ODOT contract 260092 bid tabulation
PAU-TR 33-04.75 (BRIDGE REPLACEMENT (1 BRIDGE)). Let by Ohio DOT on February 19, 2026, PAU. 3 bids received; low bid $1,136,845 by R G Zachrich Construction Inc, -13% against the engineer's estimate of $1,310,000.
- Owner
- Ohio DOT
- Letting
- 19 FEB 2026
- Pay items
- 63
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | R G Zachrich Construction Inc | $1,136,845 | Low | -13% |
| 2 | R & I Construction Inc | $1,169,790 | +3.0% | -11% |
| 3 | Eagle Bridge Co | $1,207,778 | +6.0% | -8.0% |
Engineer's estimate: $1,310,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. R G Zachrich Construction Inc | 2. R & I Construction Inc | 3. Eagle Bridge Co |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $5,000.00 | $1,000.00 | $15,500 |
| 2 | Pavement removed (202E23000) | SY | 606 | $10.00 | $6.00 | $15.00 |
| 3 | Guardrail removed (202E38000) | FT | 80 | $5.00 | $2.00 | $3.00 |
| 4 | Excavation (203E10000) | CY | 103 | $44.00 | $20.00 | $60.00 |
| 5 | Embankment (203E20000) | CY | 15 | $60.00 | $50.00 | $50.00 |
| 6 | Subgrade compaction (204E10000) | SY | 582 | $4.00 | $2.00 | $12.00 |
| 7 | Proof rolling (204E45000) | HR | 1 | $1,000.00 | $25.00 | $125.00 |
| 8 | Guardrail, type MGS (606E15050) | FT | 287.50 | $21.00 | $21.00 | $21.00 |
| 9 | Anchor assembly, MGS type A (606E25550) | EACH | 4 | $1,400.00 | $1,400.00 | $1,400.00 |
| 10 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 4 | $2,400.00 | $2,400.00 | $2,400.00 |
| 11 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $1,155.00 | $1,155.00 | $3,000.00 |
| 12 | Post construction survey monument verification and report (623E51000) | LS | 1 | $1,155.00 | $1,155.00 | $3,000.00 |
| 13 | Rock channel protection, type C with aggregate filter (601E32210) | CY | 140 | $92.00 | $90.00 | $75.00 |
| 14 | Topsoil (659E00300) | CY | 35 | $40.00 | $50.00 | $15.00 |
| 15 | Seeding and mulching (659E10000) | SY | 316 | $6.35 | $5.00 | $7.00 |
| 16 | Repair seeding and mulching (659E14000) | SY | 16 | $6.35 | $1.00 | $3.00 |
| 17 | Inter-seeding (659E15000) | SY | 16 | $4.00 | $1.00 | $3.00 |
| 18 | Commercial fertilizer (659E20000) | TON | 0.04 | $850.00 | $500.00 | $1,000.00 |
| 19 | Lime (659E31000) | ACRE | 0.07 | $35.00 | $100.00 | $5.00 |
| 20 | Water (659E35000) | MGAL | 2 | $1.00 | $1.00 | $10.00 |
| 21 | Erosion control (832E30000) | EACH | 10,000 | $1.00 | $1.00 | $1.00 |
| 22 | Aggregate drains (605E31100) | FT | 131 | $20.00 | $10.00 | $15.00 |
| 23 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 57 | $315.00 | $360.00 | $350.00 |
| 24 | Aggregate base (304E20000) | CY | 120 | $80.00 | $70.00 | $135.00 |
| 25 | Non-tracking tack coat (407E20000) | GAL | 53 | $2.50 | $1.00 | $3.00 |
| 26 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 41 | $380.00 | $390.00 | $370.00 |
| 27 | Barrier reflector, type 1(bidirectional) (626E00102) | EACH | 4 | $30.00 | $13.00 | $13.00 |
| 28 | Barrier reflector, type 2(bidirectional) (626E00110) | EACH | 4 | $40.00 | $13.00 | $13.00 |
| 29 | Removal of ground mounted sign and reerection (630E85100) | EACH | 1 | $125.00 | $125.00 | $100.00 |
| 30 | Removal of ground mounted post support and reerection (630E86010) | EACH | 1 | $125.00 | $125.00 | $125.00 |
| 31 | Water (616E10000) | MGAL | 2 | $1.00 | $1.00 | $10.00 |
| 32 | Structure removed, over 20 foot span (202E11002) | LS | 1 | $95,000 | $150,000 | $85,000 |
| 33 | Wearing course removed (202E23500) | SY | 365 | $7.00 | $10.00 | $12.00 |
| 34 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $24,000 | $5,000.00 | $65,000 |
| 35 | Unclassified excavation (503E21300) | LS | 1 | $10,000 | $17,000 | $25,000 |
| 36 | Pile driving equipment mobilization (505E11100) | LS | 1 | $65,000 | $20,000 | $25,000 |
| 37 | Steel piles HP10X42, furnished (507E00100) | FT | 480 | $40.50 | $55.00 | $60.00 |
| 38 | Steel piles HP10X42, driven (507E00150) | FT | 420 | $2.00 | $5.00 | $4.00 |
| 39 | Steel piles HP12X53, furnished (507E00200) | FT | 450 | $48.82 | $64.00 | $65.00 |
| 40 | Steel piles HP12X53, driven (507E00250) | FT | 400 | $2.00 | $5.00 | $5.00 |
| 41 | Special - pile encasement (507E71200) | FT | 130 | $129.50 | $175.00 | $115.00 |
| 42 | Epoxy coated steel reinforcement (509E10000) | LB | 24,358 | $1.70 | $1.75 | $1.40 |
| 43 | Class QC2 concrete, superstructure, as per plan (511E31611) | CY | 80 | $800.00 | $1,000.00 | $1,250.00 |
| 44 | Class QC2 concrete, pier cap (511E43260) | CY | 21 | $1,042.00 | $1,000.00 | $1,650.00 |
| 45 | Class QC1 concrete, abutment including footing (511E43510) | CY | 66 | $400.00 | $1,000.00 | $800.00 |
| 46 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 127 | $16.50 | $30.00 | $45.00 |
| 47 | Prestressed concrete composite box beam bridge members, level 1, CB17-48 (515E12030) | EACH | 21 | $17,000 | $14,700 | $15,400 |
| 48 | 1" preformed expansion joint filler (516E13600) | SF | 26 | $22.00 | $4.00 | $8.00 |
| 49 | Integral abutment expansion joint seal (516E14014) | FT | 60 | $30.00 | $30.00 | $40.00 |
| 50 | 1/8" preformed bearing pad, type CDP (516E41100) | EACH | 42 | $42.23 | $5.00 | $25.00 |
| 51 | Elastomeric bearing with internal laminates only (neoprene) (516E43200) | EACH | 84 | $100.00 | $200.00 | $110.00 |
| 52 | Railing (twin steel tube) (517E70000) | FT | 284.32 | $204.50 | $204.50 | $204.50 |
| 53 | Porous backfill with geotextile fabric (518E21230) | LS | 1 | $8,000.00 | $3,000.00 | $5,000.00 |
| 54 | Special - steel drip strip (518E22300) | FT | 336 | $14.50 | $15.00 | $14.00 |
| 55 | 6" perforated corrugated plastic pipe (518E40000) | FT | 92 | $15.00 | $12.00 | $10.00 |
| 56 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 60 | $15.00 | $12.00 | $15.00 |
| 57 | Reinforced concrete approach slabs (T=13") (526E15000) | SY | 124 | $360.00 | $260.00 | $325.00 |
| 58 | Type A installation (526E90010) | FT | 58 | $140.00 | $200.00 | $225.00 |
| 59 | Polymer modified asphalt expansion joint system (846E00110) | CF | 24 | $805.87 | $806.00 | $806.00 |
| 60 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $17,500 | $14,000 | $15,000 |
| 61 | Maintaining traffic (614E11000) | LS | 1 | $10,000 | $4,606.00 | $2,500.00 |
| 62 | Construction layout stakes and surveying (623E10000) | LS | 1 | $8,000.00 | $6,280.00 | $10,000 |
| 63 | Mobilization (624E10000) | LS | 1 | $57,500 | $90,000 | $50,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of February 19, 2026. Compiled by Mirage Metrics.