (630E85100) | EACH | 2 | $347.37 | $100.00 | $100.00 |
| 37 | Wet reflective epoxy pavement marking, edge line, 6" (807E12010) | MI | 0.30 | $10,421 | $6,300.00 | $12,000 |
| 38 | Wet reflective epoxy pavement marking, center line (807E12200) | MI | 0.31 | $13,895 | $6,300.00 | $13,000 |
| 39 | Grooving for 4" recessed pavement marking, (asphalt) (850E10000) | MI | 0.31 | $9,263.16 | $6,500.00 | $4,000.00 |
| 40 | Grooving for 6" recessed pavement marking, (asphalt) (850E10010) | MI | 0.15 | $10,421 | $6,500.00 | $4,200.00 |
| 41 | Grooving for 6" recessed pavement marking, (concrete) (850E20010) | MI | 0.15 | $16,211 | $6,500.00 | $4,200.00 |
| 42 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 24 | $115.79 | $50.00 | $85.00 |
| 44 | Detour signing (614E12420) | LS | 1 | $16,579 | $7,722.43 | $15,000 |
| 47 | Portable changeable message sign, as per plan (614E18601) | SNMT | 6 | $1,621.05 | $1,231.01 | $1,000.00 |
| 48 | Water (616E10000) | MGAL | 18 | $17.37 | $1.00 | $55.00 |
| 50 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $290,632 | $275,000 | $350,000 |
| 51 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $28,842 | $45,000 | $10,000 |
| 52 | Maintaining traffic (614E11000) | LS | 1 | $11,113 | $10,000 | $35,000 |
| 53 | Field office, type B, as per plan (619E16011) | MNTH | 4 | $936.84 | $1,500.00 | $2,500.00 |
| 54 | Construction layout stakes and surveying (623E10000) | LS | 1 | $14,579 | $15,000 | $50,000 |
| 55 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $3,894.74 | $2,200.00 | $2,000.00 |
| 56 | Post construction survey monument verification and report (623E51000) | LS | 1 | $2,894.74 | $2,200.00 | $2,000.00 |
| 57 | Mobilization (624E10000) | LS | 1 | $41,004 | $75,000 | $65,000 |
| 100 | Signing, misc.:additional signs, ground mounted, A (630E97800) | SF | 300 | $2.00 | $28.72 | $37.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of December 4, 2025. Compiled by Mirage Metrics.