ODOT contract 260342 bid tabulation
ALL-SR 65-13.25 (BRIDGE REPAIR). Let by Ohio DOT on July 30, 2026, ALL. 4 bids received; low bid $2,008,664 by Eagle Bridge Co, -18% against the engineer's estimate of $2,440,000.
- Owner
- Ohio DOT
- Letting
- 30 JUL 2026
- Pay items
- 85
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Eagle Bridge Co | $2,008,664 | Low | -18% |
| 2 | Vernon Nagel Inc | $2,028,632 | +1.0% | -17% |
| 3 | Miller Bros Const Inc | $2,074,382 | +3.0% | -15% |
| 4 | Complete General Construction Company | $2,155,803 | +7.0% | -12% |
Engineer's estimate: $2,440,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Eagle Bridge Co | 2. Vernon Nagel Inc | 3. Miller Bros Const Inc | 4. Complete General Construction Company |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $100.00 | $5,000.00 | $1,345.06 | $4,000.00 |
| 2 | Pavement removed (202E23000) | SY | 690 | $15.00 | $30.00 | $12.40 | $22.00 |
| 3 | Guardrail removed (202E38000) | FT | 600 | $2.00 | $4.00 | $3.80 | $2.00 |
| 4 | Excavation (203E10000) | CY | 159 | $55.00 | $30.00 | $54.25 | $32.00 |
| 5 | Embankment (203E20000) | CY | 60 | $55.00 | $20.00 | $89.26 | $40.00 |
| 6 | Subgrade compaction (204E10000) | SY | 797 | $7.00 | $1.00 | $3.23 | $4.50 |
| 7 | Reshaping under guardrail (209E15050) | MI | 0.10 | $2,500.00 | $2,500.00 | $5,000.00 | $2,500.00 |
| 8 | Guardrail, type MGS, as per plan (606E15051) | FT | 450 | $27.20 | $27.20 | $27.50 | $27.20 |
| 9 | MGS bridge terminal assembly, type 1, as per plan (606E35003) | EACH | 4 | $2,820.00 | $2,820.00 | $2,750.00 | $2,820.00 |
| 10 | Curb, type 4-C (609E24510) | FT | 105 | $55.00 | $92.00 | $86.69 | $60.00 |
| 11 | Monument assembly adjusted to grade (623E39500) | EACH | 2 | $1,250.00 | $410.00 | $1,000.00 | $500.00 |
| 12 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $2,500.00 | $1,850.00 | $2,500.00 | $2,400.00 |
| 13 | Post construction survey monument verification and report (623E51000) | LS | 1 | $2,500.00 | $1,850.00 | $2,500.00 | $2,400.00 |
| 14 | Tied concrete block mat with type 2 underlayment (601E21060) | SY | 198 | $65.00 | $95.00 | $97.08 | $105.00 |
| 15 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 3 | $250.00 | $240.00 | $403.21 | $300.00 |
| 16 | Concrete masonry (602E20000) | CY | 0.40 | $4,000.00 | $5,300.00 | $8,152.37 | $3,000.00 |
| 17 | Seeding and mulching (659E10000) | SY | 530 | $7.00 | $3.25 | $2.60 | $6.37 |
| 18 | Commercial fertilizer (659E20000) | TON | 0.07 | $1,500.00 | $800.00 | $800.00 | $1,052.00 |
| 19 | Water (659E35000) | MGAL | 2.86 | $10.00 | $0.10 | $0.10 | $1.00 |
| 20 | Erosion control (832E30000) | EACH | 10,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 21 | Aggregate drains (605E31100) | FT | 102.30 | $15.00 | $15.00 | $28.22 | $25.00 |
| 22 | 12" conduit, type B (611E04400) | FT | 56 | $135.00 | $135.00 | $99.66 | $95.00 |
| 23 | 12" conduit, type F (611E05200) | FT | 160 | $70.00 | $125.00 | $107.59 | $145.00 |
| 24 | Catch basin, no. 3A (611E98180) | EACH | 4 | $4,250.00 | $4,000.00 | $4,957.16 | $3,000.00 |
| 25 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 159 | $225.00 | $260.00 | $260.00 | $260.00 |
| 26 | Aggregate base (304E20000) | CY | 164 | $125.00 | $115.00 | $113.86 | $160.00 |
| 27 | Non-tracking tack coat (407E20000) | GAL | 99 | $5.00 | $1.00 | $1.00 | $1.00 |
| 28 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 46 | $405.00 | $450.00 | $450.00 | $450.00 |
| 29 | Structure grounding system (625E33000) | EACH | 1 | $15,000 | $32,760 | $32,760 | $36,500 |
| 30 | RPM (621E00100) | EACH | 3 | $700.00 | $980.00 | $325.00 | $700.00 |
| 31 | Raised pavement marker removed (621E54000) | EACH | 3 | $15.00 | $14.21 | $54.39 | $70.00 |
| 32 | Ground mounted support, no. 3 post (630E03100) | FT | 72 | $20.00 | $14.00 | $20.00 | $20.00 |
| 33 | Sign post reflector (630E08600) | EACH | 4 | $45.00 | $45.00 | $45.00 | $45.00 |
| 34 | Sign, flat sheet (630E80100) | SF | 9 | $25.00 | $40.00 | $25.00 | $25.00 |
| 35 | Removal of ground mounted sign and disposal (630E84900) | EACH | 3 | $22.72 | $25.00 | $25.00 | $15.00 |
| 36 | Removal of ground mounted sign and reerection (630E85100) | EACH | 6 | $97.73 | $75.00 | $150.00 | $75.00 |
| 37 | Removal of ground mounted post support and disposal (630E86002) | EACH | 6 | $22.73 | $25.00 | $25.00 | $20.00 |
| 38 | Edge line, 6", type 1 (642E00104) | MI | 0.18 | $5,000.00 | $5,000.00 | $7,917.00 | $5,000.00 |
| 39 | Center line, type 1 (642E00300) | MI | 0.09 | $5,000.00 | $7,500.00 | $15,883 | $5,000.00 |
| 40 | Pavement repair (253E02000) | CY | 20 | $320.00 | $420.00 | $528.34 | $420.00 |
| 41 | Tack coat (407E10000) | GAL | 20 | $10.00 | $1.00 | $1.00 | $1.00 |
| 42 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 10 | $400.00 | $500.00 | $500.00 | $500.00 |
| 43 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 64 | $140.00 | $125.00 | $126.91 | $95.00 |
| 44 | Replacement sign (614E12500) | EACH | 2 | $150.00 | $195.00 | $150.00 | $240.00 |
| 45 | Replacement drum (614E12600) | EACH | 20 | $45.00 | $50.00 | $50.00 | $55.00 |
| 46 | Portable changeable message sign, as per plan (614E18601) | SNMT | 10 | $750.00 | $1,250.00 | $995.00 | $1,011.00 |
| 47 | Compacted aggregate (617E10100) | CY | 50 | $90.00 | $70.00 | $48.90 | $135.00 |
| 48 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $250,000 | $200,000 | $245,504 | $265,000 |
| 49 | Approach slab removed (202E22900) | SY | 189 | $45.00 | $60.00 | $70.88 | $60.00 |
| 50 | Unclassified excavation (503E21300) | LS | 1 | $20,000 | $12,000 | $27,087 | $34,000 |
| 51 | Epoxy coated reinforcing steel, as per plan (509E10001) | LB | 92,049 | $1.50 | $1.60 | $1.70 | $1.52 |
| 52 | No. 4 deformed GFRP reinforcement (509E30020) | FT | 7,854 | $1.90 | $1.50 | $1.91 | $1.67 |
| 53 | Dowel holes with nonshrink, nonmetallic grout (510E10000) | EACH | 100 | $25.00 | $35.00 | $55.14 | $28.00 |
| 54 | Semi-integral diaphragm guide (511E33500) | EACH | 2 | $5,500.00 | $4,000.00 | $3,706.75 | $4,000.00 |
| 55 | Class QC2 concrete with QC/QA, bridge deck (511E34446) | CY | 305 | $1,225.00 | $1,150.00 | $1,028.81 | $1,300.00 |
| 56 | Class QC2 concrete with QC/QA, bridge deck (parapet) (511E34450) | CY | 82 | $825.00 | $875.00 | $626.54 | $1,000.00 |
| 57 | Class QC1 concrete, abutment (511E45710) | CY | 20 | $1,500.00 | $850.00 | $1,378.06 | $1,100.00 |
| 58 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 953 | $28.00 | $28.00 | $25.00 | $28.00 |
| 59 | Structural steel members, level UF, as per plan (513E10201) | LB | 2,375 | $30.00 | $21.75 | $24.58 | $28.00 |
| 60 | Welded stud shear connectors (513E20000) | EACH | 3,255 | $4.50 | $4.15 | $4.20 | $4.15 |
| 61 | Surface preparation of existing structural steel (514E00050) | SF | 12,722 | $11.00 | $8.50 | $11.00 | $11.00 |
| 62 | Field painting of existing structural steel, prime coat (514E00056) | SF | 12,722 | $2.50 | $5.00 | $2.50 | $2.50 |
| 63 | Field painting structural steel, intermediate coat (514E00060) | SF | 12,722 | $2.50 | $4.00 | $2.50 | $2.50 |
| 64 | Field painting structural steel, finish coat (514E00066) | SF | 12,722 | $2.50 | $4.00 | $2.50 | $2.50 |
| 65 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 20 | $90.00 | $125.00 | $90.00 | $90.00 |
| 66 | Final inspection repair (514E10000) | EACH | 11 | $250.00 | $200.00 | $454.55 | $250.00 |
| 67 | 1" preformed expansion joint filler (516E13600) | SF | 20 | $10.00 | $14.00 | $8.22 | $12.00 |
| 68 | Nylon reinforced neoprene sheeting (516E25000) | SF | 262 | $13.00 | $18.00 | $16.42 | $7.00 |
| 69 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44101) | EACH | 10 | $2,500.00 | $2,650.00 | $2,782.38 | $1,700.00 |
| 70 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44101) | EACH | 15 | $3,000.00 | $3,400.00 | $3,373.51 | $2,300.00 |
| 71 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $55,000 | $50,000 | $46,491 | $50,000 |
| 72 | Porous backfill with geotextile fabric (518E21230) | LS | 1 | $4,000.00 | $2,000.00 | $6,048.21 | $4,500.00 |
| 73 | Patching concrete structure, as per plan (519E11101) | SF | 10 | $350.00 | $175.00 | $411.38 | $260.00 |
| 74 | Reinforced concrete approach slabs with QC/QA (T=1 (526E25011) | SY | 190 | $450.00 | $375.00 | $693.97 | $400.00 |
| 75 | Type C installation, as per plan (526E90031) | FT | 68 | $425.00 | $325.00 | $496.36 | $500.00 |
| 76 | Vandal protection fence, 6' straight, coated fabric, as per plan (607E39901) | FT | 370 | $42.50 | $52.50 | $64.00 | $52.50 |
| 77 | Patching concrete structures with trowelable mortar (843E50000) | SF | 10 | $250.00 | $175.00 | $278.05 | $175.00 |
| 78 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $25,000 | $20,000 | $10,072 | $16,000 |
| 79 | Maintaining traffic (614E11000) | LS | 1 | $25,000 | $50,000 | $56,877 | $76,000 |
| 80 | Field office, type B (619E16010) | MNTH | 4 | $4,250.00 | $2,500.00 | $2,889.07 | $4,700.00 |
| 81 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $5,000.00 | $20,000 | $15,000 | $24,000 |
| 82 | Mobilization (624E10000) | LS | 1 | $95,000 | $90,000 | $103,719 | $100,000 |
| 100 | Field painting, misc.:coating of beam ends (514E27702) | EACH | 10 | $3,000.00 | $6,000.00 | $3,000.00 | $3,000.00 |
| 101 | Removal of existing coatings from concrete surfaces (512E74000) | SY | 300 | $30.00 | $35.00 | $22.00 | $30.00 |
| 102 | Structural steel, misc.: steel vandal protection F (513E90000) | LB | 200 | $16.00 | $16.00 | $2.50 | $16.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of July 30, 2026. Compiled by Mirage Metrics.