ODOT contract 260245 bid tabulation
POR-SR 261-03.51 (TWO LANE RESURFACING). Let by Ohio DOT on May 7, 2026, POR. 6 bids received; low bid $1,035,990 by Shelly Company, -10% against the engineer's estimate of $1,156,000.
- Owner
- Ohio DOT
- Letting
- 07 MAY 2026
- Pay items
- 42
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly Company | $1,035,990 | Low | -10% |
| 2 | Ronyak Paving Inc | $1,040,637 | 0.0% | -10% |
| 3 | Karvo Companies Inc | $1,097,516 | +6.0% | -5.0% |
| 4 | Geauga Highway Co | $1,103,998 | +7.0% | -4.0% |
| 5 | Phillips Paving LLC | $1,132,497 | +9.0% | -2.0% |
| 6 | Barbicas Construction Company Inc | $1,200,270 | +16% | +4.0% |
Engineer's estimate: $1,156,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly Company | 2. Ronyak Paving Inc | 3. Karvo Companies Inc | 4. Geauga Highway Co | 5. Phillips Paving LLC | 6. Barbicas Construction Company Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Removal misc.: barrier reflector (202E98100) | EACH | 3 | $30.00 | $50.00 | $15.00 | $15.00 | $50.00 | $15.00 |
| 2 | Excavation (203E10000) | CY | 20 | $25.00 | $25.00 | $25.00 | $55.00 | $50.00 | $20.00 |
| 3 | Roadway, misc.: vertical clearance (203E98600) | EACH | 1 | $780.00 | $800.00 | $1,000.00 | $3,000.00 | $780.00 | $1,000.00 |
| 4 | Linear grading (209E60200) | STA | 41 | $100.00 | $15.00 | $175.00 | $90.00 | $20.00 | $20.00 |
| 5 | Preparing subgrade for shoulder paving (209E72000) | STA | 164 | $48.00 | $15.00 | $25.00 | $60.00 | $20.00 | $30.00 |
| 6 | Special - as-built construction plans (690E91000) | LS | 1 | $2,000.00 | $1,500.00 | $500.00 | $4,000.00 | $750.00 | $500.00 |
| 7 | Erosion control (832E30000) | EACH | 3,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 8 | Partial depth pavement repair (441) (251E01000) | SY | 600 | $65.00 | $45.00 | $65.00 | $60.00 | $40.00 | $26.00 |
| 9 | Pavement repair (253E01000) | SY | 300 | $240.00 | $110.00 | $125.00 | $133.00 | $170.00 | $80.00 |
| 10 | Pavement planing, asphalt concrete (T = 3.00") (254E01000) | SY | 35,027 | $1.50 | $2.00 | $3.00 | $2.94 | $3.00 | $3.50 |
| 11 | Aggregate base (304E20000) | CY | 20 | $60.00 | $60.00 | $25.00 | $100.00 | $100.00 | $60.00 |
| 12 | Non-tracking tack coat (407E20000) | GAL | 5,255 | $2.50 | $2.00 | $2.45 | $3.25 | $2.00 | $3.00 |
| 13 | Prime coat, as per plan (408E10001) | GAL | 1,455 | $5.00 | $2.00 | $6.25 | $4.50 | $3.00 | $7.00 |
| 14 | Asphalt concrete surface course, type 1, (448), PG70-22M (441E50100) | CY | 1,236 | $215.00 | $225.00 | $215.00 | $240.00 | $230.00 | $279.00 |
| 15 | Asphalt concrete intermediate course, type 2, (448) (441E50300) | CY | 1,703 | $150.00 | $185.00 | $175.00 | $205.00 | $185.00 | $219.00 |
| 16 | Compacted aggregate (617E10100) | CY | 102 | $100.00 | $110.00 | $100.00 | $118.00 | $125.00 | $100.00 |
| 17 | RPM (621E00100) | EACH | 210 | $45.00 | $45.00 | $45.00 | $45.00 | $42.00 | $45.00 |
| 18 | Raised pavement marker removed (621E54000) | EACH | 169 | $5.90 | $1.00 | $1.00 | $15.00 | $1.00 | $5.00 |
| 19 | Barrier reflector, type 2 (one way) (626E00110) | EACH | 3 | $30.00 | $150.00 | $125.00 | $12.50 | $250.00 | $275.00 |
| 20 | Edge line, 6" (646E10010) | MI | 3.10 | $3,400.00 | $3,400.00 | $3,400.00 | $10,540 | $2,850.00 | $3,400.00 |
| 21 | Center line (646E10200) | MI | 1.82 | $3,500.00 | $3,500.00 | $3,500.00 | $6,370.00 | $4,100.00 | $3,500.00 |
| 22 | Channelizing line, 8" (646E10300) | FT | 1,030 | $1.60 | $1.60 | $1.60 | $1.60 | $1.50 | $1.60 |
| 23 | Stop line (646E10400) | FT | 102 | $13.00 | $13.00 | $13.00 | $13.00 | $13.00 | $13.00 |
| 24 | Lane arrow (646E20300) | EACH | 19 | $166.00 | $166.00 | $166.00 | $166.00 | $160.00 | $166.00 |
| 25 | Advance radar detection, as per plan (809E69001) | EACH | 4 | $10,350 | $10,350 | $10,350 | $10,350 | $10,350 | $2,250.00 |
| 26 | Stop line radar detection, as per plan (809E69101) | EACH | 6 | $10,050 | $10,050 | $10,050 | $10,050 | $10,050 | $23,500 |
| 27 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 50 | $100.00 | $125.00 | $125.00 | $100.00 | $100.00 | $90.00 |
| 28 | Work zone marking sign (614E12460) | EACH | 12 | $85.00 | $85.00 | $85.00 | $85.00 | $85.00 | $70.00 |
| 29 | Asphalt concrete for maintaining traffic (614E13000) | CY | 10 | $112.00 | $350.00 | $250.00 | $100.00 | $350.00 | $200.00 |
| 30 | Portable changeable message sign, as per plan (614E18601) | SNMT | 6 | $800.00 | $800.00 | $800.00 | $800.00 | $800.00 | $800.00 |
| 31 | Work zone center line, class I (614E21000) | MI | 1.55 | $1,110.00 | $1,110.00 | $1,110.00 | $1,720.50 | $1,250.00 | $1,110.00 |
| 32 | Work zone center line, class III, 642 paint (614E21550) | MI | 1.55 | $975.00 | $975.00 | $975.00 | $975.00 | $1,250.00 | $975.00 |
| 33 | Work zone edge line, class III, 4", 642 paint (614E22350) | MI | 3.10 | $675.00 | $675.00 | $675.00 | $675.00 | $725.00 | $675.00 |
| 34 | Work zone channelizing line, class I, 8" (614E23000) | FT | 2,060 | $0.55 | $0.55 | $0.55 | $0.55 | $0.75 | $0.55 |
| 35 | Work zone channelizing line, class III, 8", 642 paint (614E23680) | FT | 1,030 | $0.50 | $0.50 | $0.50 | $0.55 | $0.75 | $0.55 |
| 36 | Work zone stop line, class I (614E26000) | FT | 204 | $3.00 | $3.00 | $3.00 | $3.00 | $4.00 | $3.00 |
| 37 | Work zone stop line, class III, 642 paint (614E26610) | FT | 102 | $3.00 | $3.00 | $3.00 | $3.00 | $4.00 | $3.00 |
| 38 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $5,000.00 | $7,295.75 | $8,700.00 | $10,000 | $25,000 | $8,000.00 |
| 39 | Maintaining traffic (614E11000) | LS | 1 | $78,000 | $60,000 | $45,618 | $14,700 | $90,000 | $24,000 |
| 40 | Field office, type B (619E16010) | MNTH | 6 | $3,500.00 | $1,500.00 | $2,500.00 | $500.00 | $1,000.00 | $800.00 |
| 41 | Construction layout stakes and surveying (623E10000) | LS | 1 | $2,000.00 | $3,000.00 | $1,500.00 | $1,000.00 | $500.00 | $200.00 |
| 42 | Mobilization (624E10000) | LS | 1 | $40,000 | $45,000 | $75,172 | $3,500.00 | $34,545 | $31,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of May 7, 2026. Compiled by Mirage Metrics.