ODOT contract 260491 bid tabulation
BEL-SR 7-25.27 (SLIDE REPAIR). Let by Ohio DOT on November 12, 2026, BEL. 8 bids received; low bid $844,260 by Saorsa Construction Ohio, Inc., -2.2% against the engineer's estimate of $863,000.
- Owner
- Ohio DOT
- Letting
- 12 NOV 2026
- Pay items
- 35
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Saorsa Construction Ohio, Inc. | $844,260 | Low | -2.0% |
| 2 | Litman Excavating Inc | $882,383 | +5.0% | +2.0% |
| 3 | Marucci & Gaffney Excavating Co | $1,167,608 | +38% | +35% |
| 4 | S E T Inc | $1,179,153 | +40% | +37% |
| 5 | Eclipse Co LLC | $1,369,825 | +62% | +59% |
| 6 | Alan Stone Co Inc | $1,395,379 | +65% | +62% |
| 7 | Ohio-West Virginia Excavating Co | $1,457,256 | +73% | +69% |
| 8 | Shelly & Sands Inc | $1,613,738 | +91% | +87% |
Engineer's estimate: $863,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Saorsa Construction Ohio, Inc. | 2. Litman Excavating Inc | 3. Marucci & Gaffney Excavating Co | 4. S E T Inc | 5. Eclipse Co LLC | 6. Alan Stone Co Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $34,200 | $30,000 | $120,000 | $43,000 | $27,500 | $45,000 |
| 2 | Pipe removed, 24" and under (202E35100) | FT | 16 | $100.00 | $280.00 | $50.00 | $5.00 | $24.20 | $50.00 |
| 3 | Fence removed (202E75000) | FT | 1,270 | $2.20 | $4.00 | $4.00 | $2.42 | $2.40 | $4.00 |
| 4 | Excavation (203E10000) | CY | 6,235 | $10.00 | $12.00 | $23.90 | $18.00 | $17.35 | $15.00 |
| 5 | Excavation, as per plan (203E10001) | CY | 514 | $60.00 | $60.00 | $35.00 | $107.00 | $32.85 | $25.00 |
| 6 | Embankment (203E20000) | CY | 14,035 | $17.00 | $16.00 | $31.82 | $19.91 | $36.45 | $40.00 |
| 7 | Subgrade compaction (204E10000) | SY | 1,369 | $3.00 | $2.00 | $2.00 | $1.50 | $1.60 | $5.00 |
| 8 | Fence, type 47 (607E15000) | FT | 1,386 | $18.50 | $37.00 | $31.48 | $20.35 | $31.70 | $20.00 |
| 9 | Fence, type CLT (607E23000) | FT | 20 | $58.50 | $185.00 | $92.30 | $64.90 | $167.20 | $65.00 |
| 10 | Gate, type CLT (607E61200) | EACH | 1 | $1,685.00 | $8,000.00 | $3,120.00 | $1,853.50 | $6,000.00 | $1,900.00 |
| 11 | Paved gutter, type 1-2, as per plan (601E37501) | FT | 1,025 | $140.00 | $150.00 | $76.19 | $158.30 | $119.70 | $180.00 |
| 12 | Paved gutter, type 1-2, as per plan (601E37501) | FT | 122 | $450.00 | $170.00 | $351.37 | $637.62 | $172.40 | $310.00 |
| 13 | Soil analysis test (659E00100) | EACH | 2 | $150.00 | $800.00 | $5.00 | $1,000.00 | $135.00 | $150.00 |
| 14 | Topsoil (659E00300) | CY | 2,353 | $6.00 | $40.00 | $9.89 | $62.00 | $44.10 | $25.00 |
| 15 | Seeding and mulching (659E10000) | SY | 8,827 | $0.90 | $1.00 | $1.75 | $3.30 | $0.90 | $1.00 |
| 16 | Repair seeding and mulching (659E14000) | SY | 441 | $0.90 | $1.00 | $0.09 | $2.59 | $0.80 | $0.90 |
| 17 | Commercial fertilizer (659E20000) | TON | 1.19 | $1,250.00 | $1,200.00 | $400.00 | $1,512.50 | $939.00 | $1,100.00 |
| 18 | Lime (659E31000) | ACRE | 1.82 | $150.00 | $200.00 | $20.00 | $55.00 | $160.55 | $180.00 |
| 19 | Water (659E35000) | MGAL | 48 | $1.00 | $1.00 | $0.01 | $1.10 | $1.00 | $1.00 |
| 20 | Slope erosion protection (670E00500) | SY | 4,117 | $2.00 | $5.00 | $3.00 | $4.40 | $1.35 | $1.50 |
| 21 | Storm water pollution prevention plan (832E15000) | LS | 1 | $3,500.00 | $4,200.00 | $4,000.00 | $5,000.00 | $2,500.00 | $4,300.00 |
| 22 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $14,800 | $10,000 | $5,000.00 | $4,400.00 | $3,500.00 | $15,000 |
| 23 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $6,900.00 | $10,000 | $7,500.00 | $13,000 | $6,895.90 | $7,900.00 |
| 24 | Erosion control (832E30000) | EACH | 10,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 25 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $6,000.00 | $9,500.00 | $5,000.00 | $10,025 | $12,715 | $500.00 |
| 26 | 12" conduit, type C (611E04600) | FT | 16 | $500.00 | $200.00 | $300.00 | $167.09 | $145.55 | $410.00 |
| 27 | Catch basin, no. 5 (611E98300) | EACH | 1 | $8,650.00 | $6,000.00 | $6,000.00 | $4,730.00 | $6,113.65 | $12,000 |
| 28 | Drainage structure, misc.: mine discharge outlet (611E99920) | LS | 1 | $35,000 | $5,000.00 | $19,900 | $6,650.00 | $60,000 | $47,000 |
| 29 | Aggregate base (304E20000) | CY | 301 | $120.00 | $80.00 | $159.33 | $108.75 | $231.95 | $120.00 |
| 30 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $21,106 | $16,000 | $10,440 | $15,800 | $14,771 | $10,000 |
| 31 | Maintaining traffic (614E11000) | LS | 1 | $8,000.00 | $6,000.00 | $29,000 | $22,850 | $25,368 | $10,000 |
| 32 | Field office, type B (619E16010) | MNTH | 8 | $2,000.00 | $2,500.00 | $700.00 | $1,630.00 | $1,441.50 | $1,600.00 |
| 33 | Construction layout stakes and surveying (623E10000) | LS | 1 | $16,000 | $7,500.00 | $14,000 | $14,200 | $9,889.25 | $75,000 |
| 34 | Mobilization (624E10000) | LS | 1 | $10,000 | $10,000 | $30,000 | $46,550 | $135,000 | $87,000 |
| 100 | Excavation, as per plan (203E10001) | CY | 250 | $40.00 | $14.00 | $20.00 | $52.00 | $53.10 | $25.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of November 12, 2026. Compiled by Mirage Metrics.