ODOT contract 260358 bid tabulation
WOO-IR 75-06.94 Slide Repair (SLIDE REPAIR). Let by Ohio DOT on August 27, 2026, WOO. 4 bids received; low bid $374,697 by Ebony Construction Co, -21% against the engineer's estimate of $475,000.
- Owner
- Ohio DOT
- Letting
- 27 AUG 2026
- Pay items
- 64
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ebony Construction Co | $374,697 | Low | -21% |
| 2 | Miller Bros Const Inc | $437,718 | +17% | -8.0% |
| 3 | Vernon Nagel Inc | $499,323 | +33% | +5.0% |
| 4 | Eclipse Co LLC | $561,362 | +50% | +18% |
Engineer's estimate: $475,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ebony Construction Co | 2. Miller Bros Const Inc | 3. Vernon Nagel Inc | 4. Eclipse Co LLC |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $6,500.00 | $14,000 | $4,500.00 | $3,000.00 |
| 2 | Pavement removed (202E23000) | SY | 204 | $3.00 | $5.00 | $18.00 | $9.01 |
| 3 | Pavement removed (202E23000) | SY | 292 | $22.00 | $25.00 | $48.00 | $21.05 |
| 4 | Curb removed (202E32000) | FT | 18 | $26.00 | $16.00 | $16.50 | $23.11 |
| 5 | Pipe removed, 24" and under (202E35100) | FT | 18 | $17.50 | $26.00 | $20.00 | $61.83 |
| 6 | Guardrail removed for reuse (202E38200) | FT | 362.50 | $5.00 | $3.20 | $3.56 | $3.20 |
| 7 | Anchor assembly removed for reuse (202E42806) | EACH | 1 | $220.00 | $195.00 | $216.93 | $195.00 |
| 8 | Bridge terminal assembly removed for reuse (202E47200) | EACH | 1 | $180.00 | $160.00 | $178.00 | $160.00 |
| 9 | Fence removed (202E75000) | FT | 90 | $5.00 | $5.00 | $4.00 | $5.00 |
| 10 | Removal misc.: precast outlet (202E98100) | EACH | 1 | $127.00 | $235.00 | $365.00 | $489.98 |
| 11 | Excavation (203E10000) | CY | 2,360 | $8.00 | $12.50 | $9.50 | $20.80 |
| 12 | Embankment (203E20000) | CY | 2,360 | $10.00 | $12.50 | $28.00 | $28.77 |
| 13 | Granular material, type B (203E35110) | CY | 94 | $57.50 | $75.00 | $46.00 | $86.26 |
| 14 | Granular material, type D (203E35130) | CY | 228 | $60.00 | $75.00 | $56.00 | $73.38 |
| 15 | Borrow, as per plan (203E40001) | CY | 156 | $22.00 | $15.00 | $50.00 | $49.31 |
| 16 | Subgrade compaction (204E10000) | SY | 463 | $3.00 | $5.50 | $1.00 | $10.51 |
| 17 | Excavation of subgrade (204E13000) | CY | 154 | $10.00 | $13.50 | $24.00 | $39.31 |
| 18 | Granular material, type C (204E30020) | CY | 154 | $46.50 | $80.00 | $76.00 | $67.62 |
| 19 | Geotextile fabric (204E50000) | SY | 463 | $2.00 | $2.80 | $3.50 | $5.01 |
| 20 | Guardrail rebuilt, type MGS (606E16050) | FT | 362.50 | $68.00 | $16.80 | $18.69 | $16.80 |
| 21 | Anchor assembly rebuilt, MGS type T (606E27910) | EACH | 1 | $1,000.00 | $1,420.00 | $1,579.71 | $1,420.00 |
| 22 | MGS bridge terminal assembly rebuilt, type 2 (606E35112) | EACH | 1 | $1,350.00 | $685.00 | $762.05 | $685.00 |
| 23 | Fence, type 47 (607E15000) | FT | 90 | $44.00 | $38.50 | $44.61 | $38.50 |
| 24 | Riprap, type D, as per plan (601E11001) | SY | 4 | $176.00 | $1,100.00 | $7,200.00 | $2,109.45 |
| 25 | Tied concrete block mat with type 2 underlayment (601E21060) | SY | 294 | $50.00 | $63.00 | $66.00 | $94.49 |
| 26 | Rock channel protection, type B with filter (601E32100) | CY | 51 | $127.00 | $190.00 | $158.00 | $136.05 |
| 27 | Topsoil furnished and placed (653E10000) | CY | 257 | $70.00 | $55.00 | $72.00 | $62.17 |
| 28 | Seeding and mulching (659E10000) | SY | 2,221 | $2.00 | $1.22 | $3.80 | $1.22 |
| 29 | Repair seeding and mulching (659E14000) | SY | 116 | $2.00 | $1.22 | $1.80 | $1.22 |
| 30 | Commercial fertilizer (659E20000) | TON | 0.42 | $1,000.00 | $400.00 | $850.00 | $400.00 |
| 31 | Water (659E35000) | MGAL | 12 | $2.00 | $0.01 | $1.00 | $0.10 |
| 32 | Erosion control (832E30000) | EACH | 10,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 33 | Concrete masonry (602E20000) | CY | 0.50 | $3,400.00 | $3,500.00 | $6,100.00 | $3,574.52 |
| 34 | 6" base pipe underdrains with geotextile fabric (605E14020) | FT | 346 | $13.00 | $22.00 | $18.00 | $14.06 |
| 35 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 20 | $12.00 | $80.00 | $82.00 | $16.54 |
| 36 | 15" conduit, type F (611E06700) | FT | 107 | $70.00 | $131.00 | $162.00 | $68.14 |
| 37 | Catch basin, no. 3 (611E98150) | EACH | 2 | $4,200.00 | $5,500.00 | $6,400.00 | $5,723.32 |
| 38 | Full depth pavement sawing (252E01500) | FT | 396 | $3.00 | $5.50 | $2.25 | $3.00 |
| 39 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 84 | $250.00 | $290.00 | $260.00 | $260.00 |
| 40 | Aggregate base (304E20000) | CY | 70 | $80.00 | $75.00 | $90.00 | $83.19 |
| 41 | Tack coat (407E10000) | GAL | 45 | $4.00 | $1.00 | $2.50 | $2.50 |
| 42 | Asphalt concrete surface course, 12.5 MM, type A (449) (442E22100) | CY | 25 | $430.00 | $425.00 | $600.00 | $600.00 |
| 43 | Combination curb and gutter, type 4 (609E23000) | FT | 371 | $67.00 | $57.50 | $58.00 | $135.00 |
| 44 | Combination curb and gutter, type 4, as per plan (609E23001) | FT | 11 | $175.00 | $135.00 | $150.00 | $250.00 |
| 45 | Longitudinal joint adhesive (875E10000) | LB | 1,386 | $0.75 | $1.50 | $0.65 | $2.50 |
| 46 | Barrier reflector, type 2, one-way (626E00110) | EACH | 5 | $34.00 | $14.00 | $15.57 | $14.00 |
| 47 | Edge line, 6", type 1 (642E00104) | MI | 0.03 | $28,250 | $25,000 | $25,000 | $17,970 |
| 48 | Lane line, 6", type 1 (642E00204) | MI | 0.64 | $2,825.00 | $2,500.00 | $2,500.00 | $7,715.00 |
| 49 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 32 | $125.00 | $100.00 | $75.00 | $130.00 |
| 50 | Increased barrier delineation (614E11630) | FT | 240 | $3.40 | $3.00 | $3.00 | $2.16 |
| 51 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 1 | $3,800.00 | $4,500.00 | $4,500.00 | $3,340.00 |
| 52 | Replacement sign (614E12500) | EACH | 3 | $280.00 | $250.00 | $250.00 | $239.36 |
| 53 | Replacement drum (614E12600) | EACH | 6 | $50.00 | $45.00 | $45.00 | $55.00 |
| 54 | Barrier reflector, type 1 (one-way) (614E13310) | EACH | 18 | $23.00 | $20.00 | $20.00 | $11.47 |
| 55 | Object marker, one way (614E13350) | EACH | 18 | $34.00 | $30.00 | $30.00 | $19.96 |
| 56 | Portable changeable message sign, as per plan (614E18601) | SNMT | 3 | $1,130.00 | $1,000.00 | $1,000.00 | $1,163.68 |
| 57 | Work zone edge line, class I, 6" (614E22010) | MI | 0.65 | $3,400.00 | $3,000.00 | $3,000.00 | $2,860.00 |
| 58 | Work zone dotted line, class I (614E24000) | FT | 840 | $1.15 | $1.00 | $1.00 | $1.35 |
| 59 | Water (616E10000) | MGAL | 130 | $11.50 | $10.00 | $2.26 | $1.00 |
| 60 | Portable barrier, unanchored (622E41100) | FT | 880 | $38.00 | $35.00 | $30.00 | $35.00 |
| 61 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $4,650.00 | $2,200.00 | $10,400 | $6,601.44 |
| 62 | Maintaining traffic (614E11000) | LS | 1 | $22,000 | $43,000 | $32,300 | $18,699 |
| 63 | Construction layout stakes and surveying (623E10000) | LS | 1 | $5,000.00 | $16,300 | $14,661 | $1,500.00 |
| 64 | Mobilization (624E10000) | LS | 1 | $20,000 | $21,800 | $25,200 | $84,032 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of August 27, 2026. Compiled by Mirage Metrics.