ODOT contract 260252 bid tabulation
WAS-SR 26-00.16 Acme St (SIDEWALK). Let by Ohio DOT on May 7, 2026, WAS. 2 bids received; low bid $2,616,487 by Alan Stone Co Inc, +24% against the engineer's estimate of $2,106,000.
- Owner
- Ohio DOT
- Letting
- 07 MAY 2026
- Pay items
- 119
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Alan Stone Co Inc | $2,616,487 | Low | +24% |
| 2 | Shelly & Sands Inc | $2,645,332 | +1.0% | +26% |
Engineer's estimate: $2,106,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Alan Stone Co Inc | 2. Shelly & Sands Inc |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $35,000 | $32,000 |
| 2 | Pavement removed (202E23000) | SY | 3,309 | $15.00 | $25.00 |
| 3 | Wearing course removed (202E23500) | SY | 5,139 | $6.50 | $9.00 |
| 4 | Walk removed (202E30000) | SF | 11,830 | $3.50 | $2.00 |
| 5 | Curb removed (202E32000) | FT | 2,939 | $15.00 | $5.50 |
| 6 | Curb and gutter removed (202E32500) | FT | 1,122 | $9.50 | $14.00 |
| 7 | Pipe removed, 24" and under (202E35100) | FT | 18 | $20.00 | $55.00 |
| 8 | Catch basin removed (202E58100) | EACH | 5 | $460.00 | $600.00 |
| 9 | Removal misc.: rock (202E98100) | EACH | 1 | $460.00 | $75.00 |
| 10 | Removal misc.: quik curb delineators (202E98200) | FT | 189 | $190.00 | $135.00 |
| 11 | Excavation (203E10000) | CY | 850 | $50.00 | $55.00 |
| 12 | Embankment (203E20000) | CY | 292 | $40.00 | $25.00 |
| 13 | Subgrade compaction (204E10000) | SY | 3,464 | $3.50 | $13.00 |
| 14 | Proof rolling (204E45000) | HR | 6 | $270.00 | $300.00 |
| 15 | Pavement planing, asphalt concrete, 1.5" (254E01000) | SY | 5,388 | $4.00 | $5.50 |
| 16 | Full depth pavement removal and rigid replacement, type 1, class QC1 (255E11000) | SY | 900 | $190.00 | $205.00 |
| 17 | 5" concrete walk (608E12000) | SF | 17,830 | $8.00 | $9.40 |
| 18 | Concrete steps, type B (608E41000) | FT | 16 | $470.00 | $245.00 |
| 19 | Curb ramp (608E52000) | SF | 1,553 | $20.00 | $35.00 |
| 20 | Detectable warning (608E53020) | SF | 32 | $30.00 | $60.00 |
| 21 | Combination curb and gutter, type 2, as per plan (609E12001) | FT | 3,236 | $35.00 | $35.00 |
| 22 | Combination curb and gutter, type 2, as per plan (609E12001) | FT | 2,007 | $40.00 | $55.00 |
| 23 | Curb, type 6 (609E26000) | FT | 504 | $35.00 | $48.00 |
| 24 | Curb, type 7 (609E28000) | FT | 139 | $50.00 | $60.00 |
| 25 | Special - gas valve box adjusted to grade (611E99700) | EACH | 3 | $110.00 | $350.00 |
| 26 | Raised pavement marker removed (621E54000) | EACH | 5 | $45.00 | $25.00 |
| 27 | Pull box removed (625E31510) | EACH | 4 | $560.00 | $150.00 |
| 28 | Pull box, misc.: adjust to grade (625E31600) | EACH | 3 | $1,100.00 | $250.00 |
| 29 | Fire hydrant adjusted to grade (638E10400) | EACH | 5 | $3,700.00 | $1,450.00 |
| 30 | Fire hydrant and gate valve removed and reset (638E10600) | EACH | 1 | $6,300.00 | $7,500.00 |
| 31 | Valve box adjusted to grade (638E10800) | EACH | 10 | $410.00 | $900.00 |
| 32 | Service box adjusted to grade (638E10900) | EACH | 7 | $490.00 | $550.00 |
| 33 | Inspection and compaction testing of unbound materials (878E25000) | LS | 1 | $72,000 | $35,000 |
| 34 | Topsoil (659E00300) | CY | 550 | $80.00 | $125.00 |
| 35 | Seeding and mulching (659E10000) | SY | 1,397 | $5.00 | $2.50 |
| 36 | Commercial fertilizer (659E20000) | TON | 0.13 | $620.00 | $1,250.00 |
| 37 | Lime (659E31000) | ACRE | 0.29 | $890.00 | $150.00 |
| 38 | Water (659E35000) | MGAL | 3.77 | $110.00 | $1.00 |
| 39 | Slope erosion protection (670E00500) | SY | 750 | $2.00 | $2.00 |
| 40 | Storm water pollution prevention plan (832E15000) | LS | 1 | $3,300.00 | $2,200.00 |
| 41 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $20,000 | $7,500.00 |
| 42 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $17,000 | $15,550 |
| 43 | Erosion control (832E30000) | EACH | 73,000 | $1.00 | $1.00 |
| 44 | 12" conduit, type B (611E04400) | FT | 86 | $210.00 | $225.00 |
| 45 | Conduit, misc.: pipe removed and replaced (611E97400) | FT | 85 | $65.00 | $45.00 |
| 46 | Catch basin, no. 3 (611E98150) | EACH | 1 | $5,900.00 | $5,300.00 |
| 47 | Catch basin, no. 3, as per plan (611E98151) | EACH | 5 | $6,800.00 | $5,700.00 |
| 48 | Catch basin, no. 6 (611E98370) | EACH | 1 | $5,200.00 | $5,600.00 |
| 49 | Catch basin, no. 7 (611E98390) | EACH | 1 | $7,000.00 | $2,900.00 |
| 50 | Catch basin reconstructed to grade (611E98634) | EACH | 4 | $3,200.00 | $3,100.00 |
| 51 | Manhole, no. 3 (611E99574) | EACH | 1 | $5,100.00 | $4,350.00 |
| 52 | Manhole adjusted to grade (611E99654) | EACH | 2 | $640.00 | $1,200.00 |
| 53 | Manhole reconstructed to grade (611E99660) | EACH | 1 | $1,100.00 | $3,850.00 |
| 54 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 129 | $400.00 | $348.00 |
| 55 | Aggregate base (304E20000) | CY | 911 | $140.00 | $135.00 |
| 56 | Tack coat, 702.13 (407E13900) | GAL | 678 | $6.00 | $6.00 |
| 57 | Non-tracking tack coat (407E20000) | GAL | 950 | $6.00 | $4.00 |
| 58 | Asphalt concrete intermediate course, type 1, (449), as per plan (441E70201) | CY | 10 | $570.00 | $670.00 |
| 59 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 30 | $560.00 | $585.00 |
| 60 | Asphalt concrete surface course, 12.5 MM, type A (448) (442E20000) | CY | 538 | $300.00 | $280.00 |
| 61 | Asphalt concrete intermediate course, 19 MM, type A (448) (442E20200) | CY | 464 | $270.00 | $248.00 |
| 62 | 4" non-reinforced concrete pavement, class QC 1P (452E09010) | SY | 27 | $460.00 | $90.00 |
| 63 | 6" non-reinforced concrete pavement, class QC MS (452E10050) | SY | 336 | $240.00 | $140.00 |
| 64 | 8" non-reinforced concrete pavement, class QC 1P, as per plan (452E12011) | SY | 38.50 | $310.00 | $150.00 |
| 65 | 8" non-reinforced concrete pavement, class QC MS (452E12050) | SY | 883 | $140.00 | $130.00 |
| 66 | Ground mounted support, no. 2 post (630E02100) | FT | 184 | $30.00 | $18.00 |
| 67 | Street name sign support, no. 2 post (630E08510) | FT | 52 | $30.00 | $19.00 |
| 68 | Sign, flat sheet (630E80100) | SF | 99 | $35.00 | $25.00 |
| 69 | Sign, street name (630E80510) | EACH | 13 | $270.00 | $185.00 |
| 70 | Removal of ground mounted sign and disposal (630E84900) | EACH | 47 | $20.00 | $15.00 |
| 71 | Removal of ground mounted sign and reerection (630E85100) | EACH | 3 | $85.00 | $70.00 |
| 72 | Removal of ground mounted post support and disposal (630E86002) | EACH | 21 | $25.00 | $20.00 |
| 73 | Signing, misc.: solar-powered rectangular rapid FL (630E97700) | EACH | 2 | $11,000 | $12,500 |
| 74 | Pedestal foundation (632E64020) | EACH | 3 | $1,300.00 | $1,850.00 |
| 75 | Edge line, 4" (644E00100) | MI | 0.07 | $10,000 | $9,500.00 |
| 76 | Edge line, 4" (644E00100) | MI | 0.08 | $10,000 | $9,500.00 |
| 77 | Center line (644E00300) | MI | 0.58 | $13,000 | $12,895 |
| 78 | Channelizing line, 8" (644E00400) | FT | 1,259 | $2.00 | $3.15 |
| 79 | Stop line (644E00500) | FT | 201 | $15.00 | $9.25 |
| 80 | Crosswalk line, 12" (644E00620) | FT | 369 | $10.00 | $4.70 |
| 81 | Crosswalk line, 24" (644E00630) | FT | 390 | $15.00 | $9.50 |
| 82 | Transverse/diagonal line (644E00700) | FT | 90 | $15.00 | $9.50 |
| 83 | Chevron marking (644E00720) | FT | 91 | $15.00 | $9.50 |
| 84 | Parking lot stall marking (644E01200) | FT | 172 | $1.50 | $2.75 |
| 85 | Lane arrow (644E01300) | EACH | 21 | $130.00 | $115.00 |
| 86 | Dotted line, 4" (644E01500) | FT | 78 | $1.00 | $2.50 |
| 87 | Connection, fused pull apart (625E00450) | EACH | 8 | $160.00 | $140.00 |
| 88 | Bracket arm, 10' (625E18000) | EACH | 4 | $1,400.00 | $1,265.00 |
| 89 | No. 4 AWG 2400 volt distribution cable (625E23200) | FT | 628 | $8.00 | $7.25 |
| 90 | No. 10 AWG pole and bracket cable (625E23400) | FT | 360 | $3.50 | $3.00 |
| 91 | Conduit, 3", 725.04 (625E25500) | FT | 158 | $40.00 | $36.00 |
| 92 | Luminaire, conventional, solid state (LED), standa (625E26252) | EACH | 4 | $810.00 | $725.00 |
| 93 | Glare shield (625E28000) | EACH | 4 | $320.00 | $285.00 |
| 94 | Trench (625E29000) | FT | 153 | $20.00 | $19.00 |
| 95 | Pull box, 725.08, 18" (625E30700) | EACH | 6 | $1,800.00 | $1,600.00 |
| 96 | Ground rod (625E32000) | EACH | 5 | $390.00 | $350.00 |
| 97 | Power service (625E34000) | EACH | 1 | $4,200.00 | $3,750.00 |
| 98 | Photoelectric control (631E88000) | EACH | 1 | $250.00 | $225.00 |
| 99 | Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate (632E05006) | EACH | 8 | $2,000.00 | $1,835.00 |
| 100 | Pedestrian signal head (LED), type D2, countdown (632E20730) | EACH | 8 | $1,200.00 | $1,050.00 |
| 101 | Accessible pedestrian pushbutton (632E20750) | EACH | 9 | $1,300.00 | $1,200.00 |
| 102 | Detector loop, as per plan (632E26501) | EACH | 2 | $3,300.00 | $2,975.00 |
| 103 | Signal cable, 2 conductor, no. 14 AWG (632E40200) | FT | 426 | $3.50 | $3.15 |
| 104 | Signal cable, 5 conductor, no. 14 AWG (632E40500) | FT | 506 | $4.50 | $4.10 |
| 105 | Signal cable, 7 conductor, no. 14 AWG (632E40700) | FT | 622 | $5.00 | $4.60 |
| 106 | Signal support foundation (632E64010) | EACH | 4 | $8,800.00 | $7,900.00 |
| 107 | Signal support, type TC-81.22, design 4 (632E72110) | EACH | 4 | $19,000 | $16,825 |
| 108 | Cabinet, type TS-2, as per plan (633E65511) | EACH | 1 | $28,000 | $25,500 |
| 109 | Uninterruptible power supply (UPS), as per plan (633E74001) | EACH | 1 | $12,000 | $10,630 |
| 110 | Stop line radar detection, as per plan (809E69101) | EACH | 4 | $14,000 | $12,825 |
| 111 | Law enforcement officer with patrol car for assistance, as per plan (614E11111) | HR | 16 | $170.00 | $105.00 |
| 112 | Detour signing (614E12420) | LS | 1 | $8,600.00 | $9,000.00 |
| 113 | Work zone center line, class II (614E21400) | MI | 1.20 | $1,100.00 | $365.00 |
| 114 | Water (616E10000) | MGAL | 3.50 | $0.30 | $70.00 |
| 115 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $15,000 | $14,200 |
| 116 | Maintaining traffic (614E11000) | LS | 1 | $47,000 | $97,000 |
| 117 | Construction layout stakes and surveying (623E10000) | LS | 1 | $45,000 | $43,000 |
| 118 | Mobilization (624E10000) | LS | 1 | $93,000 | $132,000 |
| 200 | Special - utility test hole (690E98000) | EACH | 2 | $8,200.00 | $1,450.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of May 7, 2026. Compiled by Mirage Metrics.