ODOT contract 260328 bid tabulation
CUY-/GEA BH FY2027 Misc (PART 1 AND PART 2) (BRIDGE REPAIR). Let by Ohio DOT on July 16, 2026, CUY. 4 bids received; low bid $8,838,828 by Fechko Excavating LLC, -20% against the engineer's estimate of $11,050,000.
- Owner
- Ohio DOT
- Letting
- 16 JUL 2026
- Pay items
- 291
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Fechko Excavating LLC | $8,838,828 | Low | -20% |
| 2 | Ohio Concrete Maintenance LLC | $9,452,324 | +7.0% | -14% |
| 3 | Perk Company Inc | $9,519,749 | +8.0% | -14% |
| 4 | Great Lakes Construction Co | $10,049,875 | +14% | -9.0% |
Engineer's estimate: $11,050,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Fechko Excavating LLC | 2. Ohio Concrete Maintenance LLC | 3. Perk Company Inc | 4. Great Lakes Construction Co |
|---|---|---|---|---|---|---|---|
| 1 | Pavement removed (202E23000) | SY | 215 | $88.00 | $85.00 | $71.17 | $93.00 |
| 2 | Concrete barrier removed (202E30700) | FT | 100 | $47.00 | $150.00 | $66.21 | $56.00 |
| 3 | Curb removed (202E32000) | FT | 410 | $17.25 | $17.00 | $12.18 | $7.00 |
| 4 | Guardrail removed, barrier design (202E38300) | FT | 1,313 | $3.00 | $4.00 | $11.27 | $3.00 |
| 5 | Anchor assembly removed, type T (202E42040) | EACH | 2 | $200.00 | $130.00 | $604.79 | $125.00 |
| 6 | Subgrade compaction (204E10000) | SY | 787 | $3.00 | $6.00 | $2.37 | $8.00 |
| 7 | Guardrail, barrier design, type MGS (606E15550) | FT | 1,275 | $30.00 | $40.00 | $37.60 | $37.60 |
| 8 | Anchor assembly, type T (606E26500) | EACH | 1 | $1,450.00 | $1,300.00 | $1,150.00 | $1,150.00 |
| 9 | Anchor assembly, MGS type T (606E26550) | EACH | 2 | $1,450.00 | $1,600.00 | $1,480.00 | $1,480.00 |
| 10 | Impact attenuator, type 1 (bidirectional) (606E60012) | EACH | 1 | $8,100.00 | $11,000 | $9,840.00 | $9,840.00 |
| 11 | Concrete barrier, type D (622E24000) | FT | 44 | $290.00 | $640.00 | $242.97 | $225.00 |
| 12 | Concrete barrier end section, type D (622E25000) | EACH | 4 | $3,440.00 | $8,000.00 | $6,662.65 | $6,100.00 |
| 13 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 29 | $180.00 | $145.00 | $90.28 | $125.00 |
| 14 | Erosion control (832E30000) | EACH | 10,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 15 | Pavement planing, asphalt concrete, as per plan, V (254E01001) | SY | 5,387 | $11.00 | $16.50 | $11.00 | $11.00 |
| 16 | Asphalt concrete base, PG64-22, (449) (302E56000) | CY | 55 | $915.00 | $950.00 | $915.00 | $915.00 |
| 17 | Aggregate base (304E20000) | CY | 131 | $98.15 | $135.00 | $100.90 | $175.00 |
| 18 | Non-tracking tack coat (407E20000) | GAL | 333 | $40.00 | $45.00 | $40.00 | $40.00 |
| 19 | Asphalt concrete surface course, 12.5 MM, type A (449), as per plan (442E22101) | CY | 188 | $900.00 | $1,000.00 | $900.00 | $900.00 |
| 20 | Asphalt concrete surface course, 12.5 MM, type A (449), as per plan (442E22101) | CY | 46 | $950.00 | $1,150.00 | $950.00 | $950.00 |
| 21 | Asphalt concrete intermediate course, 19 MM, type A (449) (442E22400) | CY | 12 | $915.00 | $1,000.00 | $915.00 | $915.00 |
| 22 | Curb, type 6 (609E26000) | FT | 410 | $37.00 | $80.00 | $60.00 | $35.00 |
| 23 | Rumble strips, shoulder (asphalt concrete) (618E40600) | MI | 3.09 | $4,375.00 | $5,000.00 | $15,000 | $4,375.00 |
| 24 | Barrier reflector, type 2 bidirectional (626E00110) | EACH | 16 | $12.50 | $30.00 | $13.50 | $13.50 |
| 25 | Lane line, 6" (643E00204) | MI | 0.28 | $2,955.00 | $31,000 | $25,500 | $12,770 |
| 26 | Stop line (643E00500) | FT | 56 | $10.00 | $27.00 | $22.00 | $10.00 |
| 27 | Edge line, 6" (644E00104) | MI | 2.77 | $5,310.00 | $6,000.00 | $7,500.00 | $5,310.00 |
| 28 | Edge line, 6" (644E00104) | MI | 3.31 | $5,310.00 | $6,000.00 | $7,500.00 | $5,310.00 |
| 29 | Lane line, 6" (644E00204) | MI | 4.30 | $2,955.00 | $3,300.00 | $3,750.00 | $2,955.00 |
| 30 | Channelizing line, 8" (644E00400) | FT | 2,504 | $2.50 | $2.75 | $2.75 | $2.50 |
| 31 | Dotted line, 6" (644E01510) | FT | 5,392 | $2.25 | $2.50 | $2.00 | $2.25 |
| 32 | Edge line, 6" (646E10010) | MI | 0.41 | $5,380.00 | $6,000.00 | $26,750 | $5,380.00 |
| 33 | Edge line, 6" (646E10010) | MI | 0.28 | $5,380.00 | $6,200.00 | $26,750 | $5,380.00 |
| 34 | Lane line, 6" (646E10110) | MI | 0.37 | $1,865.00 | $2,500.00 | $25,500 | $1,865.00 |
| 35 | Center line (646E10200) | MI | 0.55 | $7,180.00 | $8,000.00 | $28,500 | $7,180.00 |
| 36 | Channelizing line, 8" (646E10300) | FT | 700 | $2.25 | $2.50 | $3.25 | $2.25 |
| 37 | Transverse/diagonal line (646E10600) | FT | 400 | $11.65 | $13.00 | $17.50 | $11.65 |
| 38 | Dotted line, 6" (646E20504) | FT | 806 | $2.00 | $2.50 | $2.25 | $2.00 |
| 39 | Concrete reinforcement, replacement of existing concrete reinforcement, as per plan (509E20001) | LB | 100 | $2.00 | $7.00 | $4.75 | $3.75 |
| 40 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 550 | $30.00 | $50.00 | $32.00 | $32.00 |
| 41 | Sealing concrete bridge decks with HMWM resin (512E10300) | SY | 102 | $13.00 | $12.00 | $19.04 | $35.00 |
| 42 | Special - urethane top coat sealer (512E71500) | SY | 129 | $30.00 | $35.00 | $32.00 | $32.00 |
| 43 | Removal of existing coatings from concrete surfaces (512E74000) | SY | 548 | $28.00 | $40.00 | $30.00 | $30.00 |
| 44 | Special - composite fiber wrap system (519E00100) | SF | 1,160 | $34.00 | $45.00 | $35.00 | $35.00 |
| 45 | Patching concrete structure (519E11100) | SF | 20 | $150.00 | $200.00 | $160.00 | $160.00 |
| 46 | Patching concrete structure, as per plan (519E11101) | SF | 277 | $150.00 | $175.00 | $160.00 | $160.00 |
| 47 | Special - structures: measuring and surveying exis (530E00200) | LS | 1 | $2,220.00 | $5,000.00 | $7,500.00 | $3,000.00 |
| 48 | Special - structures: cleaning of drainage system (530E00400) | EACH | 6 | $600.00 | $600.00 | $1,470.56 | $300.00 |
| 49 | Slope protection, misc.:concrete slope protection (601E21100) | SY | 8 | $970.00 | $1,200.00 | $664.00 | $675.00 |
| 50 | Fence removed and rebuilt (607E35000) | FT | 154 | $89.75 | $20.00 | $68.50 | $68.50 |
| 51 | Galvanic anode protection, as per plan (844E20001) | EACH | 447 | $25.00 | $25.00 | $30.00 | $30.00 |
| 52 | Superplasticized dense concrete overlay using hydrodemolition (848E10200) | SY | 1,167 | $93.00 | $200.00 | $86.52 | $125.00 |
| 53 | Surface preparation using hydrodemolition (848E20000) | SY | 1,167 | $100.00 | $110.00 | $188.00 | $115.00 |
| 54 | Superplasticized dense concrete overlay (variable thickness), material only (848E30200) | CY | 243 | $366.00 | $100.00 | $26.30 | $220.00 |
| 55 | Hand chipping (848E50000) | SY | 176 | $200.00 | $150.00 | $186.44 | $325.00 |
| 56 | Test slab (848E50100) | LS | 1 | $1,300.00 | $100.00 | $2,339.20 | $1,500.00 |
| 57 | Full depth repair, as per plan (848E50201) | CY | 5 | $768.00 | $500.00 | $4,221.26 | $2,700.00 |
| 58 | Existing concrete overlay removed (2.75" thick) (848E50320) | SY | 1,167 | $21.00 | $22.00 | $28.96 | $21.00 |
| 59 | Concrete reinforcement, replacement of existing concrete reinforcement, as per plan (509E20001) | LB | 100 | $2.00 | $7.00 | $4.75 | $3.75 |
| 60 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 482 | $30.00 | $50.00 | $32.00 | $32.00 |
| 61 | Treating of concrete bridge deck with SRS (512E10400) | SY | 419 | $8.00 | $12.00 | $22.87 | $8.50 |
| 62 | Special - urethane top coat sealer (512E71500) | SY | 65 | $30.00 | $40.00 | $32.00 | $32.00 |
| 63 | Removal of existing coatings from concrete surfaces (512E74000) | SY | 473 | $28.00 | $40.00 | $30.00 | $30.00 |
| 64 | Removal of existing pavement marking (512E74500) | FT | 290 | $3.25 | $10.00 | $6.92 | $3.25 |
| 65 | Special - composite fiber wrap system (519E00100) | SF | 585 | $34.00 | $48.00 | $35.00 | $35.00 |
| 66 | Patching concrete bridge deck overlay with micro-silica modified concrete (519E10000) | SY | 7 | $954.00 | $1,000.00 | $622.19 | $2,950.00 |
| 67 | Patching concrete structure (519E11100) | SF | 36 | $150.00 | $200.00 | $160.00 | $160.00 |
| 68 | Patching concrete structure, as per plan (519E11101) | SF | 320 | $150.00 | $150.00 | $160.00 | $160.00 |
| 69 | Special - structures: cleaning of drainage system (530E00400) | EACH | 3 | $592.00 | $1,000.00 | $1,470.56 | $300.00 |
| 70 | Tied concrete block mat with type 2 underlayment, as per plan (601E21061) | SY | 34 | $188.00 | $145.00 | $81.34 | $170.00 |
| 71 | Slope protection, misc.:concrete slope protection (601E21100) | SY | 8 | $970.00 | $1,200.00 | $664.00 | $675.00 |
| 72 | Fence removed and rebuilt (607E35000) | FT | 78 | $89.75 | $15.00 | $72.50 | $72.50 |
| 73 | Galvanic anode protection, as per plan (844E20001) | EACH | 519 | $25.00 | $30.00 | $30.00 | $30.00 |
| 74 | Concrete reinforcement, replacement of existing concrete reinforcement, as per plan (509E20001) | LB | 100 | $2.00 | $7.00 | $4.75 | $3.75 |
| 75 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 94 | $30.00 | $50.00 | $32.00 | $32.00 |
| 76 | Special - urethane top coat sealer (512E71500) | SY | 64 | $30.00 | $40.00 | $32.00 | $32.00 |
| 77 | Removal of existing coatings from concrete surfaces (512E74000) | SY | 92 | $28.00 | $45.00 | $30.00 | $30.00 |
| 78 | Special - composite fiber wrap system (519E00100) | SF | 575 | $34.00 | $45.00 | $35.00 | $35.00 |
| 79 | Patching concrete structure (519E11100) | SF | 17 | $150.00 | $200.00 | $160.00 | $160.00 |
| 80 | Patching concrete structure, as per plan (519E11101) | SF | 220 | $150.00 | $175.00 | $160.00 | $160.00 |
| 81 | Special - structures: cleaning of drainage system (530E00400) | EACH | 3 | $592.00 | $1,000.00 | $1,470.56 | $300.00 |
| 82 | Slope protection, misc.:concrete slope protection (601E21100) | SY | 45 | $970.00 | $500.00 | $364.03 | $675.00 |
| 83 | Fence removed and rebuilt (607E35000) | FT | 103 | $89.75 | $20.00 | $72.00 | $72.00 |
| 84 | Galvanic anode protection, as per plan (844E20001) | EACH | 363 | $25.00 | $30.00 | $30.00 | $30.00 |
| 85 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $164,160 | $94,000 | $86,525 | $192,500 |
| 86 | Granular embankment, as per plan (203E35001) | CY | 17 | $190.00 | $120.00 | $173.60 | $225.00 |
| 87 | Epoxy coated reinforcing steel, as per plan (509E10001) | LB | 3,284 | $2.50 | $3.00 | $2.65 | $2.80 |
| 88 | Concrete reinforcement, replacement of existing concrete reinforcement, as per plan (509E20001) | LB | 200 | $2.00 | $7.00 | $4.75 | $3.75 |
| 89 | Class QC2 concrete, superstructure, as per plan (511E34411) | CY | 29 | $2,820.00 | $1,500.00 | $1,544.69 | $2,700.00 |
| 90 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 614 | $30.00 | $50.00 | $32.00 | $32.00 |
| 91 | Sealing concrete bridge decks with HMWM resin (512E10300) | SY | 1,413 | $13.00 | $15.00 | $24.05 | $18.50 |
| 92 | Removal of existing coatings from concrete surfaces (512E74000) | SY | 583 | $28.00 | $40.00 | $30.00 | $30.00 |
| 93 | Removal of existing pavement marking (512E74500) | FT | 748 | $3.25 | $10.00 | $6.01 | $3.25 |
| 94 | Structural steel members, level UF, as per plan (513E10201) | LB | 4,585 | $12.00 | $16.50 | $12.15 | $11.00 |
| 95 | Field painting of damaged structural steel, as per plan (514E20001) | SF | 729 | $95.00 | $150.00 | $130.00 | $110.00 |
| 96 | Structural expansion joint including elastomeric strip seal, as per plan (516E11211) | FT | 169 | $900.00 | $1,000.00 | $1,060.00 | $930.00 |
| 97 | Reset bearing, as per plan (516E46701) | EACH | 3 | $1,780.00 | $1,200.00 | $1,090.00 | $1,250.00 |
| 98 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $18,500 | $5,000.00 | $9,065.00 | $30,000 |
| 99 | Structure drainage, misc.:weep hole reconstruction (518E62200) | EACH | 13 | $2,100.00 | $500.00 | $953.12 | $300.00 |
| 100 | Patching concrete bridge deck overlay with micro-silica modified concrete (519E10000) | SY | 223 | $768.00 | $600.00 | $292.56 | $375.00 |
| 101 | Patching concrete structure (519E11100) | SF | 77 | $150.00 | $150.00 | $160.00 | $160.00 |
| 102 | Patching concrete structure, as per plan (519E11101) | SF | 29 | $150.00 | $225.00 | $160.00 | $160.00 |
| 103 | Special - structures: measuring and surveying exis (530E00200) | LS | 1 | $4,245.00 | $5,000.00 | $7,500.00 | $3,000.00 |
| 104 | Special - structures: cleaning of bridge seat (530E00400) | EACH | 2 | $1,500.00 | $1,500.00 | $2,000.00 | $2,000.00 |
| 105 | Special - structures: cleaning of drainage system (530E00400) | EACH | 10 | $591.00 | $600.00 | $1,471.95 | $300.00 |
| 106 | Slope protection, misc.:concrete slope protection (601E21100) | SY | 102 | $140.00 | $550.00 | $153.18 | $150.00 |
| 107 | Slope protection, misc.:concrete slope protection (601E21100) | SY | 20 | $970.00 | $900.00 | $390.28 | $675.00 |
| 108 | Galvanic anode protection, as per plan (844E20001) | EACH | 782 | $31.00 | $30.00 | $30.00 | $35.00 |
| 109 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $131,000 | $90,000 | $80,885 | $145,000 |
| 110 | Granular embankment, as per plan (203E35001) | CY | 31 | $190.00 | $120.00 | $173.71 | $225.00 |
| 111 | Epoxy coated reinforcing steel, as per plan (509E10001) | LB | 2,687 | $2.50 | $3.00 | $2.70 | $2.80 |
| 112 | Concrete reinforcement, replacement of existing concrete reinforcement, as per plan (509E20001) | LB | 200 | $2.00 | $7.00 | $4.75 | $3.75 |
| 113 | Class QC2 concrete, superstructure, as per plan (511E34411) | CY | 24 | $2,743.00 | $1,500.00 | $1,563.14 | $2,700.00 |
| 114 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 557 | $30.00 | $45.00 | $32.00 | $32.00 |
| 115 | Treating of concrete bridge deck with SRS (512E10400) | SY | 1,033 | $7.00 | $12.00 | $20.76 | $8.50 |
| 116 | Removal of existing coatings from concrete surfaces (512E74000) | SY | 546 | $28.00 | $40.00 | $30.00 | $30.00 |
| 117 | Removal of existing pavement marking (512E74500) | FT | 555 | $3.25 | $10.00 | $6.01 | $3.25 |
| 118 | Structural steel members, level UF, as per plan (513E10201) | LB | 3,403 | $12.00 | $16.00 | $12.35 | $11.00 |
| 119 | Field painting of damaged structural steel, as per plan (514E20001) | SF | 567 | $95.00 | $150.00 | $135.00 | $110.00 |
| 120 | Structural expansion joint including elastomeric strip seal, as per plan (516E11211) | FT | 128 | $887.00 | $1,050.00 | $1,085.00 | $930.00 |
| 121 | Reset bearing, as per plan (516E46701) | EACH | 5 | $1,780.00 | $1,675.00 | $1,090.00 | $1,250.00 |
| 122 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $20,500 | $8,000.00 | $13,820 | $35,000 |
| 123 | Structure drainage, misc.:weep hole reconstruction (518E62200) | EACH | 10 | $1,500.00 | $300.00 | $953.11 | $300.00 |
| 124 | Patching concrete bridge deck overlay with micro-silica modified concrete (519E10000) | SY | 121 | $758.00 | $650.00 | $292.55 | $375.00 |
| 125 | Patching concrete structure (519E11100) | SF | 76 | $150.00 | $150.00 | $160.00 | $160.00 |
| 126 | Patching concrete structure, as per plan (519E11101) | SF | 20 | $150.00 | $250.00 | $160.00 | $160.00 |
| 127 | Special - structures: measuring and surveying exis (530E00200) | LS | 1 | $4,250.00 | $5,000.00 | $7,500.00 | $3,000.00 |
| 128 | Special - structures: cleaning of bridge seat (530E00400) | EACH | 2 | $1,500.00 | $1,500.00 | $2,000.00 | $2,000.00 |
| 129 | Special - structures: cleaning of drainage system (530E00400) | EACH | 8 | $592.00 | $700.00 | $1,102.92 | $300.00 |
| 130 | Slope protection, misc.:concrete slope protection (601E21100) | SY | 185 | $140.00 | $250.00 | $142.07 | $150.00 |
| 131 | Slope protection, misc.:concrete slope protection (601E21100) | SY | 6 | $970.00 | $1,200.00 | $664.01 | $675.00 |
| 132 | Slope protection, misc.:slope protection cleaning (601E21100) | SY | 225 | $9.97 | $30.00 | $25.54 | $15.00 |
| 133 | Galvanic anode protection, as per plan (844E20001) | EACH | 505 | $30.00 | $30.00 | $30.00 | $35.00 |
| 134 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $239,000 | $95,000 | $146,429 | $265,000 |
| 135 | Epoxy coated reinforcing steel, as per plan (509E10001) | LB | 3,623 | $2.40 | $3.00 | $2.65 | $2.80 |
| 136 | Concrete reinforcement, replacement of existing concrete reinforcement, as per plan (509E20001) | LB | 200 | $2.00 | $7.00 | $4.75 | $3.75 |
| 137 | Class QC2 concrete, superstructure, as per plan (511E34411) | CY | 46 | $1,980.00 | $1,500.00 | $1,769.29 | $3,100.00 |
| 138 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 776 | $30.00 | $50.00 | $32.00 | $32.00 |
| 139 | Sealing concrete bridge decks with HMWM resin (512E10300) | SY | 1,992 | $13.00 | $15.00 | $23.62 | $18.50 |
| 140 | Removal of existing coatings from concrete surfaces (512E74000) | SY | 753 | $28.00 | $40.00 | $30.00 | $30.00 |
| 141 | Removal of existing pavement marking (512E74500) | FT | 1,149 | $3.25 | $10.00 | $6.01 | $3.25 |
| 142 | Structural steel members, level UF, as per plan (513E10201) | LB | 5,114 | $11.00 | $14.75 | $11.55 | $10.50 |
| 143 | Field painting of damaged structural steel, as per plan (514E20001) | SF | 842 | $95.00 | $150.00 | $115.00 | $110.00 |
| 144 | Structural expansion joint including elastomeric strip seal, as per plan (516E11211) | FT | 195 | $872.00 | $980.00 | $1,030.00 | $930.00 |
| 145 | Refurbish bearing device, as per plan (516E45305) | EACH | 3 | $3,250.00 | $5,800.00 | $2,475.00 | $3,500.00 |
| 146 | Reset bearing, as per plan (516E46701) | EACH | 4 | $1,226.00 | $2,000.00 | $990.00 | $1,250.00 |
| 147 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $13,820 | $7,500.00 | $13,820 | $20,000 |
| 148 | Patching concrete bridge deck overlay with micro-silica modified concrete (519E10000) | SY | 211 | $738.00 | $600.00 | $296.03 | $375.00 |
| 149 | Patching concrete structure (519E11100) | SF | 68 | $150.00 | $150.00 | $160.00 | $160.00 |
| 150 | Special - structures: measuring and surveying exis (530E00200) | LS | 1 | $4,200.00 | $5,000.00 | $7,500.00 | $3,000.00 |
| 151 | Special - structures: cleaning of bridge seat (530E00400) | EACH | 2 | $1,500.00 | $1,500.00 | $2,000.00 | $2,000.00 |
| 152 | Special - structures: cleaning of drainage system (530E00400) | EACH | 11 | $592.00 | $800.00 | $952.52 | $300.00 |
| 153 | Galvanic anode protection, as per plan (844E20001) | EACH | 1,082 | $25.00 | $30.00 | $30.00 | $35.00 |
| 154 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $138,200 | $95,000 | $56,690 | $165,000 |
| 155 | Epoxy coated reinforcing steel, as per plan (509E10001) | LB | 2,806 | $2.50 | $2.25 | $2.53 | $2.80 |
| 156 | Concrete reinforcement, replacement of existing concrete reinforcement, as per plan (509E20001) | LB | 200 | $2.00 | $7.00 | $4.75 | $3.75 |
| 157 | Class QC2 concrete, superstructure, as per plan (511E34411) | CY | 26 | $2,440.00 | $1,500.00 | $1,667.35 | $2,650.00 |
| 158 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 701 | $30.00 | $50.00 | $32.00 | $32.00 |
| 159 | Treating of concrete bridge deck with SRS (512E10400) | SY | 1,302 | $7.00 | $12.00 | $13.84 | $8.50 |
| 160 | Removal of existing coatings from concrete surfaces (512E74000) | SY | 600 | $28.00 | $40.00 | $30.00 | $30.00 |
| 161 | Removal of existing pavement marking (512E74500) | FT | 708 | $3.25 | $10.00 | $6.01 | $3.25 |
| 162 | Structural steel members, level UF, as per plan (513E10201) | LB | 3,650 | $11.00 | $18.75 | $11.75 | $10.50 |
| 163 | Field painting of damaged structural steel, as per plan (514E20001) | SF | 622 | $95.00 | $150.00 | $125.00 | $110.00 |
| 164 | Structural expansion joint including elastomeric strip seal, as per plan (516E11211) | FT | 141 | $872.00 | $960.00 | $1,085.00 | $930.00 |
| 165 | Refurbish bearing device, as per plan (516E45305) | EACH | 8 | $3,250.00 | $6,500.00 | $3,375.00 | $3,500.00 |
| 166 | Reset bearing, as per plan (516E46701) | EACH | 5 | $1,780.00 | $1,900.00 | $990.00 | $1,250.00 |
| 167 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $23,200 | $20,000 | $23,150 | $30,000 |
| 168 | Patching concrete bridge deck overlay with micro-silica modified concrete (519E10000) | SY | 58 | $740.00 | $600.00 | $346.76 | $380.00 |
| 169 | Patching concrete structure (519E11100) | SF | 115 | $150.00 | $150.00 | $160.00 | $160.00 |
| 170 | Special - structures: measuring and surveying exis (530E00200) | LS | 1 | $4,260.00 | $5,000.00 | $7,500.00 | $3,000.00 |
| 171 | Special - structures: cleaning of bridge seat (530E00400) | EACH | 2 | $1,500.00 | $1,500.00 | $2,932.74 | $2,000.00 |
| 172 | Special - structures: cleaning of drainage system (530E00400) | EACH | 10 | $592.00 | $600.00 | $992.63 | $300.00 |
| 173 | Galvanic anode protection, as per plan (844E20001) | EACH | 532 | $31.00 | $30.00 | $30.00 | $35.00 |
| 174 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $155,600 | $90,000 | $75,574 | $175,000 |
| 175 | Approach slab removed (202E22900) | SY | 249 | $60.00 | $65.00 | $48.63 | $90.00 |
| 176 | Granular embankment, as per plan (203E35001) | CY | 67 | $190.00 | $120.00 | $177.68 | $225.00 |
| 177 | Epoxy coated reinforcing steel, as per plan (509E10001) | LB | 6,032 | $2.30 | $2.25 | $2.53 | $2.80 |
| 178 | Concrete reinforcement, replacement of existing concrete reinforcement, as per plan (509E20001) | LB | 200 | $2.00 | $7.00 | $4.75 | $3.75 |
| 179 | Class QC2 concrete, superstructure, as per plan (511E34411) | CY | 29 | $2,386.00 | $1,500.00 | $1,931.02 | $3,000.00 |
| 180 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 728 | $30.00 | $50.00 | $45.00 | $32.00 |
| 181 | Special - urethane top coat sealer (512E71500) | SY | 134 | $30.00 | $40.00 | $32.00 | $32.00 |
| 182 | Removal of existing coatings from concrete surfaces (512E74000) | SY | 645 | $28.00 | $40.00 | $30.00 | $30.00 |
| 183 | Structural steel members, level UF, as per plan (513E10201) | LB | 3,281 | $12.50 | $16.50 | $12.60 | $11.25 |
| 184 | Field painting of damaged structural steel, as per plan (514E20001) | SF | 541 | $95.00 | $175.00 | $160.00 | $110.00 |
| 185 | Structural expansion joint including elastomeric strip seal, as per plan (516E11211) | FT | 119 | $913.00 | $1,075.00 | $1,140.00 | $930.00 |
| 186 | Reset bearing, as per plan (516E46701) | EACH | 10 | $1,780.00 | $1,750.00 | $990.00 | $1,250.00 |
| 187 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $29,000 | $15,000 | $19,580 | $35,000 |
| 188 | Structure drainage, misc.:weep hole reconstruction (518E62200) | EACH | 8 | $356.00 | $700.00 | $909.03 | $300.00 |
| 189 | Special - composite fiber wrap system (519E00100) | SF | 1,202 | $34.00 | $40.00 | $35.00 | $35.00 |
| 190 | Patching concrete bridge deck overlay with micro-silica modified concrete (519E10000) | SY | 17 | $783.00 | $700.00 | $446.28 | $410.00 |
| 191 | Patching concrete structure (519E11100) | SF | 92 | $150.00 | $175.00 | $160.00 | $160.00 |
| 192 | Patching concrete structure, as per plan (519E11101) | SF | 362 | $150.00 | $175.00 | $160.00 | $160.00 |
| 193 | Reinforced concrete approach slabs (T=15") (526E25000) | SY | 328 | $498.00 | $500.00 | $515.08 | $500.00 |
| 194 | Type A installation (526E90010) | FT | 118 | $258.00 | $225.00 | $247.75 | $295.00 |
| 195 | Special - structures: measuring and surveying exis (530E00200) | LS | 1 | $8,500.00 | $5,000.00 | $7,500.00 | $3,000.00 |
| 196 | Special - structures: cleaning of bridge seat (530E00400) | EACH | 2 | $1,500.00 | $1,500.00 | $2,932.74 | $2,000.00 |
| 197 | Slope protection, misc.:concrete slope protection (601E21100) | SY | 399 | $140.00 | $300.00 | $142.06 | $150.00 |
| 198 | Paved gutter, type 1-4, as per plan (601E38001) | FT | 90 | $52.00 | $155.00 | $112.04 | $245.00 |
| 199 | 4" concrete walk, as per plan (608E10001) | SF | 1,368 | $16.00 | $15.00 | $13.30 | $21.00 |
| 200 | Galvanic anode protection, as per plan (844E20001) | EACH | 1,127 | $28.00 | $30.00 | $30.00 | $35.00 |
| 201 | Polymer modified asphalt expansion joint system (846E00110) | CF | 50 | $600.00 | $800.00 | $615.00 | $810.00 |
| 202 | Superplasticized dense concrete overlay using hydrodemolition (848E10200) | SY | 821 | $103.00 | $145.00 | $102.74 | $125.00 |
| 203 | Surface preparation using hydrodemolition (848E20000) | SY | 821 | $122.00 | $135.00 | $174.96 | $115.00 |
| 204 | Superplasticized dense concrete overlay (variable thickness), material only (848E30200) | CY | 5 | $366.00 | $500.00 | $263.84 | $325.00 |
| 205 | Hand chipping (848E50000) | SY | 124 | $290.00 | $150.00 | $185.96 | $325.00 |
| 206 | Test slab (848E50100) | LS | 1 | $1,310.00 | $500.00 | $2,339.20 | $1,500.00 |
| 207 | Full depth repair, as per plan (848E50201) | CY | 4 | $750.00 | $500.00 | $4,221.26 | $2,700.00 |
| 208 | Existing concrete overlay removed (1.75" thick) (848E50320) | SY | 821 | $26.25 | $25.00 | $31.85 | $28.00 |
| 209 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $117,200 | $70,000 | $53,284 | $125,000 |
| 210 | Approach slab removed (202E22900) | SY | 134 | $62.00 | $70.00 | $79.12 | $90.00 |
| 211 | Granular embankment, as per plan (203E35001) | CY | 44 | $190.00 | $120.00 | $222.27 | $225.00 |
| 212 | Epoxy coated reinforcing steel, as per plan (509E10001) | LB | 5,419 | $2.50 | $2.25 | $2.53 | $2.80 |
| 213 | Concrete reinforcement, replacement of existing concrete reinforcement, as per plan (509E20001) | LB | 200 | $2.00 | $7.00 | $4.75 | $3.75 |
| 214 | Class QC2 concrete, superstructure, as per plan (511E34411) | CY | 22 | $2,342.00 | $1,300.00 | $1,892.38 | $2,850.00 |
| 215 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 507 | $30.00 | $50.00 | $32.00 | $32.00 |
| 216 | Treating of concrete bridge deck with SRS (512E10400) | SY | 734 | $8.00 | $12.00 | $16.54 | $8.50 |
| 217 | Removal of existing coatings from concrete surfaces (512E74000) | SY | 507 | $28.00 | $40.00 | $30.00 | $30.00 |
| 218 | Removal of existing pavement marking (512E74500) | FT | 515 | $3.25 | $10.00 | $6.01 | $3.25 |
| 219 | Structural steel members, level UF, as per plan (513E10201) | LB | 2,214 | $12.00 | $16.50 | $12.50 | $11.25 |
| 220 | Field painting of damaged structural steel, as per plan (514E20001) | SF | 364 | $95.00 | $200.00 | $170.00 | $110.00 |
| 221 | Structural expansion joint including elastomeric strip seal, as per plan (516E11211) | FT | 84 | $870.00 | $1,200.00 | $1,250.00 | $930.00 |
| 222 | Reset bearing, as per plan (516E46701) | EACH | 8 | $1,780.00 | $1,850.00 | $990.00 | $1,250.00 |
| 223 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $38,800 | $13,000 | $17,205 | $30,000 |
| 224 | Structure drainage, misc.:weep hole reconstruction (518E62200) | EACH | 6 | $356.00 | $700.00 | $909.27 | $300.00 |
| 225 | Patching concrete structure, as per plan (519E11101) | SF | 27 | $150.00 | $175.00 | $160.00 | $160.00 |
| 226 | Reinforced concrete approach slabs (T=15") (526E25000) | SY | 214 | $529.00 | $500.00 | $487.85 | $550.00 |
| 227 | Type A installation (526E90010) | FT | 77 | $265.00 | $240.00 | $252.58 | $315.00 |
| 228 | Special - structures: measuring and surveying exis (530E00200) | LS | 1 | $7,400.00 | $5,000.00 | $7,500.00 | $3,000.00 |
| 229 | Special - structures: cleaning of bridge seat (530E00400) | EACH | 2 | $1,500.00 | $1,500.00 | $2,932.74 | $2,000.00 |
| 230 | Slope protection, misc.:concrete slope protection (601E21100) | SY | 262 | $181.00 | $225.00 | $192.56 | $150.00 |
| 231 | Paved gutter, type 1-4, as per plan (601E38001) | FT | 70 | $52.00 | $175.00 | $132.40 | $245.00 |
| 232 | 4" concrete walk, as per plan (608E10001) | SF | 837 | $16.00 | $14.00 | $16.72 | $21.00 |
| 233 | Galvanic anode protection, as per plan (844E20001) | EACH | 312 | $30.00 | $30.00 | $30.00 | $35.00 |
| 234 | Polymer modified asphalt expansion joint system (846E00110) | CF | 33 | $600.00 | $825.00 | $615.00 | $810.00 |
| 235 | Concrete reinforcement, replacement of existing concrete reinforcement, as per plan (509E20001) | LB | 100 | $2.00 | $7.00 | $4.75 | $3.75 |
| 236 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 109 | $30.00 | $50.00 | $32.00 | $32.00 |
| 237 | Special - urethane top coat sealer (512E71500) | SY | 82 | $30.00 | $40.00 | $32.00 | $32.00 |
| 238 | Removal of existing coatings from concrete surfaces (512E74000) | SY | 109 | $28.00 | $40.00 | $30.00 | $30.00 |
| 239 | Structural steel members, level UF, as per plan (513E10201) | LB | 151 | $59.00 | $166.00 | $82.00 | $104.00 |
| 240 | Field painting of damaged structural steel, as per plan (514E20001) | SF | 5 | $500.00 | $1,800.00 | $2,500.00 | $500.00 |
| 241 | Special - composite fiber wrap system (519E00100) | SF | 736 | $34.00 | $45.00 | $35.00 | $35.00 |
| 242 | Patching concrete structure (519E11100) | SF | 5 | $150.00 | $200.00 | $160.00 | $160.00 |
| 243 | Patching concrete structure, as per plan (519E11101) | SF | 122 | $180.00 | $175.00 | $160.00 | $180.00 |
| 244 | Special - structures: cleaning of bridge seat (530E00400) | EACH | 2 | $1,500.00 | $1,500.00 | $3,428.12 | $2,000.00 |
| 245 | Tied concrete block mat with type 2 underlayment (601E21060) | SY | 40 | $154.00 | $140.00 | $107.29 | $125.00 |
| 246 | Tied concrete block mat with type 2 underlayment, as per plan (601E21061) | SY | 90 | $149.00 | $140.00 | $133.40 | $170.00 |
| 247 | Fence removed and rebuilt (607E35000) | FT | 10 | $89.75 | $50.00 | $86.00 | $86.00 |
| 248 | Treating of concrete bridge deck with SRS (512E10400) | SY | 1,102 | $8.00 | $12.00 | $14.48 | $8.50 |
| 249 | Removal of existing pavement marking (512E74500) | FT | 695 | $3.25 | $10.00 | $6.01 | $3.25 |
| 250 | Concrete reinforcement, replacement of existing concrete reinforcement, as per plan (509E20001) | LB | 100 | $2.00 | $7.00 | $4.75 | $3.75 |
| 251 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 189 | $30.00 | $50.00 | $32.00 | $32.00 |
| 252 | Removal of existing coatings from concrete surfaces (512E74000) | SY | 189 | $28.00 | $40.00 | $30.00 | $30.00 |
| 253 | Structural steel members, level UF, as per plan (513E10201) | LB | 568 | $49.00 | $77.00 | $35.50 | $47.00 |
| 254 | Field painting of damaged structural steel, as per plan (514E20001) | SF | 128 | $115.00 | $375.00 | $330.00 | $150.00 |
| 255 | Reset bearing, as per plan (516E46701) | EACH | 6 | $1,966.00 | $2,000.00 | $1,175.00 | $1,350.00 |
| 256 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $28,000 | $9,000.00 | $24,706 | $30,000 |
| 257 | Patching concrete structure (519E11100) | SF | 30 | $150.00 | $200.00 | $160.00 | $160.00 |
| 258 | Special - structures: cleaning of bridge seat (530E00400) | EACH | 2 | $1,500.00 | $1,500.00 | $2,932.74 | $2,000.00 |
| 259 | Concrete reinforcement, replacement of existing concrete reinforcement, as per plan (509E20001) | LB | 100 | $2.00 | $7.00 | $4.75 | $3.75 |
| 260 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 189 | $30.00 | $50.00 | $32.00 | $32.00 |
| 261 | Removal of existing coatings from concrete surfaces (512E74000) | SY | 189 | $28.00 | $40.00 | $30.00 | $30.00 |
| 262 | Structural steel members, level UF, as per plan (513E10201) | LB | 422 | $62.00 | $70.00 | $62.00 | $47.50 |
| 263 | Field painting of damaged structural steel, as per plan (514E20001) | SF | 104 | $115.00 | $375.00 | $375.00 | $150.00 |
| 264 | Reset bearing, as per plan (516E46701) | EACH | 6 | $1,965.00 | $1,900.00 | $1,175.00 | $1,350.00 |
| 265 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $28,500 | $9,000.00 | $24,706 | $30,000 |
| 266 | Patching concrete structure (519E11100) | SF | 27 | $150.00 | $175.00 | $160.00 | $160.00 |
| 267 | Special - structures: cleaning of bridge seat (530E00400) | EACH | 2 | $1,500.00 | $1,500.00 | $2,932.74 | $2,000.00 |
| 268 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 750 | $65.00 | $120.00 | $125.00 | $105.00 |
| 269 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 11 | $2,147.50 | $1,200.00 | $2,340.00 | $2,147.47 |
| 270 | Detour signing (614E12420) | LS | 1 | $30,000 | $35,000 | $75,000 | $29,763 |
| 271 | Barrier reflector, type 1, one-way (614E13310) | EACH | 177 | $12.25 | $14.00 | $12.50 | $12.22 |
| 272 | Object marker, one way (614E13350) | EACH | 172 | $20.25 | $23.00 | $20.00 | $20.26 |
| 273 | Portable changeable message sign, as per plan (614E18601) | SNMT | 12 | $1,012.50 | $1,200.00 | $1,368.11 | $1,012.50 |
| 274 | Work zone center line, class I, 642 paint (614E21100) | MI | 0.44 | $1,645.00 | $2,000.00 | $3,750.00 | $1,645.00 |
| 275 | Work zone edge line, class I, 6", 642 paint (614E22110) | MI | 7.48 | $1,305.00 | $1,500.00 | $3,250.00 | $1,305.00 |
| 276 | Work zone edge line, class I, 6", 642 paint (614E22110) | MI | 5.53 | $1,305.00 | $1,500.00 | $3,250.00 | $1,305.00 |
| 277 | Work zone channelizing line, class I, 12", 642 paint (614E23210) | FT | 10,944 | $1.00 | $1.25 | $1.50 | $1.00 |
| 278 | Work zone dotted line, class I, 4", 642 paint (614E24200) | FT | 7,936 | $0.80 | $1.00 | $1.40 | $0.80 |
| 279 | Pavement for maintaining traffic, class B (615E25000) | SY | 1,666 | $99.00 | $240.00 | $91.95 | $85.00 |
| 280 | Portable barrier, unanchored (622E41100) | FT | 8,223 | $36.00 | $25.00 | $28.00 | $20.00 |
| 281 | Structural steel, misc.: retrofit stiffener (513E95030) | EACH | 100 | $1,797.00 | $2,300.00 | $1,825.00 | $2,550.00 |
| 282 | Structural steel, misc.: retrofit stiffener (513E95030) | EACH | 100 | $1,797.00 | $2,300.00 | $1,825.00 | $2,550.00 |
| 283 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 720 | $65.00 | $120.00 | $125.00 | $105.00 |
| 284 | Portable changeable message sign, as per plan (614E18601) | SNMT | 10 | $1,012.50 | $1,200.00 | $1,368.11 | $1,012.50 |
| 285 | Premium on railroads' protective public liability and property damage liability insurance (100E00300) | LS | 1 | $10,000 | $10,000 | $10,000 | $5,000.00 |
| 286 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $69,480 | $90,000 | $80,000 | $149,300 |
| 287 | CPM progress schedule (108E10000) | LS | 1 | $9,000.00 | $60,000 | $33,289 | $1,000.00 |
| 288 | Maintaining traffic (614E11000) | LS | 1 | $396,650 | $275,000 | $742,000 | $1,115,000 |
| 291 | Construction layout stakes and surveying (623E10000) | LS | 1 | $8,900.00 | $10,000 | $63,300 | $20,000 |
| 292 | Mobilization (624E10000) | LS | 1 | $484,500 | $315,000 | $750,000 | $500,000 |
| 300 | Roads for maintaining traffic (615E10000) | LS | 1 | $11,500 | $20,000 | $42,000 | $50,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of July 16, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.