ODOT contract 260176 bid tabulation
HAR-SR 67-Sidewalks (SIDEWALK). Let by Ohio DOT on April 9, 2026, HAR. 2 bids received; low bid $1,068,922 by D L Smith Concrete LLC, +8.5% against the engineer's estimate of $985,000.
- Owner
- Ohio DOT
- Letting
- 09 APR 2026
- Pay items
- 97
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | D L Smith Concrete LLC | $1,068,922 | Low | +9.0% |
| 2 | Helms and Sons Excavating | $1,147,122 | +7.0% | +16% |
Engineer's estimate: $985,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D L Smith Concrete LLC | 2. Helms and Sons Excavating |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $22,500 | $15,000 |
| 2 | Pavement removed (202E23000) | SY | 2,245 | $25.00 | $13.00 |
| 3 | Walk removed (202E30000) | SF | 107 | $3.00 | $8.00 |
| 4 | Curb removed (202E32000) | FT | 423 | $12.00 | $14.00 |
| 5 | Pipe removed, 24" and under (202E35100) | FT | 97 | $20.00 | $84.00 |
| 6 | Catch basin removed (202E58100) | EACH | 5 | $800.00 | $1,450.00 |
| 7 | Removal misc.:conduit (202E98200) | FT | 10 | $100.00 | $75.00 |
| 8 | Excavation (203E10000) | CY | 919 | $30.00 | $38.00 |
| 9 | Embankment (203E20000) | CY | 167 | $35.00 | $18.00 |
| 10 | Subgrade compaction (204E10000) | SY | 221 | $13.50 | $2.00 |
| 11 | 4" concrete walk, as per plan (608E10001) | SF | 21,461 | $9.00 | $10.00 |
| 12 | Concrete steps, type B (608E41000) | FT | 24 | $165.00 | $450.00 |
| 13 | Curb ramp, as per plan (608E52001) | SF | 1,013 | $22.00 | $27.00 |
| 14 | Topsoil furnished and placed (653E10000) | CY | 60 | $50.00 | $150.00 |
| 15 | Special - mailbox removed and reset (690E50350) | EACH | 1 | $225.00 | $300.00 |
| 16 | Topsoil (659E00300) | CY | 661 | $55.00 | $50.00 |
| 17 | Seeding and mulching, class 1 (659E00500) | SY | 3,732 | $3.00 | $2.00 |
| 18 | Repair seeding and mulching (659E14000) | SY | 187 | $5.00 | $2.00 |
| 19 | Inter-seeding (659E15000) | SY | 187 | $5.00 | $2.00 |
| 20 | Commercial fertilizer (659E20000) | TON | 0.50 | $790.00 | $900.00 |
| 21 | Lime (659E31000) | ACRE | 0.77 | $30.00 | $50.00 |
| 22 | Water (659E35000) | MGAL | 21 | $1.00 | $1.50 |
| 23 | Slope erosion protection (670E00500) | SY | 1,138 | $5.00 | $3.00 |
| 24 | Storm water pollution prevention plan (832E15000) | LS | 1 | $2,900.00 | $1,650.00 |
| 25 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $6,720.00 | $6,650.00 |
| 26 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $9,000.00 | $15,500 |
| 27 | Erosion control (832E30000) | EACH | 30,000 | $1.00 | $1.00 |
| 28 | 6" conduit, type B (611E00900) | FT | 24 | $75.00 | $147.00 |
| 29 | 8" conduit, type B (611E01800) | FT | 288 | $85.00 | $101.00 |
| 30 | 10" conduit, type B (611E03100) | FT | 26 | $90.00 | $237.00 |
| 31 | Conduit, misc.:type B for drainage discharge (611E97200) | EACH | 10 | $150.00 | $207.00 |
| 32 | Conduit, misc.:type C for drainage discharge (611E97200) | EACH | 10 | $125.00 | $227.00 |
| 33 | Conduit, misc.:type E for drainage discharge (611E97200) | EACH | 10 | $100.00 | $207.00 |
| 34 | Conduit, misc.:type F for drainage discharge (611E97200) | EACH | 10 | $100.00 | $207.00 |
| 35 | Catch basin, no. 2-2B (611E98470) | EACH | 3 | $4,500.00 | $3,775.00 |
| 36 | Catch basin reconstructed to grade (611E98634) | EACH | 2 | $950.00 | $1,925.00 |
| 37 | Catch basin, misc.:ype 1 catch basin, as per plan (611E98690) | EACH | 2 | $6,200.00 | $6,340.00 |
| 38 | Manhole adjusted to grade (611E99654) | EACH | 3 | $525.00 | $1,125.00 |
| 39 | Manhole reconstructed to grade (611E99660) | EACH | 3 | $845.00 | $2,100.00 |
| 40 | Inspection well (611E99720) | EACH | 1 | $800.00 | $1,500.00 |
| 41 | Drainage structure, misc.:ard drain, as per plan (611E99900) | EACH | 2 | $2,500.00 | $3,500.00 |
| 42 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 25 | $565.00 | $360.00 |
| 43 | Asphalt concrete base, PG64-22, (449), (driveways) (301E56100) | CY | 55 | $565.00 | $292.00 |
| 44 | Aggregate base (304E20000) | CY | 322 | $60.00 | $112.00 |
| 45 | Non-tracking tack coat (407E20000) | GAL | 60 | $5.00 | $8.00 |
| 46 | Stabilized crushed aggregate (411E10000) | CY | 199 | $80.00 | $117.00 |
| 47 | Asphalt concrete surface course, 12.5 MM, type A (449) (442E22100) | CY | 9 | $1,025.00 | $422.00 |
| 48 | Asphalt concrete surface course, 12.5 MM, type A (449) (driveways) (442E22120) | CY | 17 | $1,025.00 | $720.00 |
| 49 | Asphalt concrete intermediate course, 19 MM, type A (449) (442E22400) | CY | 13 | $885.00 | $350.00 |
| 50 | Asphalt concrete intermediate course, 19 MM, type A (449) (driveways) (442E22420) | CY | 24 | $885.00 | $715.00 |
| 51 | 6" non-reinforced concrete pavement, class QC 1P, as per plan (452E10011) | SY | 52 | $110.00 | $112.00 |
| 52 | 9" non-reinforced concrete pavement, class QC 1P, as per plan (452E13011) | SY | 1,031 | $120.00 | $123.00 |
| 53 | Combination curb and gutter, type 2, as per plan (609E12001) | FT | 215 | $55.00 | $83.00 |
| 54 | Curb, misc.:curb replaced (in-kind), as per plan (609E98000) | FT | 13 | $85.00 | $83.00 |
| 55 | Valve box adjusted to grade (638E10800) | EACH | 5 | $210.00 | $1,375.00 |
| 56 | Ground mounted support, no. 3 post (630E03100) | FT | 173 | $14.00 | $20.00 |
| 57 | Sign support assembly, pole mounted (630E79500) | EACH | 6 | $175.00 | $263.00 |
| 58 | Sign, flat sheet (630E80100) | SF | 54 | $28.00 | $43.00 |
| 59 | Sign, double faced, street name (630E80500) | EACH | 6 | $125.00 | $188.00 |
| 60 | Removal of ground mounted sign and disposal (630E84900) | EACH | 17 | $25.00 | $38.00 |
| 61 | Removal of ground mounted sign and reerection (630E85100) | EACH | 3 | $75.00 | $113.00 |
| 62 | Removal of ground mounted post support and disposal (630E86002) | EACH | 10 | $25.00 | $38.00 |
| 63 | Removal of pavement marking (643E30000) | FT | 163 | $20.00 | $6.00 |
| 64 | Center line (644E00300) | MI | 0.01 | $10,000 | $15,000 |
| 65 | Stop line (644E00500) | FT | 54 | $9.00 | $18.00 |
| 66 | Crosswalk line, 12" (644E00620) | FT | 424 | $5.00 | $15.00 |
| 67 | 4" conduit, type E (611E00400) | FT | 40 | $1.00 | $7.50 |
| 68 | Conduit, 2", 725.051 (625E25408) | FT | 80 | $10.00 | $16.00 |
| 69 | Conduit, 3", 725.051 (625E25504) | FT | 19 | $12.00 | $18.00 |
| 70 | Conduit, jacked or drilled, 725.052, as per plan (625E25909) | FT | 81 | $50.00 | $80.00 |
| 71 | Trench (625E29000) | FT | 99 | $12.00 | $19.00 |
| 72 | Pull box, 725.08, 18" (625E30700) | EACH | 2 | $1,300.00 | $1,900.00 |
| 73 | Ground rod (625E32000) | EACH | 6 | $400.00 | $425.00 |
| 74 | Underground warning marking tape (625E36010) | FT | 99 | $2.00 | $3.00 |
| 75 | Pedestrian signal head (LED), type D2, countdown, as per plan (632E20731) | EACH | 10 | $830.00 | $1,300.00 |
| 76 | Accessible pedestrian pushbutton, as per plan (632E20751) | EACH | 10 | $1,025.00 | $1,935.00 |
| 77 | Covering of pedestrian signal head (632E25010) | EACH | 10 | $20.00 | $24.00 |
| 78 | Signal cable, 5 conductor, no. 14 AWG (632E40500) | FT | 1,293 | $4.00 | $6.00 |
| 79 | Pedestal foundation (632E64020) | EACH | 6 | $1,200.00 | $2,835.00 |
| 80 | Loop detector lead-in cable, 2 conductor, no. 12 AWG (632E65400) | FT | 1,277 | $3.00 | $4.00 |
| 81 | Conduit riser, 2" diameter, as per plan (632E70401) | EACH | 1 | $800.00 | $695.00 |
| 82 | Conduit riser, 3" diameter, as per plan, type A (632E70601) | EACH | 1 | $1,000.00 | $2,250.00 |
| 83 | Conduit riser, 3" diameter, as per plan, type C (632E70601) | EACH | 1 | $1,500.00 | $3,240.00 |
| 84 | Pedestal, 8', transformer base (632E89900) | EACH | 5 | $1,300.00 | $2,043.00 |
| 85 | Removal of traffic signal installation, as per plan (632E90101) | EACH | 2 | $2,500.00 | $9,450.00 |
| 86 | Signalization, misc.:pedestrian pedestal, removed (632E90400) | EACH | 1 | $800.00 | $1,575.00 |
| 87 | Signalization, misc.:unlash and relash messenger W (632E90500) | FT | 311 | $9.00 | $11.00 |
| 88 | Controller item, misc.:rewire/reprogram controller (633E99000) | EACH | 2 | $1,800.00 | $4,230.00 |
| 89 | Wireless magnetometer detection system, as per plan (898E10001) | EACH | 2 | $2,200.00 | $4,590.00 |
| 90 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $15,000 | $15,000 |
| 91 | Maintaining traffic (614E11000) | LS | 1 | $45,000 | $22,500 |
| 92 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 16 | $80.00 | $115.00 |
| 93 | Field office, type B (619E16010) | MNTH | 4 | $1,025.00 | $250.00 |
| 94 | Construction layout stakes and surveying (623E10000) | LS | 1 | $21,000 | $30,240 |
| 95 | Monument, misc.:post construction monument verific (623E40900) | EACH | 1 | $2,650.00 | $15,000 |
| 96 | Monument, misc.:reconstruction monument verificati (623E40900) | EACH | 1 | $2,650.00 | $15,000 |
| 97 | Mobilization (624E10000) | LS | 1 | $83,000 | $50,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 9, 2026. Compiled by Mirage Metrics.