ODOT contract 260252 bid tabulation

WAS-SR 26-00.16 Acme St (SIDEWALK). Let by Ohio DOT on May 7, 2026, WAS. 2 bids received; low bid $2,616,487 by Alan Stone Co Inc, +24% against the engineer's estimate of $2,106,000.

Owner
Ohio DOT
Letting
07 MAY 2026
Pay items
119
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Alan Stone Co Inc$2,616,487Low+24%
2Shelly & Sands Inc$2,645,332+1.0%+26%
ODOT contract 260252: bids by rank

Engineer's estimate: $2,106,000.

Bid tabulation

LinePay itemUnitQuantity1. Alan Stone Co Inc2. Shelly & Sands Inc
1Clearing and grubbing (201E11000)LS1$35,000$32,000
2Pavement removed (202E23000)SY3,309$15.00$25.00
3Wearing course removed (202E23500)SY5,139$6.50$9.00
4Walk removed (202E30000)SF11,830$3.50$2.00
5Curb removed (202E32000)FT2,939$15.00$5.50
6Curb and gutter removed (202E32500)FT1,122$9.50$14.00
7Pipe removed, 24" and under (202E35100)FT18$20.00$55.00
8Catch basin removed (202E58100)EACH5$460.00$600.00
9Removal misc.: rock (202E98100)EACH1$460.00$75.00
10Removal misc.: quik curb delineators (202E98200)FT189$190.00$135.00
11Excavation (203E10000)CY850$50.00$55.00
12Embankment (203E20000)CY292$40.00$25.00
13Subgrade compaction (204E10000)SY3,464$3.50$13.00
14Proof rolling (204E45000)HR6$270.00$300.00
15Pavement planing, asphalt concrete, 1.5" (254E01000)SY5,388$4.00$5.50
16Full depth pavement removal and rigid replacement, type 1, class QC1 (255E11000)SY900$190.00$205.00
175" concrete walk (608E12000)SF17,830$8.00$9.40
18Concrete steps, type B (608E41000)FT16$470.00$245.00
19Curb ramp (608E52000)SF1,553$20.00$35.00
20Detectable warning (608E53020)SF32$30.00$60.00
21Combination curb and gutter, type 2, as per plan (609E12001)FT3,236$35.00$35.00
22Combination curb and gutter, type 2, as per plan (609E12001)FT2,007$40.00$55.00
23Curb, type 6 (609E26000)FT504$35.00$48.00
24Curb, type 7 (609E28000)FT139$50.00$60.00
25Special - gas valve box adjusted to grade (611E99700)EACH3$110.00$350.00
26Raised pavement marker removed (621E54000)EACH5$45.00$25.00
27Pull box removed (625E31510)EACH4$560.00$150.00
28Pull box, misc.: adjust to grade (625E31600)EACH3$1,100.00$250.00
29Fire hydrant adjusted to grade (638E10400)EACH5$3,700.00$1,450.00
30Fire hydrant and gate valve removed and reset (638E10600)EACH1$6,300.00$7,500.00
31Valve box adjusted to grade (638E10800)EACH10$410.00$900.00
32Service box adjusted to grade (638E10900)EACH7$490.00$550.00
33Inspection and compaction testing of unbound materials (878E25000)LS1$72,000$35,000
34Topsoil (659E00300)CY550$80.00$125.00
35Seeding and mulching (659E10000)SY1,397$5.00$2.50
36Commercial fertilizer (659E20000)TON0.13$620.00$1,250.00
37Lime (659E31000)ACRE0.29$890.00$150.00
38Water (659E35000)MGAL3.77$110.00$1.00
39Slope erosion protection (670E00500)SY750$2.00$2.00
40Storm water pollution prevention plan (832E15000)LS1$3,300.00$2,200.00
41Storm water pollution prevention inspections (832E15002)LS1$20,000$7,500.00
42Storm water pollution prevention inspection software (832E15010)LS1$17,000$15,550
43Erosion control (832E30000)EACH73,000$1.00$1.00
4412" conduit, type B (611E04400)FT86$210.00$225.00
45Conduit, misc.: pipe removed and replaced (611E97400)FT85$65.00$45.00
46Catch basin, no. 3 (611E98150)EACH1$5,900.00$5,300.00
47Catch basin, no. 3, as per plan (611E98151)EACH5$6,800.00$5,700.00
48Catch basin, no. 6 (611E98370)EACH1$5,200.00$5,600.00
49Catch basin, no. 7 (611E98390)EACH1$7,000.00$2,900.00
50Catch basin reconstructed to grade (611E98634)EACH4$3,200.00$3,100.00
51Manhole, no. 3 (611E99574)EACH1$5,100.00$4,350.00
52Manhole adjusted to grade (611E99654)EACH2$640.00$1,200.00
53Manhole reconstructed to grade (611E99660)EACH1$1,100.00$3,850.00
54Asphalt concrete base, PG64-22, (449) (301E56000)CY129$400.00$348.00
55Aggregate base (304E20000)CY911$140.00$135.00
56Tack coat, 702.13 (407E13900)GAL678$6.00$6.00
57Non-tracking tack coat (407E20000)GAL950$6.00$4.00
58Asphalt concrete intermediate course, type 1, (449), as per plan (441E70201)CY10$570.00$670.00
59Asphalt concrete surface course, type 1, (449), (driveways) (441E70500)CY30$560.00$585.00
60Asphalt concrete surface course, 12.5 MM, type A (448) (442E20000)CY538$300.00$280.00
61Asphalt concrete intermediate course, 19 MM, type A (448) (442E20200)CY464$270.00$248.00
624" non-reinforced concrete pavement, class QC 1P (452E09010)SY27$460.00$90.00
636" non-reinforced concrete pavement, class QC MS (452E10050)SY336$240.00$140.00
648" non-reinforced concrete pavement, class QC 1P, as per plan (452E12011)SY38.50$310.00$150.00
658" non-reinforced concrete pavement, class QC MS (452E12050)SY883$140.00$130.00
66Ground mounted support, no. 2 post (630E02100)FT184$30.00$18.00
67Street name sign support, no. 2 post (630E08510)FT52$30.00$19.00
68Sign, flat sheet (630E80100)SF99$35.00$25.00
69Sign, street name (630E80510)EACH13$270.00$185.00
70Removal of ground mounted sign and disposal (630E84900)EACH47$20.00$15.00
71Removal of ground mounted sign and reerection (630E85100)EACH3$85.00$70.00
72Removal of ground mounted post support and disposal (630E86002)EACH21$25.00$20.00
73Signing, misc.: solar-powered rectangular rapid FL (630E97700)EACH2$11,000$12,500
74Pedestal foundation (632E64020)EACH3$1,300.00$1,850.00
75Edge line, 4" (644E00100)MI0.07$10,000$9,500.00
76Edge line, 4" (644E00100)MI0.08$10,000$9,500.00
77Center line (644E00300)MI0.58$13,000$12,895
78Channelizing line, 8" (644E00400)FT1,259$2.00$3.15
79Stop line (644E00500)FT201$15.00$9.25
80Crosswalk line, 12" (644E00620)FT369$10.00$4.70
81Crosswalk line, 24" (644E00630)FT390$15.00$9.50
82Transverse/diagonal line (644E00700)FT90$15.00$9.50
83Chevron marking (644E00720)FT91$15.00$9.50
84Parking lot stall marking (644E01200)FT172$1.50$2.75
85Lane arrow (644E01300)EACH21$130.00$115.00
86Dotted line, 4" (644E01500)FT78$1.00$2.50
87Connection, fused pull apart (625E00450)EACH8$160.00$140.00
88Bracket arm, 10' (625E18000)EACH4$1,400.00$1,265.00
89No. 4 AWG 2400 volt distribution cable (625E23200)FT628$8.00$7.25
90No. 10 AWG pole and bracket cable (625E23400)FT360$3.50$3.00
91Conduit, 3", 725.04 (625E25500)FT158$40.00$36.00
92Luminaire, conventional, solid state (LED), standa (625E26252)EACH4$810.00$725.00
93Glare shield (625E28000)EACH4$320.00$285.00
94Trench (625E29000)FT153$20.00$19.00
95Pull box, 725.08, 18" (625E30700)EACH6$1,800.00$1,600.00
96Ground rod (625E32000)EACH5$390.00$350.00
97Power service (625E34000)EACH1$4,200.00$3,750.00
98Photoelectric control (631E88000)EACH1$250.00$225.00
99Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate (632E05006)EACH8$2,000.00$1,835.00
100Pedestrian signal head (LED), type D2, countdown (632E20730)EACH8$1,200.00$1,050.00
101Accessible pedestrian pushbutton (632E20750)EACH9$1,300.00$1,200.00
102Detector loop, as per plan (632E26501)EACH2$3,300.00$2,975.00
103Signal cable, 2 conductor, no. 14 AWG (632E40200)FT426$3.50$3.15
104Signal cable, 5 conductor, no. 14 AWG (632E40500)FT506$4.50$4.10
105Signal cable, 7 conductor, no. 14 AWG (632E40700)FT622$5.00$4.60
106Signal support foundation (632E64010)EACH4$8,800.00$7,900.00
107Signal support, type TC-81.22, design 4 (632E72110)EACH4$19,000$16,825
108Cabinet, type TS-2, as per plan (633E65511)EACH1$28,000$25,500
109Uninterruptible power supply (UPS), as per plan (633E74001)EACH1$12,000$10,630
110Stop line radar detection, as per plan (809E69101)EACH4$14,000$12,825
111Law enforcement officer with patrol car for assistance, as per plan (614E11111)HR16$170.00$105.00
112Detour signing (614E12420)LS1$8,600.00$9,000.00
113Work zone center line, class II (614E21400)MI1.20$1,100.00$365.00
114Water (616E10000)MGAL3.50$0.30$70.00
115Premium for contract performance bond and for payment bond (103E05000)LS1$15,000$14,200
116Maintaining traffic (614E11000)LS1$47,000$97,000
117Construction layout stakes and surveying (623E10000)LS1$45,000$43,000
118Mobilization (624E10000)LS1$93,000$132,000
200Special - utility test hole (690E98000)EACH2$8,200.00$1,450.00
ODOT contract 260252: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of May 7, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.