ODOT contract 258006 bid tabulation
BEL-US 40-23.26 (BRIDGE REPAIR). Let by Ohio DOT on April 24, 2025, BEL. 1 bid received; low bid $17,016,026 by Beaver Excavating Company, -9.5% against the engineer's estimate of $18,800,000.
- Owner
- Ohio DOT
- Letting
- 24 APR 2025
- Pay items
- 166
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Beaver Excavating Company | $17,016,026 | Low | -9.0% |
Engineer's estimate: $18,800,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Beaver Excavating Company |
|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $82,500 |
| 2 | Pavement removed (202E23000) | SY | 1,738 | $25.00 |
| 3 | Walk removed (202E30000) | SF | 31 | $10.00 |
| 4 | Concrete barrier removed (202E30700) | FT | 20 | $65.00 |
| 5 | Curb removed (202E32000) | FT | 76 | $11.00 |
| 6 | Gutter removed (202E32600) | FT | 204 | $9.00 |
| 7 | Pipe removed, 24" and under (202E35100) | FT | 60 | $55.00 |
| 8 | Guardrail removed (202E38000) | FT | 225 | $3.50 |
| 9 | Anchor assembly removed, type E (202E42010) | EACH | 2 | $250.00 |
| 10 | Bridge terminal assembly removed (202E47000) | EACH | 2 | $135.00 |
| 11 | Catch basin removed (202E58100) | EACH | 2 | $365.00 |
| 12 | Excavation (203E10000) | CY | 480 | $40.00 |
| 13 | Embankment (203E20000) | CY | 24 | $52.00 |
| 14 | Subgrade compaction (204E10000) | SY | 1,981 | $5.50 |
| 15 | Guardrail, type MGS with long posts (606E15100) | FT | 93.70 | $55.00 |
| 16 | Anchor assembly, MGS type E(MASH 2016) (606E26150) | EACH | 1 | $2,700.00 |
| 17 | Anchor assembly, MGS type T (606E26550) | EACH | 1 | $1,350.00 |
| 18 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 1 | $2,750.00 |
| 19 | MGS bridge terminal assembly, type 2 (606E35102) | EACH | 1 | $550.00 |
| 20 | 4" concrete walk (608E10000) | SF | 35 | $50.00 |
| 21 | Barrier, misc.:barrier transition north (622E90200) | EACH | 1 | $9,500.00 |
| 22 | Barrier, misc.:barrier transition south (622E90200) | EACH | 1 | $7,500.00 |
| 23 | Slope protection, misc.:grout filled fabric mat (601E21100) | SY | 109 | $550.00 |
| 24 | Paved gutter, type 2 (601E38400) | FT | 192 | $65.00 |
| 25 | Soil analysis test (659E00100) | EACH | 2 | $125.00 |
| 26 | Topsoil (659E00300) | CY | 69 | $110.00 |
| 27 | Seeding and mulching (659E10000) | SY | 618 | $8.52 |
| 28 | Repair seeding and mulching (659E14000) | SY | 31 | $0.80 |
| 29 | Inter-seeding (659E15000) | SY | 31 | $0.80 |
| 30 | Commercial fertilizer (659E20000) | TON | 0.09 | $891.33 |
| 31 | Lime (659E31000) | ACRE | 0.13 | $155.46 |
| 32 | Water (659E35000) | MGAL | 3 | $1.00 |
| 33 | Storm water pollution prevention plan (832E15000) | LS | 1 | $7,500.00 |
| 34 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $20,000 |
| 35 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $15,000 |
| 36 | Erosion control (832E30000) | EACH | 35,000 | $1.00 |
| 37 | 6" base pipe underdrains (605E14000) | FT | 470 | $35.00 |
| 38 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 35 | $55.00 |
| 39 | 12" conduit, type B (611E04400) | FT | 50 | $144.00 |
| 40 | Catch basin, no. 6 (611E98370) | EACH | 2 | $3,550.00 |
| 41 | Catch basin adjusted to grade (611E98630) | EACH | 2 | $1,045.00 |
| 42 | Manhole adjusted to grade (611E99654) | EACH | 1 | $1,035.00 |
| 43 | Precast reinforced concrete outlet (611E99710) | EACH | 1 | $585.00 |
| 44 | Special - miscellaneous metal (611E99820) | LB | 50 | $4.00 |
| 45 | Pavement planing, asphalt concrete(T=3") (254E01000) | SY | 587 | $16.00 |
| 46 | Pavement planing, asphalt concrete(T=4") (254E01000) | SY | 136 | $16.00 |
| 47 | Full depth pavement sawing (255E20000) | FT | 270 | $3.50 |
| 48 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 246 | $300.00 |
| 49 | Aggregate base (304E20000) | CY | 341 | $140.00 |
| 50 | 8" concrete base, class QC 1P (305E12010) | SY | 694 | $135.00 |
| 51 | Tack coat, 702.13 (407E13900) | GAL | 310 | $4.50 |
| 52 | Prime coat, as per plan (408E10001) | GAL | 34 | $20.00 |
| 53 | Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100) | CY | 86 | $500.00 |
| 54 | Asphalt concrete intermediate course, type 1, (449) (441E70200) | CY | 197 | $360.00 |
| 55 | Curb, type 2-B (609E16000) | FT | 28 | $90.00 |
| 56 | Curb, type 4-B (609E24500) | FT | 18 | $98.00 |
| 57 | Curb, type 6 (609E26000) | FT | 129 | $70.00 |
| 58 | Compacted aggregate (617E10100) | CY | 5 | $460.00 |
| 59 | Conduit, misc.: at&T 4" conduit (625E25920) | FT | 3,090 | $75.00 |
| 60 | Ground mounted support, no. 2 post (630E02100) | FT | 39 | $24.00 |
| 61 | Ground mounted support, no. 3 post (630E03100) | FT | 13.50 | $25.00 |
| 62 | Sign, flat sheet (630E80100) | SF | 19.80 | $25.00 |
| 63 | Removal of ground mounted sign and disposal (630E84900) | EACH | 5 | $25.00 |
| 64 | Removal of ground mounted post support and disposal (630E86002) | EACH | 3 | $25.00 |
| 65 | Edge line, 6" (646E10010) | MI | 0.80 | $11,250 |
| 66 | Lane line, 6" (646E10110) | MI | 0.02 | $9,690.00 |
| 67 | Center line (646E10200) | MI | 0.30 | $16,200 |
| 68 | Stop line (646E10400) | FT | 21 | $12.00 |
| 69 | Crosswalk line, 12" (646E10510) | FT | 68 | $7.50 |
| 70 | Transverse/diagonal line (646E10600) | FT | 322 | $7.00 |
| 71 | Bike lane symbol marking (646E20600) | EACH | 5 | $310.00 |
| 72 | Special - work zone traffic signal (614E11300) | EACH | 8 | $10,000 |
| 73 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 6 | $2,350.00 |
| 74 | Detour signing (614E12420) | LS | 1 | $15,000 |
| 75 | Asphalt concrete for maintaining traffic (614E13000) | CY | 50 | $400.00 |
| 76 | Barrier reflector, type 1(one way) (614E13310) | EACH | 123 | $20.00 |
| 77 | Object marker, one way (614E13350) | EACH | 123 | $22.00 |
| 78 | Portable changeable message sign, as per plan (614E18601) | SNMT | 36 | $1,500.00 |
| 79 | Work zone center line, class I, 740.06, type I (614E21200) | MI | 0.67 | $14,500 |
| 80 | Work zone edge line, class I, 6", 740.06, type I (614E22210) | MI | 1.38 | $9,950.00 |
| 81 | Work zone stop line, class I, 740.06, type I (614E26400) | FT | 42 | $12.00 |
| 82 | Water (616E10000) | MGAL | 2 | $175.00 |
| 83 | Portable barrier, unanchored (622E41100) | FT | 2,635 | $25.00 |
| 84 | Special - work involving asbestos containing mater (690E98400) | LS | 1 | $100.00 |
| 85 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $4,000,000 |
| 86 | Approach slab removed (202E22900) | SY | 184 | $45.00 |
| 87 | Unclassified excavation, as per plan (503E21301) | LS | 1 | $35,000 |
| 88 | Epoxy coated steel reinforcement (509E10000) | LB | 323,582 | $1.65 |
| 89 | Concrete reinforcement, replacement of existing concrete reinforcement, as per plan (509E20001) | LB | 500 | $80.00 |
| 90 | Chromium steel reinforcement (509E27000) | LB | 16,475 | $3.35 |
| 91 | No. 4 deformed GFRP reinforcement (509E30020) | FT | 11,611 | $2.25 |
| 92 | Dowel holes with nonshrink, nonmetallic grout (510E10000) | EACH | 112 | $37.00 |
| 93 | Class QC2 concrete with QC/QA, superstructure (511E31612) | CY | 713 | $800.00 |
| 94 | Class QC2 concrete, superstructure (511E33412) | CY | 44 | $3,025.00 |
| 95 | Class QC1 concrete, pier above footings (511E41510) | CY | 66 | $3,025.00 |
| 96 | Class QC1 concrete, abutment not including footing (511E44110) | CY | 23 | $2,955.00 |
| 97 | Class QC2 concrete with QC/QA, sidewalk (511E51512) | CY | 99 | $620.00 |
| 98 | Class QC1 concrete, misc.:moment slab (511E53010) | CY | 140 | $1,075.00 |
| 99 | Class QC2 concrete, misc.:bridge deck (parapet) WI (511E53012) | CY | 274 | $2,150.00 |
| 100 | Sealing of concrete surfaces (non-epoxy) (512E10050) | SY | 435 | $18.00 |
| 101 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 12,574 | $42.00 |
| 102 | Concrete repair by epoxy injection (512E10600) | FT | 793 | $150.00 |
| 103 | Prestressed concrete composite box beam bridge members, level 1, CB12-36 (515E12000) | EACH | 26 | $7,500.00 |
| 104 | Prestressed concrete composite box beam bridge members, level 1, CB12-36 (515E12000) | EACH | 3 | $7,500.00 |
| 105 | Prestressed concrete composite box beam bridge members, level 1, CB12-36 (515E12000) | EACH | 2 | $7,500.00 |
| 106 | Prestressed concrete composite box beam bridge members, level 1, CB12-36 (515E12000) | EACH | 3 | $7,500.00 |
| 107 | Prestressed concrete composite box beam bridge members, level 1, CB12-48 (515E12010) | EACH | 20 | $7,500.00 |
| 108 | Prestressed concrete composite box beam bridge members, level 1, CB12-48 (515E12010) | EACH | 260 | $7,500.00 |
| 109 | Prestressed concrete composite box beam bridge members, level 1, CB12-48 (515E12010) | EACH | 30 | $7,500.00 |
| 110 | Prestressed concrete composite box beam bridge members, level 1, CB12-48 (515E12010) | EACH | 30 | $7,500.00 |
| 111 | Prestressed concrete composite box beam bridge members, level 1, CB21-36 (515E12040) | EACH | 1 | $20,000 |
| 112 | Prestressed concrete composite box beam bridge members, level 1, CB21-36 (515E12040) | EACH | 1 | $20,000 |
| 113 | Prestressed concrete composite box beam bridge members, level 1, CB21-36 (515E12040) | EACH | 1 | $20,000 |
| 114 | Prestressed concrete composite box beam bridge members, level 1, CB21-36 (515E12040) | EACH | 1 | $20,000 |
| 115 | Prestressed concrete composite box beam bridge members, level 1, CB21-36 (515E12040) | EACH | 1 | $20,000 |
| 116 | Prestressed concrete composite box beam bridge members, level 1, CB21-36 (515E12040) | EACH | 1 | $20,000 |
| 117 | Prestressed concrete composite box beam bridge members, level 1, CB21-48 (515E12050) | EACH | 1 | $15,000 |
| 118 | Prestressed concrete composite box beam bridge members, level 1, CB21-48 (515E12050) | EACH | 1 | $15,000 |
| 119 | Prestressed concrete composite box beam bridge members, level 1, CB21-48 (515E12050) | EACH | 1 | $15,000 |
| 120 | Prestressed concrete composite box beam bridge members, level 1, CB21-48 (515E12050) | EACH | 1 | $15,000 |
| 121 | Prestressed concrete composite box beam bridge members, level 1, CB21-48 (515E12050) | EACH | 1 | $15,000 |
| 122 | Prestressed concrete composite box beam bridge members, level 1, CB21-48 (515E12050) | EACH | 1 | $15,000 |
| 123 | Prestressed concrete composite box beam bridge members, level 1, CB21-48 (515E12050) | EACH | 1 | $15,000 |
| 124 | Prestressed concrete composite box beam bridge members, level 1, CB21-48 (515E12050) | EACH | 1 | $15,000 |
| 125 | Prestressed concrete composite box beam bridge members, level 1, CB21-48 (515E12050) | EACH | 1 | $15,000 |
| 126 | Prestressed concrete composite box beam bridge members, level 1, CB21-48 (515E12050) | EACH | 1 | $15,000 |
| 127 | Prestressed concrete composite box beam bridge members, level 1, CB21-48 (515E12050) | EACH | 1 | $15,000 |
| 128 | Prestressed concrete composite box beam bridge members, level 1, CB21-48 (515E12050) | EACH | 1 | $15,000 |
| 129 | Prestressed concrete composite box beam bridge members, level 1, CB21-48 (515E12050) | EACH | 1 | $15,000 |
| 130 | Prestressed concrete composite box beam bridge members, level 1, CB21-48 (515E12050) | EACH | 1 | $15,000 |
| 131 | Prestressed concrete composite box beam bridge members, level 1, CB21-48 (515E12050) | EACH | 1 | $15,000 |
| 132 | Prestressed concrete composite box beam bridge members, level 1, CB21-48 (515E12050) | EACH | 1 | $15,000 |
| 133 | Prestressed concrete composite box beam bridge members, level 1, CB21-48 (515E12050) | EACH | 1 | $15,000 |
| 134 | Prestressed concrete composite box beam bridge members, level 1, CB21-48 (515E12050) | EACH | 8 | $15,000 |
| 135 | Prestressed concrete composite box beam bridge members, level 1, CB21-48 (515E12050) | EACH | 3 | $15,000 |
| 136 | Prestressed concrete composite box beam bridge members, level 1, CB21-48 (515E12050) | EACH | 1 | $15,000 |
| 137 | Prestressed concrete composite box beam bridge members, level 1, CB21-48 (515E12050) | EACH | 1 | $15,000 |
| 138 | Prestressed concrete composite box beam bridge members, level 1, CB21-48 (515E12050) | EACH | 8 | $15,000 |
| 139 | Prestressed concrete composite box beam bridge members, level 1, CB21-48 (515E12050) | EACH | 2 | $15,000 |
| 140 | Prestressed concrete composite box beam bridge members, level 1, CB21-48 (515E12050) | EACH | 8 | $15,000 |
| 141 | Prestressed concrete composite box beam bridge members, level 1, CB21-48 (515E12050) | EACH | 2 | $15,000 |
| 142 | Prestressed concrete composite box beam bridge members, level 1, CB21-48 (515E12050) | EACH | 10 | $15,000 |
| 143 | Structural expansion joint including elastomeric strip seal (516E11210) | FT | 467 | $650.00 |
| 144 | 1" preformed expansion joint filler (516E13600) | SF | 89 | $8.00 |
| 145 | 1/8" preformed bearing pad, type CDP (516E41100) | EACH | 440 | $75.00 |
| 146 | Elastomeric bearing pad, misc.:16" X 18" plain ela (516E42000) | EACH | 39 | $200.00 |
| 147 | Elastomeric bearing pad, misc.:2" X 6" plain elast (516E42600) | FT | 33 | $140.00 |
| 148 | Bearing device, misc.:elastomeric bearing with loa (516E46900) | EACH | 1,760 | $455.00 |
| 149 | Scuppers, including supports (518E12000) | EACH | 8 | $3,000.00 |
| 150 | Special - composite fiber wrap system (519E00100) | SF | 1,609 | $75.00 |
| 151 | Special - patching concrete structuretype 1 repair (519E11600) | SF | 2,658 | $185.00 |
| 152 | Special - patching concrete structuretype 2 repair (519E11600) | SF | 565 | $275.00 |
| 153 | Reinforced concrete approach slabs with QC/QA (T=1 (526E15011) | SY | 96 | $630.00 |
| 154 | Reinforced concrete approach slabs with QC/QA (T=1 (526E25011) | SY | 115 | $650.00 |
| 155 | Type A installation (526E90010) | FT | 106 | $200.00 |
| 156 | Special - structuresarch spans erection engineerin (530E00200) | LS | 1 | $70,000 |
| 157 | Special - structurespier floorbeam shoring (530E00400) | EACH | 3 | $180,000 |
| 158 | Dumped rock fill, type C, as per plan (601E27001) | CY | 18 | $230.00 |
| 159 | Rock channel protection, type A with filter (601E32000) | CY | 304 | $140.00 |
| 160 | Galvanic anode protection (844E20000) | EACH | 4,570 | $94.00 |
| 162 | Class QC2 concrete with QC/QA, superstructure, as per plan (511E34413) | CY | 138 | $3,000.00 |
| 163 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $150,000 |
| 164 | Maintaining traffic (614E11000) | LS | 1 | $50,000 |
| 165 | Field office, type B (619E16010) | MNTH | 18 | $3,000.00 |
| 166 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $70,000 |
| 167 | Mobilization (624E10000) | LS | 1 | $850,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 24, 2025. Compiled by Mirage Metrics.