ODOT contract 258000 bid tabulation
UNI-SR 37-12.24 (BRIDGE REPAIR). Let by Ohio DOT on March 27, 2025, UNI. 4 bids received; low bid $2,006,941 by Shelly & Sands Inc, +1.4% against the engineer's estimate of $1,980,000.
- Owner
- Ohio DOT
- Letting
- 27 MAR 2025
- Pay items
- 96
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly & Sands Inc | $2,006,941 | Low | +1.0% |
| 2 | Double Z Construction Company | $2,243,833 | +12% | +13% |
| 3 | Complete General Construction Company | $2,250,449 | +12% | +14% |
| 4 | George J Igel & Co Inc | $2,433,242 | +21% | +23% |
Engineer's estimate: $1,980,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly & Sands Inc | 2. Double Z Construction Company | 3. Complete General Construction Company | 4. George J Igel & Co Inc |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $30,000 | $20,000 | $40,000 | $50,000 |
| 2 | Pavement removed, as per plan (202E23001) | SY | 414 | $30.00 | $25.00 | $25.00 | $20.00 |
| 3 | Walk removed, as per plan (202E30001) | SF | 256 | $4.00 | $5.00 | $15.00 | $13.00 |
| 4 | Curb removed (202E32000) | FT | 95 | $12.00 | $11.00 | $30.00 | $6.00 |
| 5 | Pipe removed, 24" and under (202E35100) | FT | 160 | $20.00 | $13.00 | $75.00 | $17.00 |
| 6 | Guardrail removed, as per plan (202E38001) | FT | 200 | $4.00 | $3.50 | $2.00 | $5.00 |
| 7 | Anchor assembly removed, type A, as per plan (202E42001) | EACH | 4 | $428.00 | $400.00 | $345.00 | $750.00 |
| 8 | Catch basin removed (202E58100) | EACH | 2 | $225.00 | $520.00 | $2,000.00 | $500.00 |
| 9 | Embankment, as per plan (203E20001) | CY | 59 | $40.00 | $50.00 | $30.00 | $16.00 |
| 10 | Subgrade compaction (204E10000) | SY | 710 | $7.00 | $8.00 | $8.00 | $6.00 |
| 11 | Linear grading (209E60200) | STA | 3 | $525.00 | $1,300.00 | $500.00 | $580.00 |
| 12 | Guardrail, type MGS with long posts (606E15100) | FT | 150 | $23.50 | $22.00 | $21.60 | $25.50 |
| 13 | Anchor assembly, MGS type A (606E25550) | EACH | 2 | $1,800.00 | $1,700.00 | $1,595.00 | $1,675.00 |
| 14 | MGS bridge terminal assembly, type TST-2, as per plan (606E34601) | EACH | 4 | $2,730.00 | $2,550.00 | $3,160.00 | $2,900.00 |
| 15 | 4" concrete walk, as per plan (608E10001) | SF | 98 | $35.00 | $25.00 | $25.00 | $15.00 |
| 16 | Curb ramp (608E52000) | SF | 101 | $50.00 | $30.00 | $30.50 | $42.00 |
| 17 | Rock channel protection, type B with filter (601E32100) | CY | 6 | $290.00 | $160.00 | $150.00 | $400.00 |
| 18 | Commercial fertilizer (654E11000) | TON | 0.24 | $1,500.00 | $1,780.00 | $5,000.00 | $1,411.25 |
| 19 | Topsoil (659E00300) | CY | 200 | $16.00 | $50.00 | $62.17 | $63.21 |
| 20 | Seeding and mulching (659E10000) | SY | 1,112 | $2.50 | $10.00 | $2.39 | $7.00 |
| 21 | Repair seeding and mulching (659E14000) | SY | 90 | $3.00 | $8.00 | $2.39 | $2.80 |
| 22 | Inter-seeding (659E15000) | SY | 90 | $3.00 | $8.00 | $2.39 | $2.80 |
| 23 | Lime (659E31000) | ACRE | 0.37 | $165.00 | $840.00 | $1,250.00 | $155.49 |
| 24 | Water (659E35000) | MGAL | 10 | $1.00 | $85.00 | $1.00 | $1.00 |
| 25 | Slope erosion protection (670E00500) | SY | 1,794 | $1.50 | $3.00 | $2.50 | $1.34 |
| 26 | Erosion control (832E30000) | EACH | 10,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 27 | Aggregate drains (605E31100) | FT | 24 | $40.00 | $25.00 | $50.00 | $100.00 |
| 28 | 4" conduit, type C (611E00200) | FT | 20 | $19.00 | $7.00 | $4.00 | $32.00 |
| 29 | 6" conduit, type C (611E01100) | FT | 20 | $19.00 | $8.00 | $6.00 | $50.00 |
| 30 | 8" conduit, type C (611E02000) | FT | 20 | $20.00 | $9.00 | $8.00 | $55.00 |
| 31 | 12" conduit, type B (611E04400) | FT | 162 | $118.00 | $110.00 | $175.00 | $170.00 |
| 32 | Catch basin, no. 3A (611E98180) | EACH | 2 | $4,000.00 | $4,000.00 | $5,000.00 | $4,000.00 |
| 33 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 59 | $290.00 | $305.00 | $305.00 | $425.00 |
| 34 | Aggregate base (304E20000) | CY | 15 | $120.00 | $175.00 | $150.00 | $160.00 |
| 35 | Aggregate base, as per plan (304E20001) | CY | 119 | $90.00 | $130.00 | $125.00 | $130.00 |
| 36 | Non-tracking tack coat (407E20000) | GAL | 47 | $4.00 | $4.00 | $4.00 | $7.00 |
| 37 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 36 | $260.00 | $350.00 | $350.00 | $570.00 |
| 38 | Curb, type 6 (609E26000) | FT | 60 | $62.00 | $45.00 | $52.00 | $45.00 |
| 39 | Water (617E25000) | MGAL | 1 | $73.00 | $275.00 | $100.00 | $62.00 |
| 40 | Barrier reflector, type 2, bidirectional (626E00110) | EACH | 8 | $12.00 | $12.00 | $11.50 | $11.00 |
| 41 | Removal of ground mounted sign and reerection (630E85100) | EACH | 5 | $100.00 | $100.00 | $215.00 | $100.00 |
| 42 | Edge line, 6", type 1 (642E00104) | MI | 0.13 | $3,300.00 | $27,000 | $3,300.00 | $3,300.00 |
| 43 | Center line, type 1 (642E00300) | MI | 0.32 | $3,300.00 | $1,255.00 | $3,300.00 | $3,300.00 |
| 44 | Detour signing (614E12420) | LS | 1 | $5,253.00 | $8,000.00 | $6,000.00 | $8,000.00 |
| 45 | Asphalt concrete for maintaining traffic (614E13000) | CY | 10 | $285.00 | $250.00 | $750.00 | $315.00 |
| 46 | Water (616E10000) | MGAL | 1 | $111.00 | $150.00 | $100.00 | $62.00 |
| 47 | Portions of structure removed (202E11200) | LS | 1 | $88,000 | $180,000 | $125,000 | $198,000 |
| 48 | Portions of structure removed, as per plan (202E11301) | CY | 14 | $2,100.00 | $925.00 | $1,300.00 | $1,200.00 |
| 49 | Approach slab removed (202E22900) | SY | 244 | $30.00 | $50.00 | $80.00 | $44.00 |
| 50 | Wearing course removed (202E23500) | SY | 983 | $0.72 | $13.00 | $5.00 | $20.00 |
| 51 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $125,000 | $180,000 | $85,000 | $90,000 |
| 52 | Unclassified excavation (503E21300) | LS | 1 | $8,199.00 | $18,000 | $35,000 | $20,000 |
| 53 | Steel piles HP12X53, furnished (507E00200) | FT | 315 | $33.00 | $50.00 | $45.00 | $50.00 |
| 54 | Steel piles HP12X53, driven (507E00250) | FT | 280 | $40.00 | $18.00 | $30.00 | $41.00 |
| 55 | Special - pile encasement (507E71200) | FT | 91 | $270.00 | $205.00 | $255.00 | $300.00 |
| 56 | Steel points or shoes (507E93300) | EACH | 7 | $140.00 | $140.00 | $138.00 | $200.00 |
| 57 | Galvanized steel reinforcement (509E26000) | LB | 29,481 | $2.00 | $2.00 | $2.00 | $2.10 |
| 58 | Dowel holes with nonshrink, nonmetallic grout (510E10000) | EACH | 168 | $30.00 | $26.00 | $20.00 | $40.00 |
| 59 | Class QC2 concrete with QC/QA, superstructure (511E31612) | CY | 154 | $1,000.00 | $845.00 | $1,100.00 | $1,200.00 |
| 60 | Class QC1 concrete, pier cap (511E42510) | CY | 18 | $2,100.00 | $2,500.00 | $2,250.00 | $1,700.00 |
| 61 | Class QC1 concrete, abutment (511E45710) | CY | 10 | $4,400.00 | $1,675.00 | $2,000.00 | $2,120.00 |
| 62 | Sealing of concrete surfaces (non-epoxy) (512E10050) | SY | 196 | $18.00 | $18.00 | $18.00 | $18.00 |
| 63 | Type A waterproofing (512E33300) | SY | 12 | $33.00 | $42.00 | $150.00 | $56.00 |
| 64 | Prestressed concrete composite box beam bridge members, level 1, CB27-48 (515E12070) | EACH | 22 | $19,000 | $22,000 | $22,000 | $27,000 |
| 65 | Preformed elastomeric compression joint seal (516E10000) | FT | 89 | $16.00 | $32.00 | $25.00 | $25.00 |
| 66 | Armorless preformed joint seal (516E10010) | FT | 89 | $85.00 | $60.00 | $85.00 | $70.00 |
| 67 | 1" preformed expansion joint filler (516E13600) | SF | 18 | $8.00 | $17.00 | $20.00 | $13.00 |
| 68 | 2" preformed expansion joint filler (516E13900) | SF | 89 | $9.00 | $18.00 | $20.00 | $14.00 |
| 69 | Semi-integral abutment expansion joint seal (516E14020) | FT | 95 | $48.00 | $30.00 | $48.00 | $40.00 |
| 70 | 2" deep joint sealer (516E31010) | FT | 89 | $26.00 | $16.00 | $25.50 | $30.00 |
| 71 | Elastomeric bearing with internal laminates only (neoprene) (516E43200) | EACH | 88 | $122.00 | $200.00 | $150.00 | $210.00 |
| 72 | Railing (three steel tube bridge railing) (517E70100) | FT | 312 | $435.00 | $435.00 | $450.00 | $491.00 |
| 73 | Porous backfill with geotextile fabric (518E21200) | CY | 56 | $140.00 | $145.00 | $150.00 | $200.00 |
| 74 | Special - steel drip strip (518E22300) | FT | 360 | $15.00 | $16.00 | $14.75 | $20.00 |
| 75 | 6" perforated corrugated plastic pipe (518E40000) | FT | 118 | $8.00 | $13.00 | $12.00 | $12.00 |
| 76 | 6" non-perforated corrugated plastic pipe (518E40012) | FT | 64 | $12.00 | $13.00 | $12.00 | $20.00 |
| 77 | Reinforced concrete approach slabs (T=15"), as per plan (526E25001) | SY | 247 | $390.00 | $415.00 | $300.00 | $430.00 |
| 78 | Type C installation, as per plan (526E90031) | FT | 89 | $290.00 | $360.00 | $350.00 | $340.00 |
| 79 | Precast reinforced concrete outlet (611E99710) | EACH | 4 | $350.00 | $950.00 | $500.00 | $800.00 |
| 80 | Structure grounding system (625E33000) | EACH | 1 | $18,500 | $16,500 | $15,000 | $20,000 |
| 81 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $10,905 | $12,000 | $15,000 | $12,000 |
| 82 | Maintaining traffic (614E11000) | LS | 1 | $2,682.00 | $10,000 | $5,500.00 | $15,000 |
| 83 | Construction layout stakes and surveying (623E10000) | LS | 1 | $24,785 | $19,000 | $15,000 | $14,000 |
| 84 | Mobilization (624E10000) | LS | 1 | $80,000 | $100,000 | $115,000 | $125,000 |
| 85 | Inspection and compaction testing of unbound materials (878E25000) | LS | 1 | $6,200.00 | $10,500 | $8,000.00 | $15,000 |
| 100 | Excavation (203E10000) | CY | 232 | $27.00 | $45.00 | $90.00 | $36.00 |
| 101 | Embankment (203E20000) | CY | 232 | $25.00 | $45.00 | $95.00 | $42.00 |
| 102 | Storm water pollution prevention plan, as per plan (832E15001) | LS | 1 | $535.00 | $3,500.00 | $10,600 | $2,000.00 |
| 105 | 72" conduit, type A, as per plan, 706.02 (611E26001) | FT | 105 | $1,002.00 | $1,350.00 | $625.00 | $1,000.00 |
| 106 | Special -, water filled bladder (690E98400) | LS | 1 | $197,600 | $110,000 | $230,000 | $152,000 |
| 107 | Seeding and mulching, as per plan (659E10001) | SY | 682 | $2.81 | $10.00 | $2.39 | $2.61 |
| 108 | Planting, misc.:' acer saccharinum- silver maple (661E99900) | EACH | 10 | $175.00 | $840.00 | $850.00 | $174.42 |
| 109 | Planting, misc.:' cephalanthus occidentalis? butto (661E99900) | EACH | 10 | $175.00 | $840.00 | $450.00 | $174.42 |
| 110 | Planting, misc.:' quercus bicolor- swamp white oak (661E99900) | EACH | 10 | $175.00 | $840.00 | $850.00 | $174.42 |
| 111 | Planting, misc.:' salix nigra- black willow (661E99900) | EACH | 10 | $175.00 | $840.00 | $1,000.00 | $174.42 |
| 112 | Pile driving equipment mobilization (505E11100) | LS | 1 | $20,240 | $30,000 | $35,000 | $25,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of March 27, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.